Project Time Management
Project Time Management
Construction
Management
CONSTRUCTION MANAGEMENT 1
OVERVIEW:
PROJECT TIME
MANAGEMENT
2
25/12/2023
Project Time Management is a crucial aspect of project management that involves careful planning,
organizing, and controlling the duration of a project.
It is the process of creating a project schedule that outlines the tasks, milestones, and deadlines
necessary to complete a project on time.
Effective project time management requires a thorough understanding of the project scope, the available
resources, and the constraints that may impact the project's timeline.
This includes factors such as budget, team availability, and
stakeholder expectations. The topics we will cover are as follows:
By using project time management techniques such as critical 1) 1st Process: Define activities
path analysis, Gantt charts, and resource leveling, project 2) 2nd Process: Sequence Activities
managers can ensure that their projects are completed on 3) 3rd Process: Estimate Activity
time and within budget. Resources
4) 4th Process: Estimate Activity Duration
With proper project time management, teams can maximize
5) 5th Process: Develop Schedule
their productivity and efficiency, leading to successful
6) 6th Process: Control Schedule
project outcomes.
Estimate Activity
Duration
4
25/12/2023
Defines:
6
25/12/2023
L1OGICAL SEQUENCE
Note:
All arrows in a PDM network are
essentially dummy activities.
DURATION COMPRESSION 1
Crashing
Decreasing the total project duration
by adding resources to the schedule
without changing the sequence of
activities.
Analyze both schedule and cost to
obtain the greatest amount of
compression for the least
incremental cost.
8
25/12/2023
DURATION COMPRESSION II
Fast Tracking
In planning
10
25/12/2023
3 Types of
use to Define the sequence among the activities
Dependencies
1. Mandatory Dependencies
2. Discretionary Dependencies
3. External Dependencies
11
Dependencies Determination
There are two ways that are commonly used to draw a network diagram for a project:
1. Activity on Arrow (AOA) representation.
2. Activity on Node (AON) representation
12
25/12/2023
Dependencies Determination
13
Dependencies Determination
14
25/12/2023
Dependencies Determination
An Activity can only start when all Allows for Overlap/Lag Representation
its Predecessors have Finished
Allows only for the Finish to Start Allows for the Representation of the
Relationship 4 Types of Relationship
15
PRECEDENCE DIAGRAMMING
METHOD
16
25/12/2023
Activity on Node
Activity A Activity
Dependencies
Nodes B
Nodes
Predecessor
logically comes after another activity
17
18
25/12/2023
FINISH-to-FINISH (FF)
FINISH-to-START (FS)
Example: Example:
Floor tile installation cannot start until the Column formwork is required before
floor slab has finished concreting work for column can finish.
19
START-to-FINISH (SF)
START to START (SS)
20
25/12/2023
21
22
25/12/2023
LAGS:
Activity with
LAG TIME LAG
Means the successor activity cannot start right
after the end of the predecessor activity.
A waiting time in search of between activities, Lag Time is the delay between the first and
in other words, Lag time is the delay between second activity
the first and second activity.
Example:
Need to wait 7 days after pouring concrete
on beams before removal of beam soffits.
Lag Time = Positive Value
23
A
LF (Act. A) = LS (Act. B) – Lag Time
0 3 Activity B (Node): Lag Time = LS (Act. B) – LF (Act. A)
LS = 5 ; LF = 14
0 3 D=9
Lag Time = 5 – 3 = 2
Activity A (Node): 082 2 9
LS = 0 ; LF = 3 ACTIVITY B must Start 2 Days before ACTIVITY A
D=3 B has FINISHED.
5 14
5 14
24
25/12/2023
FORWARD PASS FORWARD PASS WITH LEAD TIME & LAG TIME
25
BACKWARD PASS BACKWARD PASS WITH LEAD TIME & LAG TIME
A BACKWARD PASS through the Network determines
the LATEST TIME each activity can START and FINISH For LEAD TIME (-) between two activities;
without delaying completion of the Project. LF of the Current Activity = LF of the
Previous Activity - (-Lead Time), and
It also determines the activities that can be
LS will still be equal to LF - Its DURATION.
DELAYED or not.
Begin from END EVENT and move towards the START
EVENT. For LAG TIME (+);
The LFT for the final activity = its EFT as LF of the Current Activity = LS of the
determined by the forward pass. Previous Activity - (Lag Time}
The LFT for an activity = earliest (or minimum) LST
of the activities directly following (succeeding) it.
The LST of an activity = its LFT – Duration required
to perform the current activity.
26
25/12/2023
PDM Layout
27
28
25/12/2023
FORWARD PASS
At Activity A:
EF = ES + D ; ES = 0+4 = 4 Use the
WP1 B 6 maximum EF of
Activity 1.2 At Activity B: preceding
WP1 D 8
WP1 A 4 4 10
ES = EF (preceding activity) = 4 activities
Activity 1.1 Activity 1.4
14 22
EF = ES + D ; EF = 4 + 6 = 10
0 4
WP1 C 10
Activity 1.3 At Activity C:
4 14 ES = EF (Act. A) ; ES = 4 = 4
EF = ES + D ; EF = 4 + 10 = 14
29
30
25/12/2023
6
WP1 B
ACTIVITY 1.2 must Start 4
Activity 1.2
10 WP1 D 8 Days before ACTIVITY 1.1
WP1 A 4 4
Activity 1.1 8 14 Activity 1.4 has FINISHED
4 14 22
0
0 14 22
4 WP1 C 10
Activity 1.3
4 14
4 14
LAG TIME=4
Critical PATH: A-C-D
31
32
25/12/2023
33
34
25/12/2023
By entering:
Schedule Activities
Durations
Resources
Resource Availabilities
Logical Relationships
35
PLANNING AND
SCHEDULING
36
25/12/2023
37
Experienced Project Managers unanimously PERT is a Technique used for Planning and
acknowledged that Time estimates were typically Controlling Time.
Over-optimistic for one or more principal reasons: A Development and Research Project Tool.
CLIENT DRIVEN The Client establishes the project Aligned Towards Events.
completion deadline before technical analysis,
consultation or project management feedback CPM is a Method used to Control Cost and Time
A Construction Period Tool
CONTRACTOR RESPONSE In order to be “Fully
Responsive” Contractors (Project Managers) accept Set According to Activities
the Client’s deadline to hopefully win the contract
38
25/12/2023
39
Activity – An element of work that is required by Gantt Bar & Milestone Charting
the project, uses resources, and takes time to Critical Path Method
complete. Maybe subdivided into smaller tasks Project Scheduling Software
Activity List – is a comprehensive list including These are recognized “Best Practices”
all scheduled activities required on the project. Tools advocated by PMI
40
25/12/2023
41
42
25/12/2023
EXAMPLE #01:
What is the duration in days to install 56 square meters of walls shuttering if:
a) Crew of 2 carpenters is used with output of 18.67 square meters/day
b) Productivity is measured as 0.086 Man-Hour/square meter. Number of carpenters=3, and
number of working hours/day = 8 hours
Solution:
b) Total man-hours needed = 56 sq.m x (0.086 MH/sq.m) = 4.81 man-hours (for 1-Carpenter)
Duration (for 3-Carpenters) = 4.81 MH x 3 = 14.43 MH
Duration using 3-Carpenters in Days:
Duration = 14.43 MH/ (8MH/Day) = 1.80 Days or 2 Days
43
EXAMPLE #02:
The construction of RC wall involves placing 660 cu.m concrete, 50 tons of steel, and 790 sq.m of formwork.
Calculate the duration of the activity using a balanced mix of the resources if:
A 6 man concrete gang can place 16 cu.m of concrete / day.
One steel fixer and one assistant can fix 0.5 ton of steel / day.
One carpenter and one assistant can fix and strike 16 sq.m/ day.
Solution:
a) Duration for concrete placing (6-man gang) c) Duration for Formworks (2-man gang)
Productivity Rate: 16 cu.m/ day Productivity Rate: 16 sq.m/ day
Duration = 660 cu.m / 16 cu.m/day = 41.25 days Duration = 790 sq.m/ 16 sq.m/day = 49.4 days
b) Duration for fixing steel ( 2-man gang) For a Balance use of Resources:
Productivity Rate: 0.50 ton/ day Use a 6-Man Crew/Gang composed of 1–Carpenter;
Duration = 50 tons / 0.50 ton/day = 100 days 2- Steel Fixers and 3-Assistants, i.e., 4-man gang for
steel fabrication and fixing, 2-man gang for formwork
For a Balance Mix: Use 4-man gang. fabrication & installation, and the whole 6-man gang
Duration = 50 tons / (0.50 ton/day x 2) = 50 days for concrete placement.
44
25/12/2023
PROJECT TIME
MANAGEMENT
45
1. ___________ accounts for all time, not just spent on the project.
2. What is the process of identifying and documenting specific actions to produce the
project deliverables?
3. What is the graphical tool used for scheduling activities that maps out project
development by creating a visual representation of critical paths and dependencies?
4. Estimating the number of work periods likely to be needed to complete each activity is called:
o Sequence of activities. o Estimate activity duration.
o Estimate activity resources o Define activities.
46
25/12/2023
Construct the PDM network for the activities listed in Table below.
Code Description
A Layout foundation
B Excavation Note:
C Obtain Concrete Materials A gang of steel-fixers is used to cut
D Place Concrete and bend reinforcement and
E Obtain Steel Reinforcement another gang is used for placing
F1 Cut and Bend Reinforcement (Part 1) reinforcement. The first part of
F2 Cut and Bend Reinforcement (Part 2) reinforcement can be placed
G1 Place Reinforcement (Part 1) during formwork erection while
G2 Place Reinforcement (Part 2) the second part should wait for
H Obtain Formwork completion of formwork erection.
I Erect Formwork
J Remove Formwork
K Clean Up
47