Value Engineering
Value Engineering
Value
Engineering
IN CONSTRUCTION PROJECTS
1
1
2
25/12/2023
VE IMPLEMENTATION IN
THE PHILIPPINES
In 2004- VE was promoted by World Bank to help the GOP in its effort
to keep under control unnecessary capital expenses and combat
corruption.
There were initially 26 professionals trained in VE conducted by World
Bank that founded the Philippine Association of Value Engineers
(PAVE).
In 2005, the use of VE became a GOP policy as a means of
rationalizing and achieving cost savings efficiently in infrastructure
investment and to combat corruption. The DPWH adopted VE as one
of the ways to cut costs and combat corruption.
The roll out program of a series of VE training and workshops for
Government Agencies, LGUs, and State Universities were conducted
by World Bank in 2005.
VE IMPLEMENTATION IN
THE PHILIPPINES
The GOP pursued the Project as part of its program to equip Philippine
professionals with a working knowledge of VE and to institutionalize VE
as a professional tool to achieve more economical and functional
infrastructure facilities.
June 2009 – NEDA published the Value Analysis Handbook funded and
assisted by AusAID under the Partnership for Economic Governance
Reform (PEGR). The Handbook presented the theory and techniques
applied in conducting a value analysis to a project for the government
to achieve value for money in major development projects, optimize
infrastructure expenditures, and increase the efficiency and
effectiveness of infrastructure projects.
4
25/12/2023
VE IMPLEMENTATION IN
THE PHILIPPINES
The Philippine Development Plan 2011-2016 and 2017-2022
strongly recommended the use of VE to government
infrastructure project.
March 2023, the DPWH Secretary issued Special 0rder 62, series
of 2023 for the creation of VE Committee to establish policies
and processes relative to the conduct of value engineering
studies and identification of DPWH projects that require value
engineering studies and share information with other
government agencies on Value Engineering benefits, and
experiences of the Department.
5 5
OVERVIEW
OF
VALUE ENGINEERING
VALUE ENGINEERING 6
6
25/12/2023
WHAT IS VALUE
ENGINEERING?
Value Engineering (VE), Value Analysis (VA) and Value
Management (VM) are all terms that can be used
interchangeably.
7 7
8
25/12/2023
Engineering, • Function, worth, and satisfaction are much more difficult to quantify.
“Value” refers to To determine the function, you need to ask questions like
the following:
importance, How long will those materials or equipment last?
VALUE ENGINEERING 10
10
25/12/2023
In the end,
functionality is
determined by HIGH COST/
LOW VALUE
HIGH COST/
HIGH VALUE
VALUE
11
11
The value of air travel indicates a LOW COST but HIGH VALUE travel.
VALUE ENGINEERING 12
12
25/12/2023
VALUE ENGINEERING 13
13
VALUE ENGINEERING 14
14
25/12/2023
When to use Value Engineering Consider the following major factors when
in Construction? determining the life cycle cost of an item:
Expected life of item
Construction (initial) cost
The VE process can be use in any phase of the
Maintenance and operation cost
project’s life cycle, i.e., at pre-construction,
Salvage value
construction, and post-construction phase.
Discount rate
The most cost-effective VE are those being
done during the pre-construction stage. In some cases, a higher initial cost of an item could
result in reduced life cycle costs.
In construction, the VE evaluation is focused on
three main criteria: Similarly, a lower initial cost may result in more
1. Cost reduction frequent maintenance and shorter life cycle than a
2. Added quality higher initial cost item.
3. Lifecycle/maintenance cost
VALUE ENGINEERING 15
15
VALUE ENGINEERING 16
16
25/12/2023
17
VALUE
ENGINEERING
PROCESS AND
METHODOLOGY
VALUE ENGINEERING 18
18
25/12/2023
VE Process in Typical
Construction Project:
Value Engineering (VE) is a process using multi-disciplined
teams to review projects and standards to identify high-cost
functions with improvement potential.
VALUE ENGINEERING 19
19
20
25/12/2023
21
22
22
25/12/2023
Great complexity in the Design — Generally, the more complex the design, the
more opportunity for improving value and performance.
Advancement in the state-of-the-art — Those aspects of design that go beyond
the state-of-the-art usually offer potential value analysis savings.
High degree of time compression in the design cycle — A project having an
accelerated design program usually contains elements of over design.
A component or material that is critical, exotic, hard-to-get, or expensive
Intricate shapes, deep excavations, high embankments, steep slopes, etc.
Components that appear to be difficult to construct
Overly long material haul — excessive borrow; excessive waste
Record seeking designs (longest span, highest piers, deepest cut, etc.)
VALUE ENGINEERING 23
23
VALUE ENGINEERING 24
24
25/12/2023
25
25
Functional Analysis
Function Analysis is a technique used to identify and understand the needs of the project,
product or service, (what does it do, what must it do).
The two words used to describe a function include an active verb and a measurable noun.
The measurable noun identifies something that can be described and quantified.
VALUE ENGINEERING 26
26
25/12/2023
Highway Ditch:
One of the functions of the ditch is to “channel water”.
The word 'channel' is an active verb.
The word 'water' is a measurable noun as the amount and type of "water“ can be
described and measured.
If the highway ditch is also needed to "support habitat" the area of focus might
change.
VALUE ENGINEERING 27
27
Pencil:
If the pencil does not “mark surface” it cannot achieve its basic purpose or function.
The verb “mark” is an active verb and the noun “surface” is measurable and can
be described.
VALUE ENGINEERING 28
28
25/12/2023
VALUE ENGINEERING 29
29
30
30
25/12/2023
31
32
32
25/12/2023
33
33
34
25/12/2023
35
36
25/12/2023
37
37
The following checklist will prepare Has the team double-checked your
the value analysis team for the recommendations, costs, and savings?
presentation:
Has the team prepared back-up
Is the need for a change clearly material for questions that may be
shown? asked?
Is the problem defined? Can use of vu-graph, opaque projector,
Is the proposal concise? flip charts or blackboard sell your
Are all the pertinent facts included? ideas?
Are money savings included? Has the team established a plan of
Is your value analysis workbook action that will assure implementation
complete and accurate? of a selected alternate?
Is your information complete? Are there pictures or sketches of
before-and-after conditions?
VALUE ENGINEERING 38
38
25/12/2023
VALUE ENGINEERING 39
39
Implementation Phase
1. Information Phase
The Executive Management Team has to select the 2. Functional Analysis Phase
value alternative to be implemented and directs the 3. Creative Phase
proponent agency's project team to proceed with the
next steps. 4. Evaluation Phase
It is not the VE Team to decide what options to be 5. Development Phase
implemented.
6. Presentation Phase
The VE method is used to evaluate and make
recommendations during construction phases. Implementation Phase
The cost-benefit of VE decreases as project
progresses, but on large projects it can be highly
beneficial to use.
40
40
25/12/2023
1.
Information
Phase Some organizations may elect to define
6.
2. the Job Plan as having more or less
Functional phases, but the overall methodology
Presentation
Analysis
Phase remains unchanged.
Phase
4. Evaluation
Phase
VALUE ENGINEERING 41
41
VALUE ENGINEERING 42
42
25/12/2023
VA Report Formats
VALUE ENGINEERING 43
43
V. Evaluation Phase
VA Report Formats
VALUE ENGINEERING 44
44
25/12/2023
VALUE ENGINEERING 45
45
VA Report Formats
VALUE ENGINEERING 46
46
25/12/2023
Wrapped Up:
VALUE ENGINEERING 47
47
VALUE ENGINEERING 48
48
25/12/2023
VALUE ENGINEERING 49
49
1. Advance Technology
2. Design Deficiency
3. Excessive Cost
4. Questioning Specs
5. Redesigning Cost
6. Change in User’s Need
7. Feedback from Users.
VALUE ENGINEERING 50
50
25/12/2023
The Average Percentage Cost Savings that Value Analysis study can
be generated in a Construction Project:
VALUE ENGINEERING 51
51
References:
https://www.valueanalysis.ca/va_in_depth
https://hermosillo.com/value-engineering-explained-in-160-characters-with-examples/
VALUE ENGINEERING 52
52
25/12/2023
VALUE
ENGINEERING
53
53
VALUE ENGINEERING 54
54
25/12/2023
VALUE ENGINEERING
8. The criteria for evaluating Value Engineering
in construction projects includes:
Please tick the circle with the appropriate answer: o Cost reduction
o Added quality.
6. In value engineering, “Worth” is value of: o Lifecycle/maintenance
o Service o All of the above
o Product
o Function 9. Is Value Engineering a technique often used
o System before a product has been fabricated?
o Yes
o No
7. Is value engineering and value analysis the same?
o Yes 10. Is Value analysis a technique used to analyze
o No an existing product?
o Yes
o No
VALUE ENGINEERING 55
55
VALUE ENGINEERING
11. In construction project, the most Cost- 12. In value engineering, the term value refers to:
Effective Value Engineering proposal is done
o Functions or utility
during:
Cost
o Pre-construction stage
o Construction stage o Cost
o Post construction stage Functions or utility
o All of the above
o Functions or utility x Cost
VALUE ENGINEERING 56
56
25/12/2023
Describe the VA process and identify the likely high-cost elements and systems to apply VE of the
proposed build so that Client/Stakeholders goals and expectations are meet or achieve.
VALUE ENGINEERING 57
57