សៀវភៅរបាយការណ៍កម្មសិក្សា I3GAR 22 23

This report summarizes the author's internship experience at BilGreat Construction Co., Ltd. The internship focused on gaining hands-on experience with installation of ceilings, painting of walls, laying tile floors, and applying bathroom waterproofing. During the internship, the author learned construction site safety protocols, organization of the construction company, and specific skills and processes for different construction tasks. The author hopes this report provides useful information and examples for other students.

Uploaded by

Ra Yut
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
429 views20 pages

សៀវភៅរបាយការណ៍កម្មសិក្សា I3GAR 22 23

This report summarizes the author's internship experience at BilGreat Construction Co., Ltd. The internship focused on gaining hands-on experience with installation of ceilings, painting of walls, laying tile floors, and applying bathroom waterproofing. During the internship, the author learned construction site safety protocols, organization of the construction company, and specific skills and processes for different construction tasks. The author hopes this report provides useful information and examples for other students.

Uploaded by

Ra Yut
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

ក្រសួងអប់រ ំ យុវជន និងរីឡា

វិទ្យាស្ថានបច្ចេរវិទ្យារម្ពជា

ម្ហាវិទ្យាល័យសំណង់

ច្េប៉ាតឺម្៉ាង់ ច្ទ្យពច្ោសលយស្ថាបតយរម្ម

ច្សៀវច្ៅរបយោរណ៍រម្មសរ
ិ ា

សញ្ញ
ា បក្តវិសរ
វ រឆ្ន ំទ្យី៣

ក្បធានបទ្យ : Site Architectural

ច្្មោះជាខ្មមរ : ច្ោរ ម៉ារ ចាន់សវ


ុ ណណធិនុន

ច្្មោះជាឡាត ំង : Mr. MAK CHANSOVANTHINUN

ក្រុម្ : I3-GAR

ឯរច្ទ្យស : វិសរ
វ រ-ស្ថាបតយរម្ម

សហក្ាសទ្យទ្យួលមុសក្តូវ : BilGreat Construction Co., Ltd

ឆ្ន ំសិរា៖ ២០២២~២០២៣


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

AKNOWLEDGEMENT
After completing the third year of Faculty of Architectural Engineering at Institute of
Technology of Cambodia (ITC) with highly motivated, hard-working and holistic
knowledge that can make me work confidently. My next journey will be internships related to
the major and improved my skills during vacation. After that, I have to bring back the reports
to the university about what I have learned. During this special occasion, I have learned many
new things including hard skill and soft skill, which I have never known before. Moreover, I
might not be able to complete this internship very well without help, support from many
people. Therefore, I would like to express my deep gratitude to those who participated in my
journey.

First of all, I want to thank my family from the bottom of my heart, who sent me to
school from a young age and still gave me the opportunity to go to university with full
financial support.

I would also like to extend my deepest gratitude to His Excellency Dr. OM ROMNY,
director of Institute of Technology of Cambodia for his authorization for doing internship in a
company. I am extremely grateful to Dr. SOY TY, deputy director of Institute of Technology
of Cambodia for his participation in signing on cooperation letter for submitting to the
company I have to complete mission. Furthermore, I am deeply indented to Prof. HASH
CHANLY and Mr. THAI SRUN, head and lecture of Department of Architecture for
valuable advices and knowledge you have educated me especially providing me their name to
complete my references in my curriculum vitae.

Additionally, I cannot begin to express my thanks to Mrs. LAI CHHOENG, deputy


project manager of construction site located at Beoung Kok on project Office Building, who
had given me permission to have an internship in her controlled site. Admittedly, special
thanks to my supervisor Mr. NGETH VISAL, site manager of construction site located
Beoung Kok on project Office Building, who is a respectful person according to his
important training skill, sharing knowledge and taking his value times nurtured me. Besides,
thanks should go to all employees of, technicians and manpower, especially Mr. SOR
BORA, senior trainee of NPIC-Vocational Training C1 C2 C3, which always offer me a
warm care and many useful advice.

MAK CHANSOVANTHINUN 1|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

ABSTRACT
Everyone who has been keeping up their higher education, even top rank or bottom
rank students in any major mostly might be accustomed to believe that all of you have
already been under a lot of pressure during your studies with unintelligible lessons along with
mountain of assignments as well as some research which the professor has instructed to do in
a short time. However, these are just a few things you had experienced in college compared

to life after you have graduated.

Most of the time we can't learn everything in college, but there are so many things we
never knew or learned. Therefore, the Cambodia Institute of Technology developed an
internship program for students so that these students could gain work experience in the
company they worked for and demonstrate what they learned from the internship by
submitting a written report to their department.

At the same time, I am also a junior in the Department of Architecture, Faculty of Civil
Engineering, Cambodia Institute of Technology, and I also have the responsibility of writing
a report. I was accepted for an internship at BilGreat Construction Co., Ltd., specializing in
finishing works. The training took place from September 1 to October 6, 2023. During this
time, I learned many new things. That said, in this report I will write about some work that I
have really only done consistently, including the installation of Ceiling, Painting of wall,
laying tile floor and Bathroom waterproof applying.

I sincerely hope that this report will be helpful to young people as an idea for their
research, as an example or as an article for students studying in this field.

MAK CHANSOVANTHINUN

MAK CHANSOVANTHINUN 2|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

TABLE OF CONTENTS

AKNOWLEDGEMENT..................................................................................... 1

ABSTRACT ......................................................................................................... 2

TABLE OF CONTENTS ................................................................................... 3

TABLE OF FIGURES ........................................................................................ 4

1. INTRODUCTION ........................................................................................... 5

2. COMPANY REPRESENTATIO .................................................................. 5

2.1. Organization Chart ............................................................................... 6

2.2. Construction Site Representation ........................................................ 6

3. SAFETY AND SECURITY ........................................................................... 7

3.1. Personal Security and Site Safety Rules .............................................. 7

3.2. Construction Security........................................................................... 8

4. INSTALLATION OF CEILLING .............................................................. 10

4.1 Tools and Material................................................................................ 10

4.2. Process of Installing the Ceiling ......................................................... 12

5. LAYING OF TILE FLOOR ........................................................................ 14

5.1. Materials and Tools ............................................................................. 14

5.2. Method of concrete mixture for tile laying........................................ 16

5.3. Process of tile laying ............................................................................ 17

6. CONCLUSION.............................................................................................. 19

MAK CHANSOVANTHINUN 3|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

TABLE OF FIGURES

Figure 1 1Address : #36, St. 352, Boeung Keng Kang1,...................6

Figure 2: Logo Company .....................................................................6


Figure 3: Organization Chart................................................................6
Figure 4: Figure4: Site Location ..........................................................7
Figure 5: Personal Protective Equipment (PPE)! .................................8
Figure 6: Site Safety Rules ...................................................................9
Figure 7: Materials .............................................................................11
Figure 8: Tools ...................................................................................11
Figure 9: Process of Installing the Ceiling .........................................13
Figure 10: Materials ...........................................................................15
Figure 11: Tools for Tile laying .........................................................16
Figure 12: Process of Tile laying .......................................................18

MAK CHANSOVANTHINUN 4|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

1. INTRODUCTION
For the last few decades, the world has been turned toward to a completely modern
world by technology as we see mostly in city. High rise buildings grow more and more every
year. Alongside with great changes, Cambodia which is a small, attractive and developing
country in Southeast Asia, has been going toward days by days. Especially, in construction
sector which is one of the most important sectors in Cambodia, has improved so well and so
far. Besides this great development, Cambodia has faced some critical problems. One of
those problems is the lack of professional engineers for working on construction sector. To be
an engineer, a student needs to spend at least four years in school to gain knowledge on
theoretical engineering. However, it is not enough for students to be able to work on the
construction site without any experiences. It’s only possible until they have experienced on
practical work in site or site office. By seeing this critical problem, construction company
such as BilGreat Construction Co., Ltd in short BGC has given opportunities to many
students to let them practice their theoretical knowledges about engineering in their work
areas and learn new lessons that mostly are being regardless in school. This is one of the most
effective ways which will help develop on human resource in the country. Inconclusion, as
we have seen, internship program has played on an essential role in developing by pushing
students to be an expert, experience and discover resourceful people along with education.

2. COMPANY REPRESENTATIO
BilGreat Construction Co., LTD is a reputable construction company operating in
Cambodia which has legally registered in Cambodia as engineering and construction
company since 2016. With a focus on delivering high-quality construction projects, this
company provides a range of services to clients including residential, commercial, and
industrial construction. In the recent year, BilGreat Construction Co., LTD has executive in
many projects such as high-rise building, Villa, Vocation House and others civil projects.
Moreover, BilGreat Construction is a leading architectural, civil engineering and general
contracting firm, offering an integrated, comprehensive planning, design and build solutions
for a broad range of construction and engineering projects worldwide.

BilGreat Construction Co., LTD located at Sangkat Boeng Keng Kang Muoy, Khan
Boeng Keng Kang, Phnom Penh.

MAK CHANSOVANTHINUN 5|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

Figure 1 1Address : #36, St. 352, Boeung Keng Kang1,

Chamkarmon, Phnom Penh,

Cambodia.

Figure 2: Logo Company

Figure2: Company Location

2.1. Organization Chart

Figure 3: Organization Chart

MAK CHANSOVANTHINUN 6|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

2.2. Construction Site Representation


This construction site is located at Street 169 (R1), Sangkat Srah Chak, Khan Daun
Penh, Phnom Penh. This site is the kind of Office Building which is a high rise building with
9 floors that has built for a company called Scheitic Co., Ltd.

Scheitic Co., Ltd is a wide range of integrated power electric companies, engages in
the provision of digital power and electrical equipment manufacturing & supply, power grid
and transmission, renewable and smart energy solution, technical advisory service and
construction engineering and management of high-power assets, notably Engineering,
Procurement, and Construction (EPC). They offer their customers with wide ranges of
encompass the design, engineering, manufacturing, installation, testing and commissioning of
electric power transmission lines, substations, and smart and proven technology for power
and renewable energy solutions and development of utility scale solar power plant.

Figure 4: Figure4: Site Location

3. SAFETY AND SECURITY


The first day that I interned at the construction site, the site manager taught me how to
keep ourselves safe and security rules in detail while working at the site.

3.1. Personal Security and Site Safety Rules


Personal security at a construction site is of utmost importance to ensure the safety
and well-being of workers.

MAK CHANSOVANTHINUN 7|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

Figure 5: Personal Protective Equipment (PPE)!

MAK CHANSOVANTHINUN 8|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

Figure 6: Site Safety Rules

MAK CHANSOVANTHINUN 9|Page


INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

3.2. Construction Security


Construction security refers to the measures taken to protect construction sites from
unauthorized access, theft, vandalism, and other potential risks. It is crucial to have adequate
security measures in place to ensure the safety of workers, protect valuable equipment and
materials, prevent costly delays, and maintain the integrity of the construction project.

Here are some key aspects of construction security that I found out at construction
where I interned:

1. Perimeter Fence

2. Access Control

3. Surveillance Systems

4. Lighting

5. Alarm Systems

6. Security Personnel

7. Securing Equipment and Materials

8. Emergency Preparedness

9. Security cameras

10. The building construction was surrounded by green safety net.

4. INSTALLATION OF CEILLING
4.1 Tools and Material
To install the suspended ceiling, we will need tools and material such as ceiling tiles,
suspension wires or channels, hanger wire, a tape measure, a level, wire cutters, a drill and
more tool or material.

MAK CHANSOVANTHINUN 10 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

1 1. Plasterboard 2. Mixing plaster 3. Expansion-bolt-steel

4. Fiberglass Tape 5. C- Line 6. Black Screw

Figure 7: Materials

1. Nylon string 2. Chalk line 3. Measure Tape 4. Bucket 5. Scaffolding

6. Scraper 7. Metal float 8. Roller brush 9. Electric drill 10. Electric mixer 11. laser
Figure 8: Tools

MAK CHANSOVANTHINUN 11 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

4.2. Process of Installing the Ceiling


Installing a suspended ceiling, also known as a drop ceiling or false ceiling, can be a bit
complex but manageable with the right guidance. Here's a general step-by-step guide on how
to install a suspension ceiling:

➢ Gather the necessary tools and materials: typically need ceiling tiles, suspension wires
or channels, hanger wire, a tape measure, a level, wire cutters, and a drill.

➢ Measure and mark the layout: Use a tape measure to determine the desired height of
the suspended ceiling. Mark reference lines on the walls to ensure a level installation.

➢ Install the perimeter wall angles: Attach metal wall angle brackets to the walls using
screws or nails. These will serve as the support for the outer edges of the ceiling tiles.

➢ Hang the main runners: Attach the main runners horizontally to the ceiling using
hanger wires. These main runners will run perpendicular to the ceiling joists and
provide support for the cross tees and ceiling tiles.

➢ Install cross tees: Attach cross tees to the main runners at predetermined intervals.
Most cross tees have a tab that snaps into slots on the main runners, creating a secure
connection.

➢ Cut and position the ceiling tiles: Measure and cut ceiling tiles to fit the remaining
spaces at the perimeter and around lights, vents, or other obstructions. Place the tiles
onto the grid, ensuring they are properly aligned.

➢ Install additional components: Install any additional components, such as light


fixtures, air vents, or access panels, based on the specific requirements of your project.

➢ Finishing touches: Once all the ceiling tiles are in place and properly aligned, ensure
that all connections are secure and visually inspect the installation for any gaps or
inconsistencies. Make any necessary adjustments.

MAK CHANSOVANTHINUN 12 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

Figure 9: Process of Installing the Ceiling

MAK CHANSOVANTHINUN 13 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

5. LAYING OF TILE FLOOR


5.1. Materials and Tools
For this Materials here refer to physical substance which are made from others raw
materials. In masonry works, materials that is obligatory are tile, sand, gravel, cement and
water. Normally, material characteristics are under controlled of QC.

➢ Sand is a raw material which we cannot lake of it in construction. Soft sand, also
known as builder sand, is used for bricklaying mortar, building foundations, for
paving slab, wall rendering. It is a smooth kind of sand and has cohesive properties.
The other type of sand is shape sand. It has a gritty feel to it. It is used in concrete and
can also be used for rendering wall and floors. Gravel is also a kind of needed
material. It has many sizes using in construction on demand. However, sand and
gravel before used, especially they need to pass fine and aggregate testing.

➢ Tiles are usually thin, square or rectangular coverings manufactured from hard-
wearing material such as ceramic, stone, metal, baked clay, or even glass. They are
generally fixed in place in an array to cover roofs, floors, walls, edges, or other
objects such as tabletops.

➢ Cement, In ancient time lime mortar is used for construction. However, since early
20th century Portland cement has been used the most commonly as binder in new
building.

➢ Water is one of the main admixtures in mortar mixing process, which is very
important in construction such as used for mixing of mortar, mixing of cement
concrete and also curing concrete. According to IS456:2000, water must be free from
salt, oils, acid and other substances that can cause iron corrosion. Also, impurities in
water can introduce unwanted silt and clay into concrete which reduce strength of
concrete by 25%.

MAK CHANSOVANTHINUN 14 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

Cement Tile

Sand Water

Figure 10: Materials

MAK CHANSOVANTHINUN 15 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

Tile suction cup holder Tile leveling system Head folding ruler

Mixer Tile drill locator Rubber hammer for tilling

Figure 11: Tools for Tile laying

5.2. Method of concrete mixture for tile laying


For the mixture of concrete for tile floor laying, we need to use 1 pack of cement with 6
buckets of sand and 1 to 2 buckets of water.

MAK CHANSOVANTHINUN 16 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

5.3. Process of tile laying


Laying tile floors involves several steps to ensure a successful installation. Here is a
general overview of the process:

➢ Prepare the Subfloor: The subfloor needs to be clean, dry, level, and free of any
cracks or imperfections. Remove any existing flooring materials and make any
necessary repairs before proceeding.

➢ Plan the Layout: Before starting the installation, plan the layout of the tiles to
determine the best arrangement. This involves measuring and marking the centerline
of the room and dry-fitting the tiles to ensure they fit properly.

➢ Mix the Mortar or Adhesive: Depending on the type of tiles you are using, mix mortar
(for ceramic or stone tiles) or adhesive (for vinyl or other types of tiles) according to
the manufacturer's instructions. Use a trowel to spread the mortar or adhesive on the
subfloor.

➢ Lay the Tiles: Start at the centerline and begin placing the tiles one by one, pressing
them firmly into the mortar or adhesive. Use spacers to maintain consistent spacing
between tiles. Work your way outwards, cutting tiles as needed to fit around
obstacles or along walls.

➢ Apply Grout: Once the tiles are all in place and the mortar or adhesive has cured
(usually 24-48 hours), it's time to apply grout. Mix the grout according to the
manufacturer's instructions and spread it over the tiles, using a grout float to ensure
proper coverage. Remove excess grout with a sponge and clean the tiles.

➢ Seal the Grout: To protect the grout from stains and moisture, apply a grout sealer
after it has fully cured. Follow the product instructions for application and drying
times.

MAK CHANSOVANTHINUN 17 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

Figure 12: Process of Tile laying

MAK CHANSOVANTHINUN 18 | P a g e
INSTITUTE OF TECHNOLOGY OF CAMBODIA I3-GAR REPORT YEAR 2022-2023

6. CONCLUSION
I completed my internship successfully; I can say that this importunity of internship
taught me many lessons and it is a good chance that improves myself and I learn from senior
architects and understand more about society. The internship is one of the beginnings of real
work for students to learn about the company and work. Since we all have already studied
about the theories in the classes so we cannot ignore this great opportunity of internship.
Indeed, we would get more than we expect because we all work with the professional
engineers who succeed in many projects. In the name of 13th generation of architectural
student at Institute of Technology of Cambodia, we would keep working hard and improve
ourselves to be a good student, be a responsible architect in the future to develop our
motherland to become glorious, and a good citizen for our society and for our country. This is
my great honor to be one of young Cambodian human resources to conserve and to develop
our country.

THANK YOU FOR YOUR PATIENCE!