Design Period
Design Period
supply scheme are designed to be sufficient in terms of its capacity (design capacity) is called design
period.
If the design period is taken as n years then the scheme should suffice the needs of the population at
the end of n years.
As seen above, the design period takes into consideration the water needs of the population after n
years.
Hence, knowing the future population becomes necessary in this case. Now population cannot be
just estimated randomly. A scientific approach is taken to forecast the population after completion of
the design period.
There are many methods to forecast the population. Certain criteria are to be studied and then the
most suitable method of population forecast is adopted.
Design period for water supply scheme is important owing to the following reason:
The water supply scheme includes the construction of huge structures like dams, reservoirs,
treatment works, conveyance systems, and so on. All these structures require a huge capital.
Another major limitation with these structures is that their capacities cannot be increased in
the future without sparing money.
If we talk about the water supply system, then it will include the laying of pipelines,
underground. To accommodate increased population, pipes of larger diameter will be
required.
Besides the cost of replacing the pipelines by larger ones, the whole roads have to be dug
disrupting traffic. Again, the water flow will change making the initial water head insufficient.
This will require the whole pumping system or the overhead water tank to be changed.
Hence, it is a complete waste of money and other resources to think of increasing the
capacity in just a few years of the establishment.
Now, this does not mean design period should be too long.
Design period should never be longer than the estimated useful life of the water supply
work.
As already said, the construction cost of these structures is too high and unnecessary
increase will lead to consumption of huge resources. Even then, these resources will be
wasted for life taken more than the life of the structure as the structure itself will fail.
Therefore, all the structures of the water supply scheme are designed by taking into consideration
the population of the town after a few years. ‘These few years’ is called design period.
Design period should be less than the useful life of the structure. Also, the chances of the
structure and its technique becoming obsolete should be considered. For instance, design
period of conveyance system should be decided based upon the service life of the material
of the pipe used.
The difficulty and consumption of resources for the future expansion or increase in capacities
is also considered. Higher design period is selected if the expansion is difficult and its cost is
high.
Availability of the investment funds for the water supply scheme is also take into account.
Lower funds leads to less design period.
If the rate of interest on money borrowed is less, then again higher design period can be
adopted.
If the rate of population increase of a community is higher, then higher design period can be
selected. In this consideration, the population shifts during the course of growth are also
considered.
However, the large projects with huge land acquisition requirements should be designed as per the
project requirements. Projects like tunnels, large aqueducts, etc. are such projects.
Pumping:
3 Pumping house 30 years
Electric motor & pumps 15 years
Key Points
Design Period:
The number of years the components of water supply scheme are designed to serve the
requirements in terms of capacity is called design period.
Shorter design period can lead to wastage in resources. It is not feasible to re-construct the
components of water supply scheme like dams, pipeline laying, intake works, treatment plants, and
such others.
On the other hand, a longer design period increases the cost drastically as all these construction fall
under large projects. This can lead to burden if enough funds are not available at low interest rates.
Besides this, it has to be noted, that the design period does not exceed the structure’s useful life
itself.