1 - Apqp Matrix

This document outlines an APQP chart with responsibility matrix for new product development. It details 26 key activities in a product development process broken into 3 phases: 1) Plan and define program, 2) Product design and development, and 3) Process design and development. For each activity, the document assigns responsibilities to various roles including operations, quality assurance, new product development, production, purchasing, and maintenance. Certain activities marked with ** are called out as especially important for ensuring product and process quality.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
202 views1 page

1 - Apqp Matrix

This document outlines an APQP chart with responsibility matrix for new product development. It details 26 key activities in a product development process broken into 3 phases: 1) Plan and define program, 2) Product design and development, and 3) Process design and development. For each activity, the document assigns responsibilities to various roles including operations, quality assurance, new product development, production, purchasing, and maintenance. Certain activities marked with ** are called out as especially important for ensuring product and process quality.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Doc. No.

: HOU/NPD/04

APQP CHART WITH RESPONSIBILTY MATRIX - MASTER Rev. No.: 00


Issue Date: 04.05.2022
Rev. Date: 25.05.2022

Purpose : To define the rank of new product for development & activities & responsibilities for product development , Engg change and any process change of existing items,Plant shifting /New plant, Plant lay out change.

Scope : This WI is applicable for development of new product,Engg change and any Process change of existing items,Plant shifting /New plant, Plant lay out change.
Method : Description,Rank of Development and responsibility is defined as below
EFF. DATE :- 02.02.2024
Development Responsibility
S.No Description Operation TOOL Remarks
A B C D E F G H I J MKT/ MD QA NPD PROD. PUR. MAINT HR
Head ROOM

PHASE - 1 (PLAN AND DEFINE PROGRAM)


1 Received RFQ(Part/Drawing/Sample/ECN From Customer √ √ √ √ √ P I S
2 Make And Update Enquiry Register √ √ √ √ √ P S
3 Making of CFT √ √ √ √ √ √ I S P
**4 Perform technical feasibility √ √ √ √ √ √ √ P I S
5 Component Drawing Review √ √ √ √ √ √ I S P

**6 Take clarification or inform to customer by mail/letter (if require ) √ √ √ √ √ √ √ I P S

7 Make product Pre-Feasibility Report √ √ √ √ √ √ I S P


8 Receipt LOI from customer √ √ √ √ √ √ P S I
9 Make Bill of Material & Supplier Selection ( If requiered) √ √ √ √ √ √ P S I
10 Cunduct SPEC review meeting with customer √ √ √ √ √ √ P
11 Make a List of SC/CC characteristics √ √ √ √ √ √ √ I S P
12 Make a quotation and submit it to customer √ √ √ √ √ √ S P P
**13 Prepare APQP Matrix / APQP plan √ √ √ √ √ I S P
14 Make a preliminary process flow diagramme √ √ √ √ √ √ I S P
PHASE - II (PRODUCT DESIGN & DEVELOPMENT)

15 Make resource plan against all requirement √ √ √ √ √ √ √ √ √ P S I

16 BOP Part Devlopment ( If Requiered ) √ √ √ √ √ √ √ √ √ S P

Past problem history study & Prepare PFMEA Defect √ √ √ √ √


**17 I S P
matrix.

18 Prepare prototype Control Plan √ √ √ √ √ √ √ √ √ I S P

**19 Make Tool & gauge manufacturing plan √ √ √ √ √ √ S I P

20 Make proto sample parts √ √ √ √ √ √ √ √ √ I S P

` Make proto parts inspection report √ √ √ √ √ √ √ √ √ S P I

Proto parts submission to customer and take folow up √ √ √ √ √


22 I S P
for approval
In case proto parts got reject then analysis them by √ √ √ √ √ √ √ √ √
23 I P S
PDCA cycle
PHASE-III (PROCESS DESIGN & DEVELOPMENT)

24 Make prelaunch process flow diagram √ √ √ √ √ √ √ √ I S P

**25 Prepare Process Failure Mode and Effect Analysis √ √ √ √ √ √ √ I S P

26 Prepare prelaunch Control Plan √ √ √ √ √ √ √ S P I

Prepare work instruction, process parameter sheet & √ √ √ √ √


27 P I S
Trainings etc.

After tool & gauge validation, perfrom production trial


**28 run T0, T1 etc (Using tooling & gauges) and maintain √ √ √ √ √ √ √ √ √ S P I
the record in NPD register

29 Check the parts & make sample inspection report √ √ √ √ √ P S I

Submission of sample to customer with required √ √ √ √ √


30 I S P
document

Sample approval report from customer (if required


31 take corrective action & review of change required √ √ √ √ √ I S P
documents)

32 Feedback Analysis / Corrective Action in PDCA √ √ √ √ √ √ √ √ √ I S P

33 Make a plan for MSA & SPC Study √ √ √ √ √ √ √ √ √ I S P

PHASE-IV (PRODUCT & PROCESS VALIDATION)

**34 MSA / Gauge R & R Study √ √ √ √ √ √ √ √ √ I S P S

Production Trial Run for Pilot lot & make a inspection


report and submit to customer (As agreed by √ √ √ √ √ √ √ √ √ √
**35 I P S
customer for considering pilot lot as a PPAP lot),
otherwise submit separate PPAP lot to customer.

**36 Process Capability Evaluation (Cp &Cpk Study) √ √ √ √ √ √ √ √ √ √ I P S S

Make a process & product audit report to ensure the


37 availability and adherence of all inputs whichever √ √ √ √ √ √ √ √ √ √ I P S
required
Finalize packing & logistic requirement and attach in √ √ √ √ √ √ √ √ √ √
38 I P S
PPAP
Make PPAP Documents in relevant formats and √ √ √ √ √ √ √ √ √ √
39 I S P
submit to customer
Receive PPAP approval & approved PSW or sample √ √ √ √ √ √ √ √ √ √
40 I S P
report from customer
PHASE-V (ASSESMENT & FEEDBACK)

41 Feedback Analysis / Corrective Action √ √ √ √ √ √ √ √ √ I S P

Reviewed all the required documents and implement on √ √ √ √ √ √ √ √ √


42 I S P
shop floor and make a summary of TGR & TGW.

43 Make Production Control Plan (If required) √ √ √ √ √ √ √ √ √ I S P

Make a APQP sign off sheet and handover the project to √ √ √ √ √ √ √ √ √ √


**44 I S P
production

45 Initial supply announcement & start the IPC √ √ √ √ √ √ √ √ √ √ I S P

Development Rank:
Rank Details
A New Product / Part / New Technology
B ECN in Existing Part Dimensionly
C Material Change in Existing Part
D Similier Parts
E Process Sequence/ Layout change
F Process Equipment change
G Relocation of plant
H Supplier change
I Off loaded Tools
J New Tool After Life Complete
For Responsibility
Legend Definition

Prime Responsibility
P
Co-Responsibility
S
Information
I

Prepared By : Approved By :

NOTE :- ** Marked are critical activity