Project Provisional Acceptance Hamusit
Project Provisional Acceptance Hamusit
Location: Hamusit Rural Kebele Town, Mecha Woreda, West Gojjam Zone of Amhara Region
Contractor: Yonas Girma Machinery Rent and General Water Construction PLC
This project provisional acceptance certificate after due notification to all concerned parties, we under
signed perceive through all the project components.
Page 1 of 8
Construction Generator and pump house with CI G-32 its wall and roof and
Electromechanical plants
1.1.5. Construction of Faucet
Construction 10 in Number Faucets
1.1.6. Construction of 20m3 Collection Chamber
Construction of 20m3 underground collection chamber
Gravity pipe line from spring capping to 20m3 collection chambers (two parallel 100mm
Dia. Medium class GI pipes )
1.1.7. Construction of Spring (Mushirit Spring)
Spring development at mushirit spring which is found North East of Rural Town u/s of Koga
Reservoir
2.1 Electromechanical Work
No Type of work Unit Qty Remark
1 ….. kva stand by generator No 1
2 ….. kw surface pump No 1
3 2.5” Water meter No 1
4 2.5” gate vale No 1
5 2.5” check valve No 1
6 Pressure gauge No 1
2.2. Preliminary Operation and Testing For Provisional Acceptance Data For Standby
Generator-set at collection chamber
2.2.1. General
Page 2 of 8
Water level and additives Control Fuse & Fuse
Rating………..
H = ….. m
At collection chamber
Panel ID Voltage
Function Current
Page 3 of 8
Manufacturer Power
Model. Frequency
Enclosure
External Body /
Internal Body /
Protection Indices /
Bonding of Doors /
Cable Gland/Brushes X
Drawing holders X
Company Label X
Paint Quality /
Panel Heating/Cooling/Lighting
Component Assembling
Page 4 of 8
Wiring Terminals Size, Position& Marking /
Incoming Section
Power distribution
Buttons Numbers
Wiring
Operation I
Page 5 of 8
Operation II
Phase To Earth X
Phase To Earth X
3. Having considered the above main remark preliminary operation & testing of the pumping station is
found to be satisfactory & provisionally accepted. All the above remarks to be rectified as soon as
possible before the final acceptance of the project works.
4. Provisional acceptance testing and operation
The Spring Development (Mushirit): Constructed according the design drawing & contract
agreement and properly working
Pipe laying works: Both pressure and distribution lines done according the design drawing
& contract agreement and properly working
60m3, 8m high concrete Service Reservoir: Constructed according to the design drawing
and contract agreement and properly working
20m3 Masonry Wall Collection Chamber : Constructed according to the design drawing and
contract agreement and properly working
Construction of generator and faucets : Constructed according to the design drawing and
contract agreement and properly working
Electromechanical work : installed according to the design drawing and contract agreement
and properly working
5. Remark
Page 6 of 8
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
__________________________________________________________________________
6. Conclusions
The date of the final acceptance will be one year after thorough investigations of works in all its parts
expecting invisible latent defects. We declare that all maintenance will be executed in accordance with
specifications and agreements in acceptable manner. We witness that,
The project is accomplished according to the design and the agreement as confirmed by the
relevant experts.
All the remarks have been provided to the contractor with full specifications for practical
purposes after due.
The provisional acceptance will be effective from the date of signing and sealed by all parties.
The Rural Kebele Town Water Board / New Committee / Town Administrator/ taking over
the responsibility to run the water supply service on wards today.
Page 7 of 8
7. Signing Parties and Witness
7.2. Client
Name Title Signature Date
1. ------------------------------ --------------------------- --------------- --------------
2. ------------------------------ --------------------------- --------------- --------------
7.3. Consultant
Name Title Signature Date
1. ------------------------------ --------------------------- --------------- --------------
2. ------------------------------ --------------------------- --------------- --------------
3. ------------------------------ --------------------------- --------------- --------------
7.4. Contractor
Name Title Signature Date
1. ------------------------------ --------------------------- --------------- ----------------
2. ------------------------------ --------------------------- --------------- ----------------
7.6. Witness
Name Title Signature Date
1. ------------------------------ --------------------------- --------------- --------------
2. ------------------------------ --------------------------- --------------- --------------
3. ------------------------------ --------------------------- --------------- --------------
4. ------------------------------ --------------------------- --------------- --------------
Page 8 of 8