1 5HKU Control 72ps Buiding Control Mechanism
1 5HKU Control 72ps Buiding Control Mechanism
• Registration of AP/RSE/RGE/RI/RC
• Approval and consent required to carry out
Building Control Mechanism building works
• Need for site supervision according to
supervision plans
• Need to appoint AP/RSE/RGE to design and
supervise works and hold them liable for non-
compliance
• Need to appoint RC for building and specialist
works and hold them liable for non-
compliance
1 2
3 4
5 6
Key Steps in Building Development Key Steps in Building Development
8. During construction, AP, RSE, RGE and 11.AP, RSE and RGE jointly endorse on
registered contractor provide required certificate that works have been erected in
supervision and inspections. accordance with approved plans and are
9. AP, RSE and RGE submit test, monitoring, structurally safe. The certificate is submitted
supervision reports and construction reports to BA for application of occupation permit.
to BA as required. 12.Building may be occupied when BA has
10.Upon completion of building works or street issued an occupation permit.
works, registered contractor certifies in
specified form that works have been erected
in accordance with provisions of BO.
7 8
9 10
11 12
Plot Ratio Gross Floor Area
• Plot Ratio obtained by dividing the gross floor Gross floor area:
area (GFA) of the building by the site area. • Area contained within outer surface of external
walls of building, measured at each floor.
• External finishes and curtain walls may be
disregarded in measurement.
• Some areas in building are exempted from
gross floor area calculation
Examples: main common entrance lobbies, fire
refuge areas, water tanks, transformer rooms.
13 14
15 16
17 18
Permitted SC and PR under Lease
• However, there may also be restrictions on
permitted plot ratio under lease of site
• In many cases, site coverage and plot ratio
permitted under lease is less than that
permitted under Buildings Ordinance.
19 20
21 22
23 24
Quality and Sustainable Building Design Quality and Sustainable Building Design
• Some design elements are to be considered in 1. Design for building separation to reduce
new building developments to improve air undesirable walling effect of “long buildings”.
ventilation, enhance the environmental quality 2. Lower part of a building to be set back to
at pedestrian level and reduce heat island reduce deep street canyon effect (deep valley
effect (situation where average temperature of effect) such that minimum air flow sectional
an area is higher than nearby rural areas). area is provided along street.
• These requirements may be imposed as 3. Building development in large site (site area
conditions in lease of new land sale sites or in of 1,000 m2 or more) to be provided with
planning approvals of Planning Board. greenery area (area planted with trees,
climbers, grasses etc.)
25 26
27 28
Compartmentation
• Compartmentation of building consists of subdividing it
into compartments, with fire resisting walls, floors or roofs
• Subdivision is made to limit spread of fire and restrict
damage to building and its contents
• Maximum compartment sizes are set up need to restrict
losses and ease fire fighting
29 30
Collapsed Floor Slab Sagged Roof Slab
31 32
33 34
Fire Test for Timber Door (1 hour FRR) Fire Test Set Up
35 36
2:37 from Start 5:37 from Start
37 38
39 40
41 42
1:00:05 from Start 1:09:57
43 44
45 46
Fire Test to Lift Door (Front) Fire Test to Lift Door (Rear)
47 48
Fire Glass Panel before Fire Test Fire Glass Panel
after Fire Test
49 50
51 52
53 54
S/K10/16
55 56
57 58
Zone 2 Area (Mid-level & central Kowloon) Zone 3 Area (Peak and Island South)
Max PR = 5 Max PR = 3
10
59 60
Town Planning Ordinance
• Town Planning Ordinance also imposes
restrictions to plot ratios lower than that
permitted by Buildings Ordinance to
residential buildings, according to density
zoning of the area.
• Example:
Maximum domestic plot ratio in Residential Zone
3 may be as low as 3.
61 62
63 64
65 66
Lease Conditions (3)
Lease Conditions (2)
• Some of the lease requirements are:
• For Special Conditions, they can broadly be classified Users
into 3 types. Total gross floor area
• Some of them, such as those on building covenant, Maximum site coverage
restriction on alienation and Deed of Mutual Covenant, Maximum number of storeys
are requirements imposed by LandsD. Design and disposition
Height
• Some others, such as those on rock crushing, illegal
Formation
dumping of wastes, damage to services, construction and
connection of drains, are requirements imposed by other Non-building area
Government Departments. Recreational facilities
Preservation of trees
• Lastly, there are Special Conditions which are of common
Landscaping
concerns to the Buildings Department (BD), Planning
Car parking, loading and unloading requirements
Department (PD) and Lands Department (LandsD).
Vehicular access
67 68
69 70
12
71 72
Structural Plans and Calculations Structural Plans and Calculations
• Structural details should include general • Structural calculations are grouped into 2 parts.
specification notes on structural materials, such as • The first part contains essential information on
concrete grades, characteristic strengths, the structural design, such as basic anatomy of
workmanship, corrosion protection, fire resistance stability of the foundation and structural system,
requirement. design method, assumptions, codes used, essential
• There should be adequate drawings consisting of information on the use of computer programs
floor plans, sections and elevations showing used, summary of wind, dead and impose load
layout, dimensions, levels and identification of resisting system, design details on members with
frames and members. significant instability implications including
• Notes on design imposed loads should be given transfer members, cantilever canopies and
on the corresponding floor plans. balconies.
73 74
75 76
77 78
79 80
81 82
83 84
Precast Concrete Construction (1) Precast Concrete Construction (2)
• Code of Practice for Precast Concrete Construction 2016 • Ensure durability:
gives recommendations and guidelines on the design, – Shape and size of precast unit (to have good drainage)
construction and quality control of structural and non-
– Concrete constituents
structural precast concrete elements
– Concrete cover
• Careful planning with regard to standardization,
buildability, voids and buried conduits, layout plan, – Environmental exposure
compatibility and demolition should be considered – Protection against fire
• Overall stability of whole structure must be checked. – Protection and maintenance
Temporary stability of structure as well as that of – Production
individual components during all stages of construction – Transportation, storage and installation
should also be considered. Precast building structures
– Design of joint details
should also be checked for disproportionate collapse as
result of progressive failure.
85 86
Precast Concrete
CoP for Structural Use of Steel
• Code of Practice for
Structural Use of Steel
2011 (the Steel Code)
gives recommendations
for design, construction
and quality control of steel
buildings and structures.
87 88
15
89 90
Welding Cladding (1)
• Cladding = facing or architectural decoration
additional to external walls of building
• Be provided with sufficient flexible joints
horizontally and vertically to cater for
differential movement
• Main defects in welds
Under-cutting • Cladding details be shown in general building
Incomplete penetration plans for approval
Lack of side wall fusion
Gas pockets • When installed above 6 m from street level,
Slag inclusions details of cladding and fixings be shown also
• Weld defects reduce strength of joint and initiate failure due to in structural plans for approval
brittle fracture or fatigue
91 92
93 94
Curtain Wall
Curtain Wall (2)
• Sequence and duration of cyclic test
where:
p1 = 0.5 p2
p2 = design wind pressure
p3 = 1.25 p2 16
95 96
Curtain Wall
Window and Window Wall (1)
• Structural submission required in case window or
window wall meets all of following conditions
Design wind pressure is 2.86 kPa or above
Form wholly or partly the external wall above ground floor
of building
Least dimension and area of opening of such window or
window wall > 1.8 m and 6 m2 respectively
• Heat soaking accelerates expulsion of nickel sulphide
inclusions in tempered glass. It is a means of
detecting presence of nickel sulphide in tempered
glass. Risk of spontaneous breakage is reduced
significantly for tempered glass treated with heat
soaking process
97 98
99 100
• https://www.youtube.com/watch?v=bcS5DRjnDvU
17
• https://www.youtube.com/watch?v=PFMlM8ppnHg
101 102
Impact Test
Fragmentation Test
103 104
Glass Reinforced Polyester Water Tanks (1) Glass Reinforced Polyester Water Tanks (2)
• Except for small GRP water tanks, dimensional and • Performance tests upon completion of GRP water
technical particulars are required to be included in the tank:
structural plans submitted for approval. Design Leakage tests – no visible sign of leakage after
calculations are also required to be submitted to assembled tank standing for at least 48 hours
substantiate the structural adequacy and integrity of Deflection – deflection of sides and bottom shall ≯
the water tank and the base support 15% of depth of tank and 10 mm respectively after
• Documents submitted prior to consent application: maintaining full water level for at least 2 hours
Test reports to substantiate mechanical properties of
fibre glass panel and its ability to withstand 6 times
hydrostatic pressure
Manufacturer’s quality control details
105 106
Case Study
18
http://dragageshk.com/projects-post/kai-tak-cruise-terminal-building/
107 108
109 110
Self
Shading Natural
Ventilation
Stack Effect
Recycling
Rainwater Recycling Photovoltaic Heat Exchange
111 112
Precast Construction
19
113 114
Construction Sequence
115 116
117 118
20
119 120
121 122
Box Beams
Construction
123 124
21
125 126
127 128
129 130
22
131 132
Façade Design
133 134
23