Model Design and Construcion Supervision TOR For URRAP Proejcts
Model Design and Construcion Supervision TOR For URRAP Proejcts
Terms of Reference
The average road density in Ethiopia is about 44.3km per 1000 square kilometres. This is
lower than the average road density of 54km per 1000 square kilometre for sub-Saharan
African countries. Similarly, the road density per 1000 population of 0.58km is also low. The
Rural Access Index, RAI, which measures the number of rural people who live within two
kilometres of an all-season road (typically equivalent to a walk of 20-25 minutes) as a
proportion of the total rural population, is on average 27% for the country.
Improved road access features strongly in the Government’s strategic Growth and
Transformation Plan (GTP), which is also directly linked to the Road Sector Development
Programme, RSDP-IV. The GTP (2010-2015) embodies targets to improve the condition,
integration and reach of the road network and includes an ambitious rural access expansion
programme.
The RSDP-IV includes a major investment in wereda and kebele access roads under the Universal
Rural Road Access Programme (URRAP). The objective of URRAP is to connect all kebeles by
roads of a standard that provides all-weather, year round access, meets the needs of the rural
communities, and is affordable and maintainable. URRAP is designed to improve rural livelihoods
by reducing isolation for rural populations and to provide year round access to their markets, social
and other services.
URRAP is an ambitious programme targeting the construction of some 45,800km of new all
weather access roads and upgrading of some 27,000 km existing kebele access roads to all weather
standards. The programme will maximise use of one of the country’s least expensive and most
abundant resources – labour – as well as naturally occurring road construction materials. Road
works implemented under the programme will be predominantly labour or intermediate equipment
based. Low cost solutions will be used to achieve all weather access.
In accordance with the above and under its overall road sector strategy, the FDRE,
represented by XXXX Wereda Administration, has allocated a budget to finance payments for
consultancy services for the design and supervision of prioritised kebele access roads.
Prepare tender documents and assist the wereda road office in procurement of the
works contract;
Contract management and supervision of the road construction operation by the
contractor.
The scope of services shall include all the services necessary to achieve the objectives
described in Item No. “2” above. In so doing the Consultant shall execute not less than the
tasks described below, with the following provisos:
1. If the Wereda Administration and Regional Road Authority require a “fast track”
approach to the project, the detailed design of the road will be carried out
simultaneously with the construction (i.e. Phase IV and Phase V will be combined).
Under these circumstances the contractor will be awarded a contract with a schedule of
rates and indicative quantities.
2. For DC2 roads it might be necessary to prepare conventional road design drawings and
details instead of strip maps / line drawings (to be agreed between the Consultant, RRA
and Wereda Road Office).
3. The scope of the social impact and economic analysis will depend on the road class.
The design of DC2 roads will require more data collection and analysis than the design
of DC1 roads. The scope of these activities will be agreed between the Consultant,
RRA and Wereda Road Office.
d) Environmental Survey: involving the scoping of the area of influence to establish the
relevant environmental characteristics of the route corridor, and identifying possible
changes due to the improvement of the road. Particular attention shall be given to the
impact of borrow and spoil areas, and likely changes in drainage patterns.
rock or other acceptable founding material on culverts, and two inspection pits on larger
structures.
It is expected that the road will largely follow the lie of the existing land. Significant
earthworks to improve the vertical or horizontal alignment are not envisaged. The Consultant
should consider alternative alignments within or close to the existing road corridor where this
may lead to improved geometric design or avoid problematic soils.
The Whole Life Cost shall include investment and maintenance costs specified in economic
price terms. The Consultant shall make a year-by-year determination of the costs of the
different options over the design life using discounted cash flow techniques to bring them all to
their present value. Residual values of an investment may be used when there is a good case
that the remaining economic life stretches beyond the end of the design life. The Consultant
shall discount costs and benefits from the investment to take into account the different
economic values of costs and benefits made at different times during the analysis period using
the planning discount rate for Ethiopia.
Initial estimates of construction costs may be derived from past experience of completed
projects. This should be compared with detailed investment cost estimates based on the
traditional bill of quantity approach together with estimates of unit rates for different
components of the works. The quantities of work should be estimated from the preliminary
engineering design of the road.
The value of land taken for the project should be incorporated into the costing of the project
even if payment for the land is not made. The value may be derived from a rental income or
the value of the lost agricultural production.
Location of new culverts and bridges, lined drains and other drainage structures
Pavement design and surfacing.
Conventional road design drawings may be required for DC2 roads. (It is to be agreed
with the RRA and Wereda Road office).
vi. Typical Cross Sections.
vii. Recommendations for Complimentary Interventions.
viii. Economic Evaluation with recommendations for least cost solution.
The detailed design of the pavement on each section of the road will be based on the results of
the soils and materials investigations and the traffic data collected during Phase II. The
pavement layers shall be derived from the design catalogues included in the ERA Low Volume
Roads Design manual.
The Consultant shall prepare detailed construction drawings for all culverts and bridges.
If provisional sums and a contingency are to be included, the amounts and percentages
proposed must be justified and indicated in the project cost estimate. Provisional sums may be
specified by the Employer, and these will be entered in the relevant bidding forms. These sums
shall be added into the Consultant’s estimates unaltered.
The Consultant shall prepare and submit a Book of Computations containing calculations and
summaries of quantities organized in pay item sequences. The book shall show the back up
calculations which substantiate the summary of quantities and the basis of estimating the
quantities. The Consultant shall produce and submit a confidential final Bill of Quantities and
estimated cost for the project.
3.21 Procurement
The Consultant shall assist Wereda in the procurement of a contractor to undertake the Works.
This shall include the technical and financial evaluation of bids and preparation of a Tender
Evaluation Report.
ii) optimize the use of available material resources to minimize costs to the Client, to
maximize the quality of the Works, to expedite construction and to optimize the
use of natural resources and ensure environmentally as well as socially sustainable
construction ; and
iii) Ensure that the road is constructed within the Contract Price and Time for
Completion allowed under the Contract or any agreed amendments thereto.
The Consultant shall fulfil all the duties and responsibilities as detailed under the Contract
for construction of the Works. The services consist of furnishing complete engineering
services in all respects, including all field and office work in strict accordance with the
highest standards of the civil engineering profession and with proper interpretation of the
duties and responsibilities of the Engineer/Employer’s Representative.
The scope of the Services shall include all the services necessary to achieve the objectives
described above and, in so doing, the Consultant shall expeditiously execute not less than
the following tasks:
i) The Consultant shall review the design, in relation to site conditions, during the
whole construction period and propose necessary changes to the Employer and
shall make necessary amendments.
ii) The Consultant shall make a survey of existing utility services and liaise closely
with authorities concerned on the proposed relocation of such services. The
Consultant shall prepare detailed plans and proposals for the relocation of these
services if affected by the proposed work. All official dealings with any service
agencies shall be done through the Employer.
iii) Issue the Contractor with all necessary copies of the Drawings, Technical
Specifications and Contract Documents or timely provide any such supplementary
information requested by the Contractor, necessary for the Contractor to carry
out the Works.
iv) With due diligence and efficiency supervise fully the construction of the works
which are to be executed in accordance with sound technical administration,
financial and economic practices. The Consultant shall perform all duties
associated with such tasks to ensure that only the best construction practice is
followed and that the final product is in all respects equal to that specified, at the
most economic cost and is executed in full compliance with the Specifications.
v) Check and verify on a regular basis the validity of all insurance/guarantees which
the Contractor is obliged to have in place.
vi) Check that the Contractor follows safe working practices in all operations and
immediately draw attention to any instances where this policy is not followed,
directing the Contractor to carry out all such works deemed necessary in case of
emergency/ affecting the safety of personnel, works and adjacent property.
Ensure that the minimum impediment is caused to the flow of traffic and that safe
acceptable detours are provided and maintained at all times.
vii) Organize the supervision of the works contract with proper allocation of
responsibilities to individual members of the supervision team and supervise their
work in order to ensure that it is effectively executed.
viii) Prepare any design changes as necessary or advisable to suit field conditions
including improvement of alignments during construction or which could result in
reduction of construction costs without sacrificing strength or quality of the
work. In particular supervise any ground investigations at bridge sites carried out
by the Contractor and review and modify the design of structures as necessary.
Prepare Instructions and Variation Orders (VO) as recommended or necessary
complete with the associated measurement and payment instructions. Issue such
Instructions and VOs to the Contractor in writing - whilst advising the Employer
of such Instructions and VOs and of the associated implications. (The Particular
Conditions of Contract may require the Employer’s approval prior to issue of
some instructions or variations).
ix) Routinely and at not more than quarterly intervals, advise the Employer of the
estimated total cost of completion of the Works.
x) The Consultant shall check the horizontal and vertical alignments set out by the
Contractor, as well as the setting out of cross-sections and reference control
points, prior to issuing approval to construct the Works. The Consultant may use
low-technology survey methods including Abney levels, Inclinometers, line levels,
ranging rods, profile boards, tape measures, conventional survey instruments,
etc;
xi) Carry out soils and materials investigations as necessary or advisable to minimize
overhaul, to optimize the use of available resources, to enhance economy etc.
xii) For all soils and materials proposed and used by the Contractor in the Works
conduct all necessary and advisable inspection, sampling, testing and analysis for
compliance with the Technical Specifications at source and in the laboratory and
approve or reject the use of the soils or materials proposed for or used in the
Works. Whenever necessary order removal and substitution of unsatisfactory
material and workmanship.
xiii) Routinely or as requested by the Contractor, inspect the Works both under
construction and completed, for compliance with the Specifications and the
agreed method of working, as a basis for payment. The Consultant should check
the tolerances achieved by the Contractor using conventional labour-based
equipment including camber boards, ditch templates, straight edges, string lines,
line levels ,ranging rods, profile boards, tape measures, conventional survey
instruments,etc .
xiv) Formally arrange joint inspections with the Contractor, in the presence of the
Employer, of completed sections of the Works for acceptance and/or
identification of defects, both at substantial completion and upon the expiry of the
defects liability period and issue the appropriate Certificate in accordance with the
Contract.
xv) Keep and maintain up-to-date detailed Daily Site Diary and detailed records
(making them available for inspection by the Employer or his representatives
when requested to do so) of all contractual correspondence and data; all work
stoppages or delays; accidents on Site; official visitors to Site; weather records;
all activities in progress at any time on site showing the start and end time and full
details of the resources employed per activity.
xvi) Keep and maintain detailed records (and make available for inspection) of the
Contractor’s equipment on Site and its precise date of arrival or removal from
Site, its date of manufacture, previous hours worked and condition, the date
commissioned to commence work, its availability, and utilization. Establish
equipment availability figures for each category of equipment.
xvii) Review the Contractor’s proposed work programs and associated work method
statements, resource analysis and requirements in relation to the required rate of
progress, and approve or reject the proposals accordingly. Identify any changes
or additional resources required. Make sure that the program submitted for the
execution of the works shall, in addition to the program for pure construction
activities, include an alleviation program for Site staff and Labour in respect of
Sexually Transmitted Diseases (STD) including HIV/AIDS, and any
Complimentary Interventions specified in the Contract.
xviii) Continuously monitor the Contractor’s progress against programme and his
method of working in respect of each and all construction activities. Advise the
Contractor when additional resources or revised methods of working or revised
programme of the works are deemed to be required.
xix) Review and familiarize themselves with the Client’s HIV/AIDS policy and
strategy, and follow up and report in the monthly reports on how the Contractor
is implementing the alleviation program for Site staff and labour in respect of
Sexually Transmitted Diseases (STD) including HIV/AIDS. In consultation with
the Client’s responsible environmental office, advise the contractors of new
developments and additional needs in respect of the STDs and HIV-AIDS as and
when they occur.
xxiii) Review and check the Contractor’s Payment Applications and, after verifying the
accuracy of the measurement and costing calculations and the sufficiency of the
supporting documentation, prepare and issue interim payment certificates for
processing by the Employer within 7 days of receiving such statement from the
Contractor. Advise the Employer on whether liquidated damages are due from
the Contractor. Prepare and issue final certificate.
xxiv) Monitor the payment process and alert the Employer when payment delays accrue
to a point when; (a) interest charges will become due and (b) the Employer will
be in Default for late payment.
xxv) Thoroughly review and analyze all the Contractor’s applications for extensions
of time or claims for additional payment and furnish the Employer with a detailed
analysis of such applications and recommended rulings and, subject to the
Employer’s approval (where necessary), advise the Contractor accordingly.
xxvi) Ensure that all materials, tools, plant, equipment, facilities, etc, which have to be
handed over to the Client after completion of the works are properly dismantled,
packed, stored and maintained until the official handing over to the Client.
Furthermore, the Consultant shall arrange for the handing over of these items to
take place as provided in the works contract.
xxvii) In the event of adjudication or arbitration, provide the necessary personnel and
expertise to advise and assist the Employer in any such process and prepare any
further analysis of the Contractors claims submissions as may be necessary to
assist the Employer in the presentation of his case.
xxviii) Provide on-the-job training to not more than 2 graduate civil engineers at a time
(furnished by the Employer) in the various aspects of construction supervision
and application of the Works Contract including, but not limited to, training in
respect of the various contractual issues which arise. Deploy the trainees as
practicable to supervision tasks on the Works.
xxx) Take digital colour progress photographs throughout the duration of the
Contract, keep and maintain an official photographic record (available for
inspection) of monthly progress at set locations and also of any construction
activity of technical or contractual interest at any time. Each photograph to be
captioned with: reference number, time, date, precise location, subject, and points
of particular note. All digital data should be stored on computer hard drive with
back-up.
xxxi) Submit progress reports (to fully acquaint the Client with all aspects likely to
affect the Technical and Financial implementation of the project), final reports and
records, and other hard outputs regarding construction progress and the status of
the Works Contract and the consulting services contract in accordance with
Section 10 herein.
xxxii) Review, approve and submit two full sets of as-built drawings within two months
of completion of the Works, including strip maps / line drawings detailing all
alignment and level information, pavement design, position and sizes of drainage
structures, services information, and structural drawings (including type and
positions of reinforcement).
xxxiii) Review and get familiar with the Client’s Environmental Procedures Manual, as
well as with Government of Ethiopia's policies on environmental aspects and
ensure proper implementation of the project as per these guidelines. Monitor the
implementation of environmental safeguards in collaboration with the Client’s
environmental officer.
Recommendations made to minimize potential adverse impacts during construction
include, but not limited to: -
- Minimize water and soil pollution.
- Ensure safety during construction by installing the appropriate signs and signals and
wearing of appropriate safety equipment.
- All borrow pit areas will be reclaimed as much as possible to their original state.
- Minimize the risk of soil erosion by grassing the embankments; stabilize with gabions
or stone pitching at bridges and at the inlets and outlets of culverts on sandy soils.
- Long traffic diversion roads shall be avoided so as to minimize the effect of dust on the
surrounding environment.
- Spillage of oil, fuel, and lubricants, shall be avoided. If spilt, they shall be collected and
disposed of in such a way as to not adversely affect the natural environment.
- Rock blasting near settlement areas shall be properly coordinated with the relevant
officers of the Employer’s Government Authorities in an attempt to minimize levels of
noise pollution and community interference.
- Camp sites will be located in an area so as to minimize disruption to local population,
fauna and flora and water courses; adequate drainage facilities and treatment of
sewerage and waste disposals will be provided. Camp area will be dismantled and
rehabilitated once construction is completed.
The Consultant shall also have full consultation with the Local Authorities during
implementation of above mitigation measures. In administering the contract
implementation, the Consultant is to ensure the minimization of the negative impact of
the project to the society of project influence area.
The Consultant shall be responsible for the professional quality, technical accuracy and coordination
of all surveys, designs, drawings, and specifications and other services furnished by the Consultant
under this contract.
The Consultant shall provide a Quality Control Plan that describes the procedures to be utilized to
verify, independently check, and review all design drawings, specifications and other documentation
prepared as a part of the contract. The Consultant shall describe how checking and review
processes are to be documented to verify that the required procedures were followed. The Quality
Control Plan may be one utilized by the Consultant as part of the firm’s normal operation or it may
be specifically designed for this project. The Consultant shall submit a Quality Control Plan for
approval within 21 (twenty one) calendar days of the written notice to commence. A marked up set
of prints from the Quality Control review will be submitted with each deliverables review. The
responsible Professional Engineer that performed the Quality Control review will sign a statement
certifying that the review was conducted.
The Consultant shall, without additional compensation, correct all errors or deficiencies in the
designs, drawings, specifications and/ or other services. The Consultant shall include a narrative
describing the general approach to QC during design, including but not necessarily limited to:
1. How the quality control function will be organized, including the names of quality control
managers, the name of personnel at various certification levels planned for the project;
2. A detailed summary of the Consultant’s proposed design Quality Management Plan.
The Consultant’s performance will be evaluated on the full service provided. If the service does
not meet the expected professional standards, the Consultant may be overlooked for future bid
invitations. The Consultant will be informed of the findings of this evaluation by the Client.
4 Deliverables
The deliverables to be provided by the Consultant shall be of a high standard, presented in the
appropriate format, neatly bound and clearly labelled with the project title, procurement
number and date. The details of the various reports and documents to be submitted and the
numbers of copies required are given in Section 10 of the TOR.
The Consultant shall provide competent personnel for the services, who shall be managed by
the Team Leader and who will represent the Consultant in performing the services. The
minimum requirements for the team are as follows:
A. Key Personnel
1. Rural Roads Design and Supervision Engineer/ Team Leader
B.Sc. Degree in Civil Engineering with minimum of 8 years experience in road projects.
Five years experience as a Rural Roads Engineer of which two years shall have been
experience as a Team Leader in road design projects.
One year experience in site supervision of rural road works using labour based methods
and intermediate equipment.
Permanent employee of the firm/associate firm for the last one (1) year or extended
working relationship with the firm/associate firm for the last two (2) year.
2. Geotechnical/Materials Engineer
A minimum of B.Sc. in Geology or Civil Engineering or Geotechnical Engineering with
minimum of 5 years experience in ground investigation, testing and interpretation of
results for road and bridge projects.
Two years of experience in supervision of ground investigation, testing and
interpretation of results for the design of structural foundations.
Permanent employee of the firm/associate firm for the last one (1) year or extended
working relationship with the firm/associate firm for the last two (2) years.
3. Hydrologist
A minimum of B.Sc. in Civil Engineering or equivalent with minimum of 5 years
experience in hydrological investigations and drainage design for road and bridge
projects.
Permanent employee of the firm/associate firm for the last one (1) year or extended
working relationship with the firm/associate firm for the last two (2) years.
4. Contracts Engineer
BSc. degree in civil engineering or in related field with minimum of 5 years of
experience in road projects.
Experience as a specialist on contracts and tender document preparation and cost
estimation on at least three road projects.
Experience with basic economic analysis including the calculation of discounted cash
flows would be an advantage.
Permanent employee of the firm/associate firm for the last one (1) year or extended
working relationship with the firm/associate firm for the last two (2) years.
5. Inspector of Works
BSc degree in civil engineering or related fields from a Technical College or University
with zero years’ experience
OR
Diploma in related fields from a Technical College or University with a minimum of three
(3) years experience as an Inspector on rural roads construction using labour based
methods
OR
A certificate in related fields from Technical school with a minimum of five (5) years
experience as an Inspector on rural roads construction using labour based methods.
Inspection of road works includes ensuring compliance with the Standards and
Specifications of the contract for the:
Construction/improvement of sub grades and fill
Construction of drainage works
Construction of pavement layers and wearing course
Construction of structures and other ancillary works
Construction of all temporary works.
Note:
- At least one member of the team must be able to demonstrate competence in assessing
social and environmental impacts of rural roads improvement programmes.
- Only Personnel having the minimum educational qualification set will be considered
for evaluation.
- Personnel who scored below 60%, of the allotted points for their respective criteria,
will be replaced by a better-qualified one, prior to concluding the Contract signing.
- The induction of any staff including the intermittent ones shall be subject to the Client
prior approval.
- CVs of the support staff shall be submitted when and as required during the
implementation period of the project.
6 Service Duration
The duration of the Services is as stated in Part 3 Section 8 Special Condition of Contract
under clause 13.1.
The Client will provide liaison with other departments of the administration in order to
introduce the Consultant and to provide support in specific areas, in particular environmental
impacts, community liaison and the design of Complimentary Interventions. The Consultant
shall be fully responsible for collection of data and information from these departments.
necessary for the complete execution of the services. The costs of provision of each and all the
aforesaid shall be detailed in the Consultant’s financial proposal.
The Consultant shall attend monthly joint/progress meetings with the Client and shall take
minutes of those meetings and submit the minutes to the Client.
The Consultant is also responsible for providing any required assistance to the Client for
problems that arise from the design document and survey benchmarks/data during pre-
construction and construction periods. He shall also make available all relevant personnel for
specific presentations at any time when called upon by the Client, whether or not the
Consultant is normally locally resident. The Consultant shall make provision for any costs
associated with these requirements.
10 Reporting Requirements
The Consultant shall prepare and submit the following documents for the assignment. A brief
description of the contents of these reports is presented as follows:
10.5 Drawings
The Consultant shall prepare and submit tender drawings which shall be the final construction
drawings. These drawings shall include, but not be limited to:
The layout plan for the road based on the GPS survey.
Strip Maps / Line Drawings of the road (one sheet per kilometre of road).
Typical cross-sections
Drawings and details for culverts, drifts and bridges.
ANNEX A
PROPOSED POSITION:
NAME OF FIRM:
NAME OF STAFF:
I, the under signed staff, confirm that I am interested and will be available for the proposed
position mentioned here above for the Consultancy services for Identification, Design and
Supervision of a Kebele Access Road in the XXXX Wereda to work with ________________
[name of consultant] in the above mentioned position. I also declare that I have submitted my
CV and signed a declaration of interest not for more than two consultants including this
consultant in this particular project. I understand that, I will take full individual responsibility, if
I am found signing a declaration of interest for more than two consultants in this particular
project.
________________________________ _____________
Full name and signature of Staff member Day/Month/Year
______________________________ _____________
Full name and signature of authorized representative of the firm Day/Month/Year