Busbar Specifications
Busbar Specifications
SECTION 262500
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Definitions 2
1.4 Submittals 2
1.5 Quality Assurance 3
1.6 Project Conditions 3
1.7 Coordination 3
PART 2 PRODUCTS 3
2.1 Busway, General 3
2.2 Busway (Up To 5000a) 4
2.3 Supports And Accessories 4
2.4 Fire Stopping: 5
PART 3 EXECUTION 5
3.1 Installation 5
3.2 Connections 6
3.3 Field Quality Control 6
3.4 Adjusting 6
3.5 Cleaning 6
3.6 Protection 6
PART 1 GENERAL
1.2 SUMMARY
1. Feeder-bus assemblies.
2. Plug-in bus assemblies.
3. Bus plug-in devices.
1.3 DEFINITIONS
1.4 SUBMITTALS
A. General: Submit the following according to the Conditions of the Contract and
Division 1 specifications Sections.
A. Field Measurements: Don’t take measures from electrical drawings. Verify existing
dimensions by field measurements. Verify clearances and locate obstructions within
manufacturing and installation tolerances of bus way.
1.7 COORDINATION
A. Coordinate layout and installation of enclosed bus assemblies and suspension system
with other construction that penetrates ceilings or floors or is supported by them,
including light fixtures, HVAC equipment, fire-suppression system, and partition
assemblies.
B. Coordinate size and location of concrete curbs around openings for vertical bus.
PART 2 PRODUCTS
A. Bus way shall be indoor feeder type for non tapped straight runs and direct
connections between equipment, as applicable, complete with manufacturer's
recommended fittings and accessories where indicated and as required for a complete,
functioning and safe installation.
B. Bus way is to include bus bars, electrical insulators, enclosures, switchboard flange,
elbows, offsets, cable tap boxes, transformer flange connections with flexible copper
braid link, generator flange connection with flexible copper braid link and vibration
absorber,, power take-off sections, expansion joints, end closures, supports, and other
components and accessories needed to form complete systems.
C. Ratings: three phase with voltage and current ratings and requirements for neutral and
ground conductors as indicated and specified. Short circuit ratings of bus bars shall be
in excess of those indicated for each location.
D. Busway Conductor Material: hard drawn Copper with not less than 98 percent
conductivity.
F. Hot Spot Temperature Rise: not in excess of 55 deg C above an ambient temperature
of 40 deg C at any point in the bus bar when bus bar is operated at rated load current
and system frequency.
A. Type: Indoor, 600/1000 V grade, 3-phase, 5 or 4 wire with fully sized neutral and half
size earth bar, insulated, totally enclosed, non-ventilated and of compact design to
provide degree of protection of IP54 to IEC 60529, with appropriate ratings at site
maximum ambient temperature conditions. Bus bar is to comply with approved
standards. Short-circuit capacity is to be at least equal to value at main protective
device, for 1 second. Where indoor bus way is partially running through outdoor / wet
areas, these portions are to be IP66 rated.
C. Conductor joints for one modular length to the next shall are to be arranged in joint
stacks incorporating bus bar conductors, and each joint stack shall is to be arranged for
tightening with a single bolt. Joint design shall is to be such that any length or fitting
of a run may be removed without disturbing the connecting lengths.
D. Reactance: Bus bar is to be specially built and assembled to provide low reactance.
E. Accessories: Bus bar is to be complete with necessary factory made adaptor boxes,
junction boxes, bends, expansion connections, fittings, fire barriers etc. as may be
required to provide complete system between terminal points indicated on the
Drawings. Fixing and mounting materials are to be galvanized steel. For vertically
mounted bus bars, spring suspension type hangers are to be used for equalizing weight
of trunking between all supports.
G. Bulbar is to be ordered from the country of origin with proper lengths and shapes.
Bulbar cutting on site is not acceptable.
A. Spring Mounted Vertical Riser Supports: adjustable for leveling and spring tension
and arranged to permit relative movement between floor and bus bar.
C. Expansion Section: capacity and conductor provisions same as adjacent bus bar
section. Arranged to absorb expansion and contraction of bus bars and housing.
A. General: materials approved for fire ratings consistent with penetrated barriers.
B. Wall and Floor Flanges: sheet steel, 2 mm (12-gage) minimum thickness close fitting
to bus bar arranged to close the wall or floor opening at the bus bar penetration.
PART 3 EXECUTION
3.1 INSTALLATION
A. The bus assemblies shall be installed so that the maximum unsupported span does not
exceed 3 meters. Any fixings used shall be of mild steel angle or channel finished to
the same standard as the trunking and shall not cause any long term corrosion or
electrolytic action.
B. Where any cutting or damage is caused during erection, the burrs and rough edges
shall be removed and the finish made good. Any corrosion, which has occurred, shall
be removed and the area treated with a rust-proof agent. The finish shall then be made
good by the application of either a zinc rich epoxy primer or equal alternative, and for
Class 2 finishes shall be followed by coat of color matching paint.
C. Runs of enclosure shall not be used to support other equipment or services nor shall
any cables be installed in the enclosure unless the trunking is specially designed for
these purposes.
D. Where bus assemblies enclosure passes through fire barriers, walls, floors and
ceilings, fire resting barriers shall be fitted in the trunking and the hole surrounding
the trunking shall be made good to the full thickness with resisting material to provide
fire resistance equal to that of the structure through which the trunking passes.
E. In vertical runs of assemblies thrust supports shall be fitted either at each floor level or
at 3 meters spacing's whichever is of lesser dimensions.
F. Incoming cables and all outlines shall be supported to avoid appreciable mechanical
loads being imposed on the busbar trunking.
A. Prior to installing, test for electrical continuity of bonding, and earthing connections is
to demonstrate compliance with grounding requirements.
3.4 ADJUSTING
A. Align bus bar runs vertically and horizontally to eliminate sags and twists. Provide
support stiffeners at locations where indicated and where there is excessive
movement.
B. Check bus plug circuit breaker trip settings, fuse ratings, and starter overload elements
against connected loads and revise as required to conform to recommended values.
3.5 CLEANING
A. Upon completion of installation of bus bars, remove burrs, dirt, and construction
debris and repair damaged finish including chips, scratches and abrasions.
C. Paint Finish: repair damage using matching touch-up coating recommended by the
manufacturer.
3.6 PROTECTION
A. Provide final protection to ensure that moisture does not enter bus assembly.
B. Infrared Scanning: Two months after Substantial Completion perform an infrared scan
of bus assembly including joints and plug-in units.