Risk Assessment Matrix
Risk Assessment Matrix
A risk assessment matrix is a project management tool that allows a single page – quick view of
the probable risks evaluated in terms of the likelihood or probability of the risk and the severity of
the consequences.
A risk assessment matrix is easier to make, since most of the information needed can be easily
extracted from the risk assessment forms. It is made in the form of a simple table where the risks
are grouped based on their likelihood and the extent of damages or the kind of consequences that
the risks can result in.
CONSEQUENCE
LIKELIHOOD Insignificant (1) Minor (2) Moderate (3) Major (4) Extreme (5)
Rare (1) Low Low Low Low Low
Unlikely (2) Low Low Low Medium Medium
Possible (3) Low Low Medium Medium Medium
Likely (4) Low Medium Medium High High
Almost certain (5) Low Medium Medium High Extreme
Making a risk management matrix is the second step in the process of risk management, and it
follows the first step of filling up a risk assessment form to determine the potential risks.
The preparation of the assessment form is a more elaborate task and involves determining risks,
gathering risk data, determining the probability and the impact levels of the risks, understanding
consequences, assigning priorities and developing risk prevention strategies. On the other hand, a
risk assessment matrix just provides the project team with a quick view of the risks and the
priority with which each of these risks needs to be handled.
How to Place Risks in the Matrix
As mentioned above, in a risk assessment matrix, risks are placed on the matrix based on two
criteria:
1. Likelihood: the probability of a risk
2. Consequences: the severity of the impact or the extent of damage caused by the risk.
Likelihood of Occurrence
Based on the likelihood of the occurrence of a risk the risks can be classified under one of the five
categories:
1. Definite: A risk that is almost certain to show-up during project execution. If you’re looking
at percentages a risk that is more than 80% likely to cause problems will fall under this
category.
2. Likely: Risks that have 60-80% chances of occurrence can be grouped as likely.
3. Occasional: Risks which have a near 50/50 probability of occurrence.
4. Seldom: Risks that have a low probability of occurrence but still can not be ruled out
completely.
5. Unlikely: Rare and exceptional risks which have a less than 10% chance of occurrence.
The following can be used as a guide for determining likelihood. However this tool has limitations
as likelihood and frequency of events tend to vary between disciplines and functional areas.
Likelihood table
Consequences
The consequences of a risk can again be ranked and classified into one of the five categories,
based on how severe the damage can be.
1. Insignificant: Risks that will cause a near negligible amount of damage to the overall
progress of the project.
2. Marginal: If a risk will result in some damage, but the extent of damage is not too
significant and is not likely to make much of a difference to the overall progress of the
project.
3. Moderate: Risks which do not impose a great threat, but yet a sizable damage can be
classified as moderate.
4. Critical: Risks with significantly large consequences which can lead to a great amount of
loss are classified as critical.
5. Catastrophic: These are the risks which can make the project completely unproductive and
unfruitful and must be a top priority during risk management.
Extreme: The risks that fall in the cells marked with ‘E’ (red color), are the risks that are most
critical and that must be addressed on a high priority basis. The project team should gear up for
immediate action, so as to eliminate the risk completely.
High Risk: Denoted with ‘H’ with a pink background in the risk assessment template, also call for
immediate action or risk management strategies. Here in addition to thinking about eliminating
the risk, substitution strategies may also work well. If these issues cannot be resolved
immediately, strict timelines must be established to ensure that these issues get resolved before
the create hurdles in the progress.
Medium: If a risk falls in one of the orange cells marked as ‘M’ , it is best to take some reasonable
steps and develop risk management strategies in time, even though there is no hurry to have such
risks sorted out early. Such risks do not require extensive resources; rather they can be handled
with smart thinking and logical planning.
Low Risk: The risks that fall in the green cells marked with ‘L’, can be ignored as they usually do
not pose any significant problem. However still, if some reasonable steps can help in fighting these
risks, such steps should be taken to improve overall performance of the project.
Consequence Table