0% found this document useful (0 votes)
11 views22 pages

Project Monitoring and Controling

The document discusses project monitoring and control. It describes monitoring as collecting, recording, and reporting project performance data, while controlling uses this data to bring actual performance in line with plans. Key aspects of project control include planning performance metrics, measuring work status, comparing to baselines, and taking corrective actions. The document also explains techniques for monitoring and control, focusing on earned value analysis as a method to measure physical progress, schedule performance, and cost performance through variables like planned value, earned value, actual costs, schedule variance, cost variance, schedule performance index, and cost performance index.

Uploaded by

bassem djedi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views22 pages

Project Monitoring and Controling

The document discusses project monitoring and control. It describes monitoring as collecting, recording, and reporting project performance data, while controlling uses this data to bring actual performance in line with plans. Key aspects of project control include planning performance metrics, measuring work status, comparing to baselines, and taking corrective actions. The document also explains techniques for monitoring and control, focusing on earned value analysis as a method to measure physical progress, schedule performance, and cost performance through variables like planned value, earned value, actual costs, schedule variance, cost variance, schedule performance index, and cost performance index.

Uploaded by

bassem djedi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 22

Chapter 9

Project Monitoring and Control

1
Project Management Process
Groups
Project Monitoring and Control
 Monitoring – collecting, recording, and
reporting information concerning project
performance that project manger and others
wish to know
 Controlling – uses data from monitor activity
to bring actual performance to planned
performance
 Outputs include performance reports,
requested changes, and updates to various
plans
Chapter 9 Project Monitoring & Control 3
Why do we monitor?
 Simply because we know that things
don’t always go according to plan (no
matter how much we prepare)
 To detect and react appropriately to
deviations and changes to plans

Chapter 9 Project Monitoring & Control 4


Project Control
 Ongoing effort to keep your project on track
 4 primary activities:
 1. Planning performance

schedule, and a control process
 2. Measuring status of work performed

Actuals
 3. Comparing to baseline
 Variances
 4. Taking corrective action as needed

Response
 Prerequisite to good control is a good plan
5
Project Control
 “Control”
 Power, authority, domination. No.

Guiding a course of action to meet an objective. Yes.
 Principles
 Work is controlled, not workers
 Control helps workers be more effective & efficient

Control based on work completed
 Balance
 Appropriate level between too much and too little
 Includes:
 Micro-managing vs. neglect

 Too much tracking detail vs. too little

6
Progress Monitoring
 The 3 key Progress Monitoring
Questions
 What is the actual status?
 If there’s a variance, what is cause?
 What to do about it?
 Possible responses
 1. Ignore

2. Take corrective action

3. Review the plan
7
Progress Monitoring
 Monitoring rates
 Daily, weekly, monthly
 If problems occur – then adjust
 You may have to monitor problem areas more closely
 For some period of time
 Almost always there’s one or more areas under closer
scrutiny
 Status Reporting
 Part of the communications management plan

8
Status Reports
 From team to PM, from PM to stakeholders
 Typical format for letter
 Summary
 Accomplishments for this period (done)
 Tasks, milestones,
 Plans for next period (to-do)
 Risk analysis and review
 Issues & Actions
 Shoot for weekly updates
 Email notes, then hold brief meeting
 More frequently during crises
9
Traffic Light Assessment
 Identify the key element
 Break these key element in constitute element
 Access each second level element
 Green (on target)
 Amber (not on target but recoverable)
 Red (not on target but recoverable with difficulties)
 Review all the second level assessment to arrive at
first level assessment

Chapter 9 Project Monitoring & Control 10


Project Control Cycle

PLAN
Specifications
ACTION Project Schedule
Correct Project budget
deviations Resource plan
MONITOR
from plan Vendor contracts
Record status
RE-PLAN as Report progress
Report cost
necessary
COMPARE
Actual status
against plan
-Schedule
-Cost

Chapter 9 Project Monitoring & Control 11


Project Control
 Control – process and activities needed to
correct deviations from plan
 Control the triple constraints
 time (schedule)
 cost (budget, expenses, etc)
 performance (specifications, testing results, etc.)

Chapter 9 Project Monitoring & Control 12


Techniques for monitoring and
control
 Earned Value Analysis
 Critical Ratio

Chapter 9 Project Monitoring & Control 13


Earned Value Analysis (EVA)
 Earned Value analysis is a method of performance
measurement
 EVA is also called Variance Analysis
 Metric of project tracking
 “What you got for what you paid”
 Physical progress
 Pre-EVA ‘traditional’ approach
 1. Planned time and costs
 2. Actual time and costs
 Progress: compare planned vs. actual
 EVA adds third dimension: value
 Planned, actual, earned

Chapter 9 Project Monitoring & Control 14


Earned Value Analysis
 If total value of the work accomplished is in balance
with the planned (baseline) cost, and actual cost then
top mgmt has no particular need for a detailed
analysis of individual tasks
 Old models include cost & expenditure
 EVA adds schedule estimation
 Measured in dollars or hours

Chapter 9 Project Monitoring & Control 15


Earned Value Analysis
 3 major components

BCWS: Budgeted Cost of Work Scheduled
 Now called “Planned Value” (PV)
 “Yearned”
 How much work should be done?

BCWP: Budgeted Cost of Work Performed
 Now called “earned value” (EV)
 “Earned”
 How much work is done?
 BCWS * % complete
 ACWP: Actual Cost of Work Performed
 Now called “Actual Cost” (AC)
 “Burned”
 How much did the work done cost?

16
Derived EVA Variances

SV: Schedule Variance
 BCWP – BCWS
 Planned work vs. work completed

CV: Cost Variance
 BCWP – ACWP
 Budgeted costs vs. actual costs
 Negatives are termed ‘unfavorable’

“What is the project status”?
 You can use variances to answer this

17
Derived EVA Ratios
 SPI: Schedule Performance Index
 BCWP / BCWS
 CPI: Cost Performance Index
 BCWP / ACWP
 Interpretation of Indexes

18
Earned Value Analysis
 Other Derived Values

BAC: Budget At Completion
 Sum of all budges (BCWS). Your original budget.
 Planned Value (PV) at the end of the project

EAC: Estimate At Completion
 Forecast total cost at completion
 EAC = ((BAC – BCWP)/CPI) + ACWP
 Unfinished work divided by CPI added to sunk cost
 If CPI < 1, EAC will be > BAC
 CR: Critical Ratio
 SPI x CPI
 1: everything on track
 > .9 and < 1.2 ok
 Can be charted
19
EVA Example-1
 You have a project to be completed in 12 months and total cost of
project is $100,000. Six months have been passed (and schedule says
that 50% of work should be completed).
 Six months have been passed and $60,000 is spent but on closer look
you find that only 40% of work is completed so far.
 Planned Value (BCWS)
 Project duration – 12 months
 Project Cost (BAC) = $100,000
 Percent complete – 50% (as per the schedule)
 Planned Value = 50% of value of total work
 = 50% of BAC
 = 50% of $100,000
 = (50/100)X $100,000
 = $50,000

 Chapter 9 Project Monitoring & Control 20


EVA Example-1
 Earned Value (BCWP)
 Hence, Earned Value is = 40% of value of total work
 = 40 % of BAC
 = 40% of $100,000
 = 0.4X$100,000
 = $40,000
 Therefore, Earned Value (EV) is $40,000
 Actual Cost (ACWP)
And in our question, you have spent $60,000 on the project so far.
 Hence, Actual Cost is $60,000
 Calculate SPI and CPI?

Chapter 9 Project Monitoring & Control 21


Earned Value Analysis
 Benefits
 Consistent unit of measure for total progress
 Consistent methodology

Across cost and completed activity

Apples and apples comparisons
 Ability to forecast cost & schedule
 Can provide warnings early
 Success factors
 A full WBS is required (all scope)

22

You might also like