Bmy S4CLD2111 BPD en FR
Bmy S4CLD2111 BPD en FR
Subcontracting (BMY_FR)
Table of Contents
1 Purpose
2 Prerequisites
2.1 System Access
2.2 Roles
2.3 Master Data, Organizational Data, and Other Data
2.4 Business Conditions
2.5 Preliminary Steps
2.5.1 Creating Purchasing Info Record (Optional)
2.5.2 Initial Requirement Situation (Optional)
2.5.3 Creating Planned Independent Requirements
2.5.4 Material Requirements Planning at Plant Level
2.5.5 Initializing Material Stock
2.5.5.1 Option 1: For Non-Serial Number Managed Material
2.5.5.2 Option 2: For Serial Number Managed Material
2.5.6 Check Flexible Workflow for Purchase Order Approval
2.5.7 Configure Flexible Workflow for Purchase Order
3 Overview Table
4 Test Procedures
4.1 Part 1: Subcontracting without Serial Number Management
4.1.1 Convert Purchase Requisition to Purchase Order
4.1.2 Create Purchase Order
4.1.3 Monitor Subcontracting Document (Optional)
4.1.4 Approve Purchase Orders (Optional)
4.1.5 Option 1 : Outbound Delivery
4.1.5.1 Handling Unit Management (Optional)
4.1.5.2 Create Outbound Delivery
4.1.5.3 Pick and Post Goods Issue
4.1.6 Option 2: Transfer Posting
4.1.7 Receive Goods from Subcontracting PO
4.1.8 Create Supplier Invoice
4.1.9 Review Supplier Invoice (Optional)
4.2 Part 2: Subcontracting with Serial Number Management
4.2.1 Create Purchase Order
4.2.2 Approve Purchase Orders (Optional)
4.2.3 Create Outbound Delivery
4.2.4 Handling Unit Management (Optional)
4.2.5 Pick and Post Goods Issue
4.2.6 Receive Goods from Subcontracting PO
4.2.7 Create Supplier Invoice
5 Appendix
5.1 Succeeding Processes
A subcontract purchase requisition is either generated via the Material Requirements Planning (MRP) process or manually by a requestor. The purchase requisition is converted into a subcontract
purchase order. The purchase order is subject to approval based on predefined parameters before being issued to the subcontractor.
The consumption of the sent components is recorded upon the receipt of the value-added finished material. The outbound delivery is created and the goods are picked and shipped to the subcontrac-
tor. With the supply of the finished material the goods receipt is created. Subsequently the invoicing process is triggered.
This document provides a detailed procedure for testing this scope item after solution activation, reflecting the predefined scope of the solution. Each process step, report, or item is covered in its
own section, providing the system interactions (test steps) in a table view. Steps that are not in scope of the process but are needed for testing are marked accordingly. Project-specific steps must be
added.
Values in this test script (decimal notation, date formats, and so on) are presented in U.S. standard notation. If your test system is set up to use a different notation, enter values as appropriate.
This section summarizes all the prerequisites for conducting the test in terms of systems, users, master data, organizational data, other test data and business conditions.
System Details
System Accessible via SAP Fiori launchpad. Your system administrator provides you with the URL to access the various apps assigned to your role.
2.2 Roles
Create business roles using the following business role templates delivered by SAP and assign them to your individual test users.
Alternatively, if available, you can use the following spaces delivered by SAP. You create a space with pages containing predefined essential apps and assign it to the business role. You then assign
this business role to your individual users.
For more information, refer to How to Create a Business Role for the Administrator in the product assistance for SAP S/4HANA Cloud.
Configuration Expert - Business SAP_BR_BPC_EXPERT Configuration Expert - Business Process Configura- SAP_BR_BPC_EXPERT
Process Configuration tion
Vendor 12300007 Domestic FR Subcon- Note If you want to send form print outs via e-mail instead of using the print functionality make sure that you have
tractor A maintained a valid e-mail address in the vendor master data.
Subcontracting (BMY_FR) PUBLIC
Purpose Error: Reference source not found 5
Data Sample Details Comments
Value
You can find general information on how to create master data objects in the following Master Data Scripts (MDS) :
Table 1: Master Data Script Reference
MD Description
S
BN Create Product Master of Type "Semi-Finished
S Good"
BJ5 - Make-to-Stock Production - Discrete Manufactur- To run through this test script, the materials must be available in stock. If you use finished goods (FERT) you can ei-
ing ther:
Run through the Make-to-Stock Production - Discrete Manufacturing BJ5 process (for material FG126) or
Create stock using transaction MIGO (for more information, see Preliminary Steps).
Procedure
2 Access the App Open Manage Purchasing Info Records (F1982). The Manage Purchasing Info Records is dis-
played.
3 Open New Purchasing Info Choose Create. The Purchasing Info Record screen is displayed.
Record
4 Enter Header Data Make the following entries: Header data is added.
Purchasing Info Record Category: Subcontracting
Purchasing Organization: 1210
Supplier: 12300007
Material: SG23
Plant: 1210
Purchasing Group: 001
5 Enter General Information Make the following entries: General Information is added.
Available From: Today
Available To: 12/31/9999
6 Enter Purchasing Data Make the following entries: Purchasing Data is added.
Incoterm: EXW
Incoterm Location 1: VENDOR
7 Enter Delivery and Quantity Data Make the following entries: Delivery and Quantity Data is added.
Delivery Time in Days: 10
Under Delivery Tolerance in %: 10.0
Subcontracting (BMY_FR) PUBLIC
Purpose Error: Reference source not found 7
Test Step Test Step Name Instruction Expected Result Com-
# ments
Over Delivery Tolerance in %: 10.0
Tax Code: <Input Tax Code>
Order Unit: PC
Standard Order Quantity: 100
Goods-Receipt-Based Invoice Verification: X
8 Enter Condition Data In the Condition section, choose Create. Condition Data is added.
In the General Information area, make the following entries:
Valid From: Today
Valid To: 12/31/9999
Amount: 0.59
Pricing Unit: 1
Currency: EUR
Choose Apply.
9 Enter Reference Data (optional) You can enter reference data. Reference data is added.
10 Save your data Choose Save. The purchasing info record is saved.
Result
Purpose
The MRP run only creates purchase requisitions if the demand is bigger than the available quantity. You can check the requirement situation in the Stock/Requirement List. If necessary, you can
reduce the quantity of unrestricted use by posting a goods issue.
Test Step Test Step Instruction Expected Result Pass / Fail / Com-
# Name ment
1 Log on Log on to Fiori Launchpad as a Production Planner,
2 Open the Fiori Open Monitor Material Coverage (Deprecated) - Net / Individual Segments The Monitor Material Coverage (Original) screen
App (F2101) . displays.
3 Select Material Select the checkbox for material SG23 and choose the Manage Materials button The Material screen and Material Details screen dis-
(bottom right). play.
4 Check stock Select the corresponding material. The detailed Stock/Requirements List for each mate-
rial displays.
Purpose
Planned independent requirements are used to perform demand management functions. A planned independent requirement contains one planned quantity and one date, or a number of planned inde-
pendent requirements schedule lines, such as one planned quantity split over time according to dates.
Note Instead of creating a single requirement, sometimes a requirements plan that includes one or more planned independent requirements can be maintained for mass processing. In this case, the
requirements are grouped and maintained under a requirement plan number.
Procedure
2 Access the App Open Maintain PIRs (F3445) The Manage PIRs (Original) screen displays.
3 Check Default On the Maintain PIRs, choose your user name and choose App Settings. If the entry Plant 1 FR/001 is not present in the Area of
Area of Responsi- On the MRP Settings screen, choose Area of Responsibility: Responsibility screen ,choose Add to select it and then choose
OK.
Subcontracting (BMY_FR) PUBLIC
Purpose Error: Reference source not found 9
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment
bility Check only this entry is displayed there: For other plant entries in the Area of Responsibility screen,
Plant 1 FR/001 (MRP Controller 001) choose Delete to remove the others and then choose OK.
4 Select Material On the Manage PIRs (Original) screen, , make the following entries:
Plant: 1210
Period Indicator: Monthly (M)
Search: SG23.
Please make sure you have the same setting in material master data MRP 3
view for Period Indicator. If no, please refer to master data script BNS for
adaption.
6 Select Material Check the material item, and choose Edit PIRs in the upper right.
Item
7 Edit PIRs On the Edit PIRs screen, enter quantities per period, for example:
PIR: 100.
Purpose
The aim of material requirements planning is to tailor available capacities and receipts on time to suit requirements quantities. You can use MRP or consumption-based planning for this purpose.
Single-item multilevel requirement planning is performed for plant 1210.
Prerequisite
The semi product is planned at plant level. There is now a requirement for the material SG23 in plant 1210.
2 Access the App Open Schedule MRP Runs (F1339). The Application Jobs (Original) screen displays.
3 Enter Basic Parameters for New Choose + (New) above the table.
Job On the New Jobs screen, make the following entries:
Job Template: Material Requirement Planning (MRP)
Job Name: MRP forSG23
Start Immediately: X
Plant: 1210
Material (Original) : SG23
Changed BOM Components: X
Planning Mode: 1
5 Schedule New Job In the New Job screen, choose Schedule. The new job displays in the Application Jobs
(Original) table.
6 Refresh Application Jobs List To check the status of the job you created, choose Go in the top right The Application Jobs table is refreshed.
section of the screen.
Purpose
In a real business case, the materials are usually purchased from external vendors. In this case, the process is covered by the standard purchasing or subcontracting processes. For the purpose of this
test, we post initial stock directly to the storage locations.
Procedure
2 Access the App Open Manage Stock (F1062). TheManage Stock (Original) screen displays.
3 Enter Material Make the following entries and press En- The stock overview for the material is displayed.
ter:
Material (Original) : For example, RM13
and RM14
Plant: For example, 1210, Plant 1 FR
4 Select Stock Select the icon next to the stock to add A dialog box displays. The Storage Location, Stock Type, and Current Quantity fields are
initial stock. For example: displayed according to your entries in previous steps.
Storage Location: 121C (for RMxx
materials)
Unrestricted Use Stock
5 Add Initial Entry Make the following entries and choose The system displays the message Material document XXX created. The stock
Post: is added.
Document date: <Today>
Posting date: <Today>
Subcontracting (BMY_FR) PUBLIC
Purpose Error: Reference source not found 12
Test Test Step Name Instruction Expected Result Pass / Fail /
Step # Comment
Stock Change: Initial Entry
Quantity: <Enter a quantity>
Procedure
2 Access the App Open Post Goods Movement (MIGO) . The Goods Receipt It only displays it that way if it was your last transaction. So the action
Other screen displays. for the User should be to select field Reference Document for MIGO
Transaction Other
3 Input Movement Type Make the following entries and choose Enter:
Business Transaction: Goods Receipt
Business Transaction: Other
Movement Type: 561 - Receipt per initial entry
of stock balances into unr.-use
4 Input on the Goods Receipt On the Goods Receipt Other screen: Material
Other screen: Material tab tab, make the following entry and choose Enter:
Material (Original) : RM33/RM34
5 Input on the Goods Receipt On the Goods Receipt Other screen: Quantity
Other screen: Quantity tab tab, make the following entries and choose En-
ter:
Qty in Unit of Entry: <Qty in UOM>
Unit of Entry: PC
6 Input on the Goods Receipt On the Goods Receipt Other screen: Where tab,
7 Input on the Goods Receipt On the Goods Receipt Other screen: Serial
Other screen: Serial Numbers Numbers tab, enter the serial number.
tab
Purpose
In this procedure, you check the flexible workflow for purchase order approval.
When you use the flexible workflow to approve the purchase order, make sure Flexible Workflow for Purchase Order with NB document is activated, and Flexible Workflow for Purchase Order
Approval is configured.
Procedure
Depending on your configuration environment for SAP S/4HANA Cloud, choose one of the following options:
Configure Your Solution:
2. Access App Open Manage Your Solution (F1241) . The Manage Your Solution screen is dis-
played.
4. Open Active Flexible On the Configure Your Solution: Realize Phase screen, search Activate Flexible Workflow The Document Types Purchase order Change
Workflow for Purchase Orders, then choose Search. screen is displayed.
Select the line of the item and go to the next screen.
On the Configure Your Solution - Purchase Order Processing screen, choose Configure on
the line of configuration step with name Activate Flexible Workflow for Purchase Orders.
5. Check Flexible Work- Verify the following entries: The Scenario based workflow is active for
flow for PO Approval Purchasing Doc. Type: NB Purchase Orders with Document Type: NB.
2 Open Active Flexible In the Product-Specific Configuration phase, navigate to the Configuration Activities tab The Document Types Purchase order Change
Workflow and search for the following activity: Activate Flexible Workflow for Purchase Orders. screen displays.
Choose the line item in the search result to see more details about this configuration activ-
ity.
Choose the Go to Activity button to navigate directly to the SAP S/4HANA Cloud system.
Log on to the SAP Fiori launchpad as a Configuration Expert - Business Process Configu-
ration.
3. Check Flexible Work- Verify the following entries: The Scenario based workflow is active for
flow for PO Approval Purchasing Doc. Type: NB Purchase Orders with Document Type: NB.
Purpose
In this procedure, you configure your release conditions for Purchase Order Approval.
Note When you start to process this step, make sure that the flexible workflow for purchase document type NB has been activated in your system.
Procedure
Test Step Test Step Name Instruction Expected Result Pass / Fail / Com-
# ment
1 Log on Log on to the SAP Fiori launchpad as a Configuration Expert - Business Process The Fiori launchpad is displayed.
Configuration .
2 Access the App Open Manage Workflows for Purchase Orders (F2872). The Manage Workflows (Original) screen is
displayed.
3 Create Manage Work- Choose Add and make the following entries: The Workflow for Purchase Order is config-
flow Name: Test Workflow for Purchase Order ured.
4 Activate Workflow Select the Workflow Item just created and choose Activate. The Workflow Item is activated.
Item
Note Please make sure default workflow Automatic Release of Purchase Order has been activated.
This scope item consists of several process steps provided in the table below.
If your system administrator has enabled spaces and pages on the SAP Fiori launchpad, the homepage will only contain the essential apps for performing the typical tasks of a business role.
You can find all other apps not included on the homepage using the search bar.
If you want to personalize the homepage and include the hidden apps, navigate to your user profile and choose App Finder.
Convert Purchase Requisition to Purchaser Process Purchase Requisitions - Formerly Manage Purchase order is created.
Purchase Order [page ] 20 Purchase Requisitions (F1048)
Create Purchase Order [page ] 21 Purchaser Manage Purchase Orders (F0842A) PO is created.
Approve Purchase Orders (Optional) Purchasing Manager My Inbox - All Items (F0862). Purchase orders are approved.
[page ] 23
Create Outbound Delivery [page ] 25 Purchaser Display Subcontracting Stocks by Supplier (ME2ON) Outbound Delivery created.
Pick and Post Goods Issue [page ] 26 Shipping Specialist Change Outbound Delivery (VL02N)
Receive Goods from Subcontracting Warehouse Clerk Post Goods Receipt for Purchasing Document Material document and journal entry showing receipt of purchased
PO [page ] 29 (F0843) material and consumption of components.
Create Supplier Invoice [page ] 30 Accounts Payable Create Supplier Invoice - Advanced (MIRO)
Accountant
Review Supplier Invoice (Optional) Accounts Payable Supplier Invoices List (F1060a) Invoice has been reviewed.
[page ] 32 Accountant
Approve Purchase Orders (Optional) Purchasing Manager My Inbox - All Items (F0862) Purchase orders are approved.
[page ] 35
Create Outbound Delivery [page ] 36 Purchaser Display Subcontracting Stocks by Supplier (ME2ON) Outbound delivery is created.
Pick and Post Goods Issue [page ] 38 Shipping Specialist Change Outbound Delivery (VL02N)
Receive Goods from Subcontracting Warehouse Clerk Post Goods Movement (MIGO) Material document and journal entry showing receipt of purchased
PO [page ] 39 material and consumption of components.
Create Supplier Invoice [page ] 30 Accounts Payable Create Supplier Invoice (F0859) Invoice document and journal entry.
Accountant
This section describes test procedures for each process step that belongs to this scope item.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Purpose
In this activity, a purchase requisition for planned subcontracting is assigned and a corresponding purchase order is created.
If you want to use the Save Draft feature in this app, you have to use a personalized user.
2 Open Manage Purchase Open Process Purchase Requisitions - Formerly Manage Purchase A list of Requisitions is displayed.
Requisitions Requisitions (F1048).
3 Select Purchase Requi- Search for a Purchase Requisition for material SG23 with Sources The Select Source of Supply screen is displayed.
sition available, and choose the link of the sources.
4 Assign Source to Pur- Choose a displayed source with a real price (not zero). The assignment of one source to the requisition is done. The
chase Requisition Purchase Requisitions list is displayed.
5 Prepare the Purchase Select the purchase requisition where the assigned supplier is dis- The Purchase Order Preview screen is displayed.
Order played and choose Create Purchase Order (Original).
6 Create the Purchase Select Standard order from Purchase Order Type drop down list, and The purchase order is created.
Order choose Submit.
7 Back to Manage Pur- In the dialog box, choose OK. Purchase Requisition list is displayed again. The converted
chase Requisition Purchase Requisition has disappeared from the list.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
This activity creates a purchase order for subcontract material. . This activity is only required if you do not convert an existing purchase requisition as described in Assign Purchase Requisition /
Create Subcontract Order.
Note You can store purchase order data as template for frequently used data. To save the data to a template, choose Save as Template. To load data from a template, choose Load from Template.
Procedure
2 Access the App Open Create Purchase Order - Advanced (ME21N). The Create Purchase Order (Original) screen is displayed with a list of
existing Purchasing Document Items.
3 Start Purchase Order Without making any selection, choose Create Purchase Order . The Purchase Order Screen is shown.
creation
5 Save Purchase Order Choose Order and when the purchase order number is displayed, A Purchase Order is created.
write it down for further use.
Procedure
2 Access the Fiori App Open Monitor Subcontracting Documents (F3095). The Monitor Subcontracting Documents screen dis-
plays.
4 Monitor Subcontracting Click View to check the Assembly Flow. If you have multi-level subcontracting, the graph can be
Document displayed here.
5 Manage Purchase Order Check the details of your subcontracting document by clicking the
item.
Test Administration
Business
Role(s)
Subcontracting (BMY_FR) PUBLIC
Purpose Error: Reference source not found 23
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Purpose
All the purchase orders that require release by an authorized person are listed and must be approved. About the PO approve user setting, please refer to the step Configure Your Release Conditions
for PO Approval (Only for SAP S/4HANA Enterprise Management Cloud) in J45.
Note Only POs with a value higher than 500.00 EUR can be released in this transaction. POs with a value under this amount do not need to be released. For POs under this amount, this step can be
skipped.
Procedure-SETUP
2 Open Approve Open My Inbox - All Items (F0862). A list of already created Purchase Orders is displayed.
Purchase Order
3 Check Purchase Search for Purchase Order with Need Approval The Purchase Orders without follow-on documents (w/o status Follow-On Documents)
Order Status Status. and a net value of 500 EUR or more have the status In Approval.
4 Release Purchase Select the Purchase order in left of the screen and The Submit Decision dialog box is displayed.
Order click Approve in bottom right.
5 Enter Release Rea- Enter the approval reason if needed, then choose The Purchase Order is approved.
son Submit.
6 Back to Fiori Choose the Home button to go back to the Fiori The Fiori Launch Pad is displayed.
Launch Pad Launch pad.
Purpose
You can execute packing for delivery items right in a outbound delivery.
Procedure
Complete all the activities described in the test script Handling Unit Management.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Procedure
3 Search for Component or Set values to some filters to search Components. : The search results show the details with the respective filter Criteria.
Assembly Subcontractor: 12300007 Following columns must contain relevant data:
4 Display Purchase Order Choose small Arrow next to Component to expand the de- All purchase order with items number corresponding to the component
Item for a component tails must be displayed in “Purchase Order Items” column.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Procedure
Test Step Test Step Name Instruction Expected Result Pass / Fail / Com-
# ment
1 Log on Log on to the SAP Fiori launchpad as a Shipping Specialist. The SAP Fiori launchpad
displays.
2 Access App Open Change Outbound Delivery (VL02N). The app name screen displays.
5 Post Goods Issue (Original) On the Change Outbound Delivery (Original) screen, choose Post Goods Issue
(Original).
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Procedure
2 Access the App Open Subcontracting Cockpit (F2948) The Subcontracting Cockpit (Original) screen is displayed.
3 Search for Component or Set values to some filters to search Components. : The search results show the details with the respective filter Criteria.
Assembly Subcontractor: 12300007 Following columns must contain relevant data:
4 Display Purchase Order Choose small Arrow next to Component to expand the details All purchase order with items number corresponding to the compo-
Item for a component nent must be displayed in “Purchase Order Items” column.
5 Post Goods Issue (Origi- Choose a PO Item and then choose Post Goods Issue (Origi- There will be navigation to the ‘Post Goods Issue’ app.
nal) nal).
8 Post Select all the items and Post Goods Issue (Original). The system displays the message Material
document 4900000XX XXXX posted .
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Purpose
In this step, you post the goods receipt for the material against the subcontracting PO.
Procedure
Test Step Test Step Name Instruction Expected Result Pass / Fail / Com-
# ment
1 Log on Log on to the SAP Fiori launchpad as a Warehouse Clerk. The Fiori Launch Pad is displayed.
3 Select Goods Receipt Order Enter your PO number or search your subcontracting pur- The items of the selected Purchase Order display.
screen chase order.
4 Select Item Select the item for which a goods receipt is to be posted.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Purpose
2 Access the app Open Create Supplier Invoice (F0859). The Create Supplier Invoices screen is
displayed.
3 Enter General Data In case of purchase orders created with local currency in your system, make the following The Create Supplier Invoices screen dis-
entries. plays.
Transaction: Invoice
Company Code: 1210
Reference: <xxx> (reference invoice number from invoicing party)
Gross Invoice Amount : <XXX>
Currency: EUR
Invoice Date: <Today>
Posting Date: <Today>
Invoice Party: 12300001
4 Enter Purchase Order In Purchase Order References, make the following entries (use a PO you created previously) The Purchase Order References screen
References and choose Enter. displays.
Make the following entries (use a PO you created previously).
References Document Category: Purchase Order/ Scheduling Agreement
Purchase Order: <PO number>
5 Select Purchase Order Check the selection of the Purchase Order Items. All items of the selected Purchase Order
Items Confirm the warning messages. are added to the Purchase Order Item table.
You should see material items which refer
to the entered purchase order document.
6 Check the Invoice Check the Amount, the Quantity, the Tax Code (there may already be a tax code that was The Purchase Order Item's table displays.
Items data copied from the purchase order).
7 Check Tax code In the section Tax check if there is tax code information. In the Tax tab, you should see the same tax
codes as in the items.
If there is no tax, specify the tax coder V6
8 Check the balance Calculate the tax amount from the item amount multiplied by the tax value. The balance should be zero (or within the
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Purpose
The invoice verification is done in this activity using the list overview on invoice documents.
Test Step Test Step Name Instruction Expected Result Pass / Fail / Com-
# ment
1 Log on Log on to the SAP Fiori launchpad as an Accounts Payable Accoun- The Fiori Launch Pad is dis-
tant. played.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
This activity creates a purchase order for subcontract material.. This activity is only required if you do not convert an existing purchase requisition as described in Assign Purchase Requisition /
Create Subcontract Order.
Note You can store purchase order data as template for frequently used data. To save the data to a template, choose Save as Template . To load data from a template, choose Load from Template .
Procedure
2 Open Open Create Purchase Order - Advanced The Create Purchase Order (Original) screen is displayed with a list of existing Purchasing Document Items.
Create (ME21N).
Purchase
Order
3 Enter Enter the following data and choose En- All data is entered. The Item Detail screen displays.
Purchase ter: Depending on the relevance of chain liability for the supplier on a purchase order, some steps or fields may or
Order data Order type : Standard PO may not be displayed. If chain liability is relevant, you must enter the start and finish dates for the work, along
Supplier (Original) : 12300007 with the number of hours to be worked. If you are posting a portion of the invoice to your sub-contractor’s
blocked account, enter the percentage of the line items that are wage-relevant. This enables the system to pro-
In the area of Header / Org. Data : pose the amount to be posted to the blocked account.
Purchasing Org : 1210
Purchasing Group : 001
Company Code: 1210
In the area of Item Overview:
Item Category : L
Material (Original) : SG27
Quantity: 2 PC
Net. Price: x EUR
Plant: 1210
Storage Location: 121B
Subcontracting (BMY_FR) PUBLIC
Purpose Error: Reference source not found 34
Test Test Step Instruction Expected Result Pass /
Step Name Fail /
# Com-
ment
In the area of Item Detail:
Switch to Delivery Schedule, and choose
Assign Serial Number. Choose Create
Serial Number Automatically, and then
choose Continue.
4 Save Pur- Choose Save and when the purchase order A Purchase Order is created.
chase number is displayed, write it down for
Order further use.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Purpose
All the purchase orders that require release by an authorized person are listed and must be approved. About the PO approve user setting, please refer to the step Configure Your Release Conditions
for PO Approval (Only for SAP S/4HANA Enterprise Management Cloud) in J45.
Procedure
2 Access the App Open My Inbox - Approve Supplier Invoice A list of already created Purchase Orders is displayed.
(F0545A).
3 Check Purchase Search for Purchase Order with Need Approval Status. The Purchase Orders without follow-on documents (w/o status Follow-On Docu-
Order Status ments) and a net value of 500 EUR or more have the status In Approval.
4 Release Purchase Select the Purchase Order on the left side of the screen The Submit Decision screen is displayed.
Order and choose Approve at the bottom right.
5 Enter Release Enter the approval reason if necessary, and then choose The Purchase Order is approved.
Reason Submit.
6 Back to Fiori Choose the Home button to go back to the Fiori Launch The Fiori Launch Pad is displayed.
Launch Pad pad.
Test Administration
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Procedure
Test Step Test Step Name Instruction Expected Result Pass / Fail / Com-
# ment
1 Log on Log on to the SAP Fiori launchpad as a Purchaser. The SAP Fiori launchpad
displays.
2 Access App Open Display Subcontracting Stocks by Supplier (ME2ON). The app name screen dis-
plays.
4 Subcontracting Cockpit (Original) Expand the group of Requirements via SC Orders for below materials:
Material (Original) : RM33 and RM34
Find the line items with your purchase order number. Use Ctrl to select
both lines.
Select (More -) Create Delivery.
5 Creating Delivery for Subcontracting Purchase Enter Stor.Location for both lines:
Orders Stor.Location: 121C
Use Ctrl to select the both lines and choose Create Document (Original).
Note down your delivery number.
Purpose
You can execute packing for delivery items right in a outbound delivery.
Procedure
Complete all the activities described in the test script Handling Unit Management.
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Procedure
Test Step Test Step Name Instruction Expected Result Pass / Fail / Com-
# ment
1 Log on Log on to the SAP Fiori launchpad as a Shipping Specialist. The SAP Fiori launchpad
2 Access App Open Change Outbound Delivery (VL02N). The app name screen displays.
7 Post Goods Issue (Original) (Original) On the Change Outbound Delivery (Original) screen, choose Post Goods Issue
(Original).
Test Administration
Business
Role(s)
Purpose
In this step, you post the goods receipt for the material against the subcontracting PO.
Procedure
2 Open Post Goods Movement tile Open Post Goods Movement (MIGO). The Post Goods Receipt for Purchase Order (Original).
screen is displayed.
3 Select Goods Receipt Order screen On the Goods Receipt Order screen, make the following The items of the selected Purchase Order display.
entries and choose Enter:
Goods Receipt: <Select>
Purchasing Order: <Select>
Order number:<Purchase Order number>
GR goods receipt:101
Test Administration
Business
Role(s)
Responsibility <State the Service Provider, Customer or Joint Service Provider and Customer> Duration Enter a duration.
Purpose
Procedure
3 Enter General Data In case of purchase orders created with local currency in your system, make the following The Create Supplier Invoices screen dis-
entries. plays.
Transaction: Invoice
Company Code: 1210
Reference: <xxx> (reference invoice number from invoicing party)
Gross Invoice Amount : <XXX>
Currency: EUR
Invoice Date: <Today>
Posting Date: <Today>
Invoice Party: 12300001
4 Enter Purchase Order In Purchase Order References, make the following entries (use a PO you created previously) The Purchase Order References screen
References and choose Enter. displays.
Make the following entries (use a PO you created previously).
References Document Category: Purchase Order/ Scheduling Agreement
Purchase Order: <PO number>
5 Select Purchase Order Check the selection of the Purchase Order Items. All items of the selected Purchase Order
Items Confirm the warning messages. are added to the Purchase Order Item table.
You should see material items which refer
to the entered purchase order document.
6 Check the Invoice Check the Amount, the Quantity, the Tax Code (there may already be a tax code that was The Purchase Order Item's table displays.
Items data copied from the purchase order).
7 Check Tax code In the section Tax check if there is tax code information. In the Tax tab, you should see the same tax
codes as in the items.
If there is no tax, specify the tax coder V6
8 Check the balance Calculate the tax amount from the item amount multiplied by the tax value. The balance should be zero (or within the
defined tolerance).
Accounting and Financial Close (J58) Dispose of the inventory by returning to the vendor. Do not process any other activities in this document after running the external process.
Using the master data from this document, complete the following activities described in the test script:
● Run the test script in its entirety, using the master data from this test script document.
Real-Time Reporting and Monitoring for The Procurement Overview Page gives the Purchaser the most important and relevant information at a glance – instead of navigating through many
Procurement (1JI) different transactions and reports.
The global filter helps the Purchaser to focus the entire Procurement Overview Page to view all information according to specific suppliers, mate-
rial groups, purchasing groups, and more.
Using contextual navigation, the Purchaser can immediately act upon the displayed information by accessing the app or the object instance or get
more detailed information in the corresponding KPI Drill-Downs.
Example Words or characters quoted from the screen. These include field names, screen titles, pushbuttons labels, menu names,
menu paths, and menu options.
Textual cross-references to other documents.