Annex 1
Application No.
Application for Net Metering of an On-Grid Small-Scale Renewable Energy Facility
(Scheme 01)
For installed capacities up to the Contract Demand of the existing installation.
1. Project Type: Please mark in the appropriate boxes below. Please select one or a combination
of many types.
Waste
Micro Biomass (agricultural,
Wind Solar Photovoltaic
hydro (grown) industrial, municipal,
waste heat)
2. Information about the Applicant:
Electricity Consumer’s Account No.
Name
. NIC number
Address as specified in the Account No.
Demand of the Installation: single/three phase, Ampere
Note: The small-scale renewable energy facility shall be located at the premise served by the
electricity account stated above.
Telephone numbers: Email.
0
0
3. Facility Information – Please fill-in the information requested under the project type(s) selected
in item 1 above.
4. Certification
I attach the receipt number ......................dated....................for the payment of Rs
…………………… as the review fee for this application, charged by CEB.
I certify that Net Metering Facility is required at the same premise where electricity account
is already provided, and that the renewable energy resource is within the property served by
the existing electricity supply.
I have read the Agreement and the Interconnection Standards applicable for Net Metering
Facility. I agree to install all the required equipment and to provide information
whenever requested by CEB and the Sri Lanka Sustainable Energy Authority.
Name of person signing this application
registered consumer)
Signature Date:
DD-MM-YYYY
1
5. Additional Information/Requirements
Installers Details
Installer
Address
Contact Person
Fixed
Telephones
Mobile
Fax
Email
6. Information to be submitted with the application
1. Final Copy of the Circuit Diagram (proposed)
2. Compliance Certificate obtained from accredited agency, type test certificates,
manuals, operation instructions, layout diagram, single line diagram including all
devices and their respective setting, and any other relevant documents.
3. Schedule of protective devices and protection setting.
7. Installers Declaration
All the installed equipments were purchased from Original Supplier or
authorized dealer Yes /No
The Installation is fully complies with the CEB Standards
Yes /No
The Protection Setting are protected from unauthorized alterations and
tamper proof Yes /No
Operation manuals, safety guides and the relevant documentation were
submitted and clearly explained to the end user Yes /No
Additional Comments (Continue in separate sheet if necessary)
Name of the Installer Authorized seal and Signature Date