ASSIGNMENT
ASSIGNMENT
COLLEGE OF ENGINEERING
ADD THE 2ND TO THE LAST DIGIT OF d. Determine the total project duration.
YOUR STUDENT # IN EACH OF THE e. Determine the critical path.
ACTIVITY DURATION.
6 5
EX: 202012345
5 + 4 = 9 weeks 2 5 8
11
8 5
6 14 10
1 3 7 10
7 5
13
5 3
4 6 9
CMPM - CE 524C
The table shown are lists of activities for ADD THE 2ND TO THE LAST DIGIT OF
COLLEGE OF ENGINEERING
ACTIVITY 1 2 3 4 5 6 7 8
Immediate
0 1 1 2,3 2 4 5,6 6
Predecessor
Duration
5 7 10 8 9 6 5 3
(weeks)