Electrical Activity Timeline

The document outlines the schedule for several construction projects taking place from October 2018 to January 2019. It details tasks for conduit/piping installation and wiring for VRF power supply from the lower ground to penthouse with a deadline of January 15, 2019. It also outlines tasks for auxiliary, voice, and data installation and auxiliary grounding system for the lower ground in November. A separate schedule is provided for penthouse suites power supply work taking place from November 22 to 28, 2018.

Uploaded by

nikkoelbao96
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views6 pages

Electrical Activity Timeline

The document outlines the schedule for several construction projects taking place from October 2018 to January 2019. It details tasks for conduit/piping installation and wiring for VRF power supply from the lower ground to penthouse with a deadline of January 15, 2019. It also outlines tasks for auxiliary, voice, and data installation and auxiliary grounding system for the lower ground in November. A separate schedule is provided for penthouse suites power supply work taking place from November 22 to 28, 2018.

Uploaded by

nikkoelbao96
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

ACTIVITY : Conduit/Piping Installation & Wiring for VRF Power Supply (Residential Hallway Aircon) LEGENDS :

LOCATION : Lower Ground to Penthouse PENDING


DATE STARTED : Oct. 1, 2018 DEADLINE : Jan. 15, 2018 DONE

DURATION*
START DAYS DAYS MATERIALS
TASK NAME
DATE
END DATE (WORK
COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE Oct Nov Dec Jan.
DAYS)

1. Electrical 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1.1 Hanger/Support Oct. 1 Jan. 15 50 24


Chipping/Coring/Civil
1.2 Works Oct. 1 Oct. 30
Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening Oct. 1 Oct. 30 27 27

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination 0 0%

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
ACTIVITY : Auxiliary, Voice & Data Installation for Leasable @ Lower Ground LEGENDS :
LOCATION : Lower Ground TARGET :
DATE STARTED : DEADLINE : STATUS :

DURATION* DAYS DAYS MATERIALS


TASK NAME START DATE END DATE
(WORK DAYS) COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE November

1. Electrical 3 4 5 6 7 8 9 10 11 12

1.1 Hanger/Support

1.2 Chipping/Civil Works


Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
ACTIVITY : Auxiliary Grounding System LEGENDS :
LOCATION : Lower Ground TARGET : Cha
rt
Title

DATE STARTED : DEADLINE : STATUS : Cha


rt
Title

DURATION* DAYS DAYS MATERIALS


TASK NAME START DATE END DATE
(WORK DAYS) COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE November

1. Electrical 3 4 5 6 7 8 9 10 11 12

1.1 Hanger/Support
Chipping/Coring/Civil
1.2 Works
Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
ACTIVITY : Penthouse Suites Power Supply LEGENDS :
LOCATION : Penthouse TARGET
DATE STARTED : Nov. 24, 2018 DEADLINE : Nov. 28, 2018 DONE

DURATION*
START DAYS DAYS MATERIALS
TASK NAME
DATE
END DATE (WORK
COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE Nov. Dec.
DAYS)

1. Electrical 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7

1.1 Hanger/Support Nov. 22 Nov. 28 4 2 2 3 on-site


Chipping/Coring/Civil
1.2 Works Nov. 24 Nov. 28 4 2 2 3 on-site
Cable Tray Fabrication &
1.3 Installation Nov. 24 Nov. 28 4 2 2 3 on-site

1.4 Wall/Slab Opening Nov. 24 Nov. 28 4 2 2 3 on-site

1.5 Sleeve Termination Nov. 24 Nov. 28 4 2 2 3 on-site


Wire/Cable Pulling &
1.6 Termination

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.0 Response to Punchlist

2.1 Turn-over
ACTIVITY : Conduit/Piping Installation & Wiring for VRF Power Supply (Residential Hallway Aircon) LEGENDS :
LOCATION : Lower Ground to Penthouse PENDING
DATE STARTED : Oct. 1, 2018 DEADLINE : Jan. 15, 2018 DONE

DURATION*
START DAYS DAYS MATERIALS
TASK NAME
DATE
END DATE (WORK
COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE Oct Nov Dec Jan.
DAYS)

1. Electrical 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1.1 Hanger/Support Oct. 1 Jan. 15 50 24


Chipping/Coring/Civil
1.2 Works Oct. 1 Oct. 30
Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening Oct. 1 Oct. 30 27 27

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination 0 0%

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
Construction Form
1 Cable Tray Installation & Wiring for C-5 side @ Lower Ground ok
2 Plumbing and Sanitary Rectification @ Lower Ground ok
3 Penthouse Cable Tray Installation and Wiring for VRF power supply ok
4 Auxiliary / Voice & Data for leasable area @ Lower Ground
5 MDP for Video wall
6 Hyper-Aire letter
7 Installation of Aircon @ School Lobby

Testing & Commisioning


1 Testing of all basement exhaust fan (2 fans with issues)
2 Testing of Gensets (Friday to Saturday)
3 Fire Protection Pressure/Leak Test
4 Megger Testing
5 Water and Electricity Bill settlement
6 Water Pressure Test/Leak Test