Distribution System State Estimation
Distribution System State Estimation
-
Abstract A three-phase distribution system state estimation Nowadays, the technology to autoinatically monitor and
algorithm is proposed in this paper. Normal equation method is control a distribution system is available [141. In an automated
used to compute the real-time states of distribution systems distribution system, many meters are installed. Similar 10 those
modeled by their actual a-b-c phases. A current based formulation in the transmission system automation, real-time measurements
is introduced and compared with other formulations. are noisy, thus, techniques have to be developed to screen the
Observability analysis for the proposed distribution system state measurement data. Due to the requirements of filtering
estimation is discussed. Test results indicate that the normal measurement data and having real-lime system states for on-line
equation method is applicable to the distribution system state operation. the need for a distribution system slate estimator may
estimation and the current based rectangular form formulation is soon be justified. In this view, Wu and Neyer [IS]proposed an
suitable for this application. asynchronous dislribution system SE technique. The SE was
formulated as a equality consuained weighted least squares
-
Keywords State Estimation. Distribution Automation,
Distribution System Operation. Energy Management Systems
problem. A dismbution system SE that uses a minimum number
of remote measurements was presented in [ 161. An ilerative
procedure based on Kirchhoffs current law was used U, o w n the
1. INTRODUCTION distribution system SE.
Two types of data are required for S E they are the network
In the modern Energy Management System (EMS), State data and the measurement data. A transmission system has a
Estimation (SE) program processes a set of raw measurement relatively balanced nature which allows the decoupling of the
data and provides a real-time load flow solution which is the three phase system and the positive sequence network is used for
basis of the advanced functions for system security monitoring the analysis. In reality. power systems are unbalanced when the
and control. SE is based on the mathematical relations between power lines are not fully uansposed andor the loads are not
the system state variables (e.g. bus voltage magnitudes and balanced. The unbalanced nature of the distribution system
angles) and the measurements. Various techniques have been used prohibits the use of symmevical component transformation. and
to obtain an SE solution, excellent surveys on SE algorithms due lo various combinations of single-phase. two-phase, and
can be found in [l-31. Measurements used to compute the real- three-phase loads encountered in the distribution system. accurate
time system states are bus injections, line flows and bus study can be accomplished only with distribution lines modeled
voltages. In some estimators current magnitude and voltage angle in their actual a-b-c phase representation I5-81.
measurements are also used [4]. In addition to a real-time load In addition to the network dam, we also need a set of
flow solution, state estimator also provides functions such as bad redundant measuremenb to obtain an estimate of the system
measurement data detection, modeling error detection, meter states. In a f u l l y automated system the measurements are
placement and observability test. sufficient for SE. However, in the current stage of distribution
Real-time control of the distribution system reqbires an system automation. the number of meters installed in the system
estimate of the system stales. In the past most distribution is low and may not be sufficient for SE, i.e. the system may not
systems were not monitored, therefore, there was no need for SE. be completely observable. In order to obtain an SE under this
Under this condition, distribution system load flow program is condition, techniques have to be developed Lo provide additional
often used for planning purposes, such as in computing system data (i.e. pseudo measurements) to the estimator. Intuitively. one
losses Of different feeder configurations for system loss reduction. would use the historical dala of the feeders and distribution
Various techniques have been proposed to obtain distribution transformer loadings to provide such information. Pseudo
system load flow solutions (5-131. measuremenls estimated by using historical dala may not match
exacuy the real-time actual values. but they increase the data
9 4 WM 098-4 PWRS A paper recommended and approved redundancy of SE. If Uiis approach is adopted care must be taken
by the IEEE Power System Engineering Committee of the in assigning weights to various types of measurements.
IEEE Power Engineering Society for presentation at t h e Techniques lhai can be used to determine lhe meter or pseudo
IEEE/PES 1994 Winter Meeting, New York. New York,
January 30 - February 3, 1994. Manuscript submitted
measurement locations for oblaining a complete observability of
December 28, 1992; made available for printing the system are available in [17-211.
January 11, 1994 A three-phase SE algorithm based on normal equation
method is proposed in this paper. A new reclangular form SE
based on currenc instead of power, is introduced. The proposed
algorithm can be used U, handle many types of measuremenb. It
is applicable to the current magnitude measurements that are
often found in the distribution sysrem telemeuy. The three-phase
network models and mathematical formulation of the method are
described in this paper. The suitability of the proposed
0885-8950195/504.000 1994 IEEE
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
230
15
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
23 1
W k
2 = vector of measurements
X,Y = vectors of state variables
N = measurement noise 0 5 IO 15 20 25 30 35 40 45
h = functions relating state variables to measurements Bus No.
We choose bus voltages as state variables. We can choose Figure 4: Jacobian Matrix Structure
to express bus voltages in polar form (X=O and Y=IVI) or in
rectangular form (X=IVkosO and Y=IVlsinB). N is assumed to be
a Gaussian distribution with zero mean and variance 02.u - is~ 0
used to weight each individual measurement. More accurate
measurements will have lower 0 ' s . while the pseudo 10
measurements are assigned with higher U'S to highlight the lower 20
confidence given to these measurements. The noise elements are
assumed to be independent. Let R be the covariance of N, then 0 30
z
~ i= iai2, the variance of the i-th measurement. 3 40
Weighted Least Square (WLS) estimation computes the 'E 50
>
state variable vectors X and Y which minimize the following
function 1*
wY 70
J(X,Y) = l12[Z-h(X,Y)lTR-1[Z-h(X,Y)] (2) 80
J(X,Y) is minimized by differentiating it with respect to X on
and Y,and setting the resulting nonlinear equation to zero. 'hen 0 IO 20 30 40 50 60 70 80 90
the nonlinear equation is solved iteratively by Newton's method. Slate Variable No.
Let Hi bethe measurement Jacobian matrix at the i-th iteration,
then update of the state variables can be found by solving the Figure 5: Gain Matrix Structure
following equation
Current Based SE Formulation
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
232
where Gkm + JBkm = Ykm, Gmand Bkm are 3x3 block
elements of nodal admittance matrix. Since the current injection
at phase-a of Figure 3 can be expressed in rectangular form as :
I' a = .@ s ( e a - e a . ) - b , ( f a - f , . ) + g a b ( e b - e b . )
-b ab (f b -fb,)+g,(ec-ec.)-b,(fc-fc.)l
Where ej. fj. Ijr and Iji are 3x1 vectors. Using the same idea, if
we converl other types of measurements, such as branch power
flows and current magnitudes, into equivalent currents and
expressed them in rectangular form then the Jacobian terns of
these measurements are constant and equal to the branch
admittances.
Polar form Rectangular form With these background in hand, let's see how to find the
equivalent currents of branch power flow and bus injection
These power measurement Jacobian terms are state dependent, measurements. The branch power flow measurements P h m e a
i.e., they have to be. computed in each iteration of SE.
The Jacobian terms of bus current injections with respect and &,mea can be converted into measurement equivalent
to node voltages exp :ssedin rectangular form are as follows: current I h m e a ~ by
v the following equation:
m
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
233
Observability Analysis
ad
= Re(Ihmea-W) + j h(1hmea-W') (10)
0.2352+p.6561 2.7871 +jl.4761 0.2352+p.6561
0.2334 +j0.5827 0.2352 + j0.6561 2.7834 + 11.4794
I
No. of
Actual
Measure-
rnents
1
calculated currents IC', measurement Jacobian matrix H, and the
covariance matrix R are used to compute the right-hand side
vector of Equation (3). In addition to power and current
measurements, the voltage magnitude measurements, Equation 93
(11). can also be used. The first derivative of equivalent voltage 48 12
expressed in rectangular form with respect to the state variable is 48 18
unity. Based on constant Jacobian matrix H, the gain matrix
HTR-lH is constant, and it needs to be built and factorized only
once. Great improvement in the SE execution time can be
obtained by using this new scheme. Figure 7 shows the flow
diagram of the proposed three-phase SE algorithm.
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
234
SE formulation (method 3) has the best performance in all tests
Estlmatc pseudo measurcmcnts conducted. Iteration number required by the decoupled version is
at distnbuuon bansformers
higher. Test results indicate that the decoupled formulation has
& difficulty in handling current magnitude measurements. Fully
coupled formulation is more stable than the decoupled
Assign weights for pseudo formulation. It is also shown in Table 2 that if the measurement
mCaSurcments
set includes current magnitude measurements, all three
4 formulations require a higher execution time to obtain the
solution. This is due to the lack of phase information in the
Use equations (5).(7).(9),(IO).( I t ) IO
convert mcaswmcnts data into current magnitude measurements.
equivalent mcajurements expressed in During the testing of the proposed method, it was found
rectangular form that if the current magnitude measurements that have high
Jm weights are involved. a special procedure should be followed
when a flat s m is used. From equations (9) and (10). i t can be
Compute and factorize the gain seen that the equivalent complex currents obmned from a flat
matrix
start would be far away from the solution. this might result in a
convergence to an incorrect solution. To resolve this problem, a
tentative solution obtained by greally reducing the weights of
current magnitude measuements in the first and second ilerations
nght-hand side vector of equauon (3) of SE, is found first. After that the weights of current magnitude
measurements are restored back to their original values, and the
+ solution procedure continues. For instance. in Table 3, for the
case of 60 bus system with current measurements, i t requires two
Solve equation (3) and update (X,Y) iterations to obtain the tentative solution and another three
iterations to get the final solution. In this case. the gain matrix
needs to be built and factonzed twice. Using this procedure. it
seems that method 3 handles current magnitude measurements
more effectively than other methods. The above mentioned
procedure is not required if no current magnitude measurement is
involved or when a previous SE solution is available.
Table 4 shows the final J(X) values of the reponed cases.
A,
Since method 3 has converted the power measurements into the
equivalent current measurements. the equation used to calculate
the J(x) is redefned as:
The measurement data are simulated by using a three-phase The a's used in the above cquauon are computed from a's of real
load flow solution. Noise is added to each measurement and and reacuve power measurements
weights of measurements are given. Noise is added randomly to Table 5 shows the deviauons of the estimated solution
the actual and pseudo measurements and is at the ranges of *IO% from the load flou solution which is used to probide the
and f30% respectively. Two different weights are given to the measuremen1dam The demauon is defined as
measurements, one for the actual measurementsand the other one
for the pseudo measurements. The weights are 1/3 and 1/50
respectively.
Three different methods are tested, they are :
Method 1 : Fully coupled version of normal equation method
expressed in polar form.
Method 2 : Decoupled version of normal equation method
expressed in polar form. where PkmSe is Ihe estimated branch flow and pkmload is
Method 3 :The proposed current based method. the corresponding value in the load flow solution. I t should be
In method 2, tbe gain matrix is approximated by a block reminded that since measurement noise is included randomly iii
diagonal matrix, i. e. ignoring the off-diagonal terms to get the the measurements. 2 1070. and 230% respectively for actual and
decoupled gain matrices correspondingto real and reactive power, pseudo measurements, thc final SE solutions will not be the
thus, decoupling the angle and voltage components. Various tests same as the load flow solution. The results shown in Table 5
which use different types and numbers of measurements are indicate that even with only the pseudo measuremen& the
conducted. Some of them are reported here. Tests are conducted proposed algorithm can provide an S E solution. However, due to
on a SUN IPC workstation. Tables 2 and 3 show the normalized the low accuracy of me pseudo measurements. the solution is bad
execution time and number of iterations required in each case.NC when we compare i t with the base case load flow solution. This
indicates the non-converged case. In addition to voltage estimated solution can be improved by adding real-time
magnitude measurements, two types of actual measurements are measurements to the measurement set. As can be seen from
tested, they are the power flow measurements and iurrcnt Table 5, cases with higher number of actual measurements have
magnitude measurements. The execution time of method 3 with lower deviations, i.e.. they match more closely with the assumed
P, Q measurements is used as a reference and normalized to 1. real-time solution. Test results have indicated that when current
It can be seen from Tables 2 and 3 that the current based
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
magnitude measurements are involved, due to the lack of phase
information. the deviations are higher, but the percentage
differences between different methods are still small.
To verify that all three formulations have the simi!ar
solutions, using the solution obtained from method 1 as a
reference. we compute the summation of differences in branch
flows of solutions obtained from different methods. It was found
that the differences of the case of 60 bus system with only
pseudo measurements are within 1.1%. When the real-time
measurements are added. the deviations are within 0.4%. This
result indicates that the three tested methods did not converge
exactly to the same solution, but they have very similar
solutions.
With the aid of the actual measurements the proposed
distribution system SE is able to provide a load flow solution for
real-time operation. An accurate real-time update of the bus load
forecast can also be performed by using SE solution.
It can be seen from Figure 5 that the gain mamx is sparse,
thus, sparse maUix technique should be used in solving the
problem. Since individual feeder SE can be handled separately and
the problem size is generally small, the distribution system SE Soluliaos wtlb only p c u d o Solutlws wilh re~l-lmmcand pseudo
can be performed on smaller machines or processed mesiurernenli measuremenis
Method M e l b o d M e ~ D o d M i l h o d Mclbod Melhod Number
simultaneously by different machines. The tests are also 1 2 3 I 2 3 OlFrLIS
conducted on a 486 PC and similar results have been obtained. 12.514 14 I14 13.584 I82S8 2.224% 2.195% 5
% e %
13 SU4 11126 2.1WB 2.0378 10
Table 2: Normalized Execution Time 12.514
e
14 I 1 4
e e
-mcnts
p,~' 1.900 1.450 1.000 4
15 BUS Plows 1.900 1.450 1.050 6
ancal+ 3.050 PE 2.150 4
3.100 PE 2.150 6
Execution PO' 2.071 1.119 1.000 5
No. of
Ilcralioas 7. REFERENCES
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
1984. "State Estimator Measurement System Reliability
D. I. H. Sun, Distribution System Loss Analysis and Evaluation - An Efficient Algorithm Based on Topological
Optimal planning, Ph. D. Dissertation, University of Observability Theory," IEEE Trans. on Power Apparatus
Texas at Arlington, May 1980. and Systems, April 1982, pp. 997-1004.
D. I. H. Sun, S. Abe, R. R. Shoults, M. S . Chen, P.
Eichenberger, D. Farris, "Calculation of Energy Losses in Chan-Nan Lu received B.S. degree from National Taiwan
a Distribution System," IEEE Trans. on Power Apparatus University, M.S. degree from Rensselaer Polytechnic Institute,
and Systems, Vol. PAS-90, No. 4, pp. 1347-1356, and Ph. D. degree from Purdue University. He has held positions
July/Aug 1980. at General Electric Co. Pittsfield. Mass., and Harris Corp.
N. Vempati, R. R. Shoults. M. S . Chen, L Schwobel, Controls and Composition Division, Melbourne, FI.. Currently.
"SimplifiedFeeder Modeling for Load Flow Calculations," he is with Department of Electrical Engineering. National Sun
IEEE Trans. on Power Systems, Vol. PWRS-2, No. 1, Yat-Sen University, Kaohsiung, Taiwan. He is a senior member
Feb. 1987, pp. 168-174. of IEEE.
T.-H. Chen, M.-S. Chen K.-J. Hwang, P. Kotas, and E.
A. Chebli, "Distribution System Power Flow Analysis - J. H. Teng received his BS and MS degrees froin National Sun
A Rigid Approach," LEE Trans. on Power Delivery, Vol. Yat-Sen University in 1991 and 1993. Currently, he is pursuing
,NO. 3, July 1981, pp.1146-1152. his PH. D degree in the same University.
K. A. Birt, J. J . Graffy, J. D. McDonald, and A. H. El-
Abiad," Three phase load flow program," IEEE Trans. on W.-H. Edwin I.iu received the B.S. degree from National
Power Apparatus and Systems, Vol. PAS-95, No. 1, Taiwan University in 1981, the M.S. degree in 1984 and Ph.D.
Jan/Feb 1976, pp. 59-65. degree in 1987 bo& from the University of California Berkeley,
M. E. Baran, F. F. Wu, "Network Reconfiguration in in Electrical Engineering and Computer Sciences. He was a
Distribution System for Loss Reduction and Load research assistant at U. C. Berkeley from 1983 to 1987 and
Balancing," IEEE Trans. on Power Delivery, Vol. 4, No. worked for Bonneville Power Administration during the Summer
2, pp. 1401-1407, 1989. of 1986. From September 1987 to June 1991, he worked for
C. C. Liu, S. 1. Lee, K. Vu, "Loss Minimization of Empros Systems International as a Senior Engineer in the
Distribution Feeder: Optimality and Algorithm," IEEE Network Applica*ion group and developed solfware for power
Trans. on Power Delivery, Vol. 4, No. 2, pp. 1281-1289. system computer applications. Since J u l y 1991, he has been
1989. with the Applications and Systems Integration Department of
H. D. Chiang. R. J. Jumeau, "Optimal Network PG&E where he is respondible for several research and
Reconfigurations in Distribution Systems: Pan 1: a New development projecls in both analytical melhodology and
Formulation and a Solution Methodology," IEEE Trans. computer applicauons. Dr. Liu also leaches graduate courses in
on Power Delivery, Vol. 5, No. 4. pp. 1902-1909, 1990. the Engineering Division of San Francisco S w e University.
C. S. Chen, and M. Y. Cho, "Determination of Critical
Switches in Distribution System,'' IEEE Trans. on Power
Delivery, Vol. 7, No. 3, July 1992. pp. 143-1449,
"Distribution Automation: A practical tool for shspinp a
more profitable future," Special Report, Electrical World,
Dec. 1986, pp. 43-50.
F. F. Wu and A. F. Neyer, "Asynchronous Distributed
State Estimation for Power Distribution Systems."
Proceeding of 10th Power Systems Computation
Conference, Aug. 1990.
I. Roytelman, and S. M. Shahidehpour, "State Estimation
for Electric Power Distribution Systems in Quasi Real-
Time Conditions," EEE paper 93 WM 090-1 PWRD.
F. Mafaakher, A. Brameller, J. F. Bermudez, "Optimum
metering design using fast decoupled state estimator,"
IEEE Trans. on Power Apparatus and Systems, Vol. PAS-
98, Jan. 1979, pp. 62-68.
K. A. Clement, G. R. Krumpholz, P. W. Davis, "Power
system slate estimation with measurement deficiency: an
observability measurement placement algorithm," IEEE
Trans. on Power Apparatus and Systems, Vol. PAS-102,
July, 1983, pp. 2012-2020.
M. K. Celik, and W.-H. E. Liu, "A Meter Placement
Algorithm for the Enhancement of State Estimation
Function in an Energy Management System," Paper
prepared for the Third International Symposium on
Electricity Distribution and Energy Management, 1993.
A. Monticelli and F. F. Wu, "Network Observability:
Identification of Observable Islands and Measurement
Placement," IEEE Trans. on Power Apparatus and
Systems, Vol. PAS-104, May 1985, pp. 1035-1041.
K. A. Clement, G. R. Krumpholz, and P. W. Davis,
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
237
The authors assume that the phase angles of voltages are less than 10
degrees. Our experience with distribution systems indicates that this
assumption is correct only for the primary voltage level and in cable
I. Roytelman (SiemensEmprus) and S.M. Shahidehpour (Illinois systems. Since loads are connected to the secondary voltage level,
Institute of Technology)-- The topic of this paper is extremely distribution transformers voltage drop should be. taken into account.
important from the standpoint of future development of distribution In heavily loaded overhead lines, line voltage drop gives additional
management systems. The authors have proposed the implementation angle shift. These assumptions may provide a more simple model for
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
238
distribution systems, however, the simulation results may turn out to Let
be different from actual practice.
5. Test results:
Manuscript receivrd March 4, 1994. In the case where Var(P) = Var(Q), the equations can
be simplified as
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
239
iterative process. Based on our experience, slight 3. State estimation can provide a good estimate of the
approximation in the variances (i.e. weights) does not system states that can then be used by many
affect the estimation solutions too much. In order to distribution automation applications, such as feeder
validate the approximation, a 15-bus system example is reconfiguration, v o l t a g e h a r control, etc.. T h e
tested under various conditions, and results are shown usefulness of these applications requires a reasonable
in the following Table. accurate estimate of the system states. As can be seen
~~~~ ~~ ~~~ ~
in the paper, the quality of the forecasted load data are
-Weights Method 1 Method 3 improved by the distribution state estimation using
est
-15.7151
P5a,mea- p=2
Q=2
P~~ ~ 14.20619 P5aest = 14.2041 available real-time measurements. The state estimation
est
Q5a = 2.45973 Q5= est = 2.47091 can be used to check the validity of the forecasted load
p5= mea--3.10072 P=20 P5aest = 14.70647 PSaest - 14.7011
~
and to make necessary corrections. Hence, the system
Q.20
QSa
est
= 2.67225 Qsaest = 2.68437
states provided by state estimation is better than what
is available from an off-line power flow study.
P.200 Psa est 15.48135 P5aest =15.47671
Q=20
=
Furthermore, if more real-time measurements become
est
Q5a = 2.67230 Q5aest =2.68651 available in some key locations and the distribution
network becomes observable, the system states can be
mea: measurement estimated directly from the real-time data. This can
est: estimated value highly improve the solutions of all network applications.
A fully automated distribution system may become
Methods 1 and 3 correspond to the fully coupled polar feasible.
form method which uses the original measurements
and weights, and the proposed current based method,
respectively. Method 3 uses the above mentioned Drs Roytelman and Shahidehpour
method to determine the weights of equivalent
measurements. As can be seen from the Table, for 1. We agree that different model should be used if the
both methods, when the original weights are increased line under study does not have a multi-grounded neutral
(variances are decreased) the estimated injections which is the basic assumption of the Kron reduction
match the measurements more closely, and their method adopted in this paper.
results are very similar. Resembling results are
observed at different phases and nodes of the feeder. 2. In our method the current magnitude measurements
These results indicate that the measurement and are treated as regular measurements except for the
weight conversion is properly handled by the proposed special treatment in a flat start case. The estimated
method. phase angles of the corresponding branch currents are
obtained at each iteration of the estimation process. W e
Mr. Wayne Hong did not use current phase angle measurements in the
estimation.
1. Both [A] and our paper use weighted least square
technique and a three-phase model to estimate the 3. U n d e r t h e c i r c u m s t a n c e s that r e a l - t i m e
distribution system states. The major difference measurements are not sufficient for a state estimation,
between these two papers is in the approach used to any available historical data related to the feeder
obtain the constant gain matrix. In [A], some loading should be used as pseudo measurements.
approximations and transformation are used to simplify Certainly, due to different confidence on various
the Jacobian matrix while in our method, constant histoiical data, different weights are given to different
Jacobian matrix is obtained by converting power types of data. Since weight disparity has beeil identified
measurements into equivalent currents and expressing as one of the factors that could cause numerical
bus voltages in rectangular form. Both methods are problems in state estimation. The effects of weight
designed to provide an estimate of the real-time system assignment should be carefully investigated. In this
states for distribution system operation. paper, we do not explicitly address the issue of weight
assignment. The purpose of the paper is to present an
2. Due to the cost of measurement and communication effective formulation to solve distribution system state
equipments, real-time load data of each node in the estimation. Further research and development in many
feeder are not available at the present time. Load data important subjects in this area, such as meter
are often obtained based on historical data collected by placement, observability analysis, bad data processing,
utilities. Since these data are used in the estimation weights selection, etc., are certainly welcome.
process, thus, the accuracy of load data affects the
estimation of the real-time system states. Based on 4. In this paper we did not assume that the phase
some assumptions on the measurements and load data, angles of voltages are less than 10 degrees.
Table 5 provides some quantitative results of the errors
existing in the historical load data and the estimated 5. To be useful in the feeder automation, we tested the
results. proposed method on individual feeder. Since data
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.
240
Authorized licensed use limited to: INDIAN INSTITUTE OF TECHNOLOGY MADRAS. Downloaded on December 02,2023 at 19:24:55 UTC from IEEE Xplore. Restrictions apply.