Network Diagram Method and Precedence Diagram Method
Network Diagram Method and Precedence Diagram Method
C
B D
A F
C E
8
B D 6
4
5 A F
5 E
C 6
3
8
B D
4 6
PATH A-B-D-F = 23
5 A PATH A-C-E-F = 19 F
5 6
C E
3
EARLY START ACTIVITY LATE START
A F
5 6
C E
5 3
5 B 9 D
4 8
0 A 5 F
5 6
5 C 10 E
5 3
5 B 9 9 D 17
4 8
0 A 5 17 F 23
5 6
5 C 10 10 E 13
5 3
5 B 9 9 D 17
5 4 9 9 8 17
0 A 5 PATH A-B-D-F = 23 17 F 23
0 5 5 PATH A-C-E-F = 19 17 6 23
5 C 10 10 E 13
9 5 14 14 3 17
Example #2 USING ACTIVITY
A
PREDECESSOR DURATION
- 3
PDM B A 4
C A 2
D B 5
Determine the critical path of project.
E C 1
F C 2
G D,E 4
H F,G 3
B D G
4 5 4
A H
E
3 3
1
C
F
2
2
ACTIVITY PREDECESSOR DURATION
Example #2 USING PDM A - 3
B A 4
C A 2
PATH A-B-D-G-H
PATH A-C-E-G-H D B 5
PATCH A-C-F-H E C 1
F C 2
G D,E 4
H F,G 3
3 B 7 7 D 12 12 G 16
3 4 7 7 5 12 12 4 16
0 A 3 16 H 19
5 E 6
0 3 3 16 3 19
11 1 12
3 C 5
5 F 7
9 2 11
14 2 16