Project Execution Plan
Project Execution Plan
No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 1 of 35
CLIENT :
PROJECT NAME :
OUR PO NO : -
OUR WO NO : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 2 of 35
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 3 of 35
TABLE OF CONTENT
COVERING SHEET
TABULATION OF REVISED PAGES
TABLE OF CONTENT
1. PURPOSE ............................................................................................................ 6
2. SCOPE ............................................................................................................... 6
3. DEFINITION.......................................................................................................... 7
3.4. Resources..................................................................................................................................................... 8
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 4 of 35
4. REFERENCE ........................................................................................................ 9
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 5 of 35
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 6 of 35
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 7 of 35
1. PURPOSE
This project execution plan prepared for PHE OSES – Fabrication of Demulsifier Separator Vessel V -1400. It
is intended to enhance communication and coordination of project activities between Company and
Subcontractor.
The Company is PHE OSES
The Client is PHE OSES
The Contractor is Consortium of PT. Asiaserv Indonesia and PT. Surya Besindo
Sakti
This procedure serves as a project guideline for all parties to achieve effective and efficient project
implementation. The primary uses of the project plan are to document planning assumptions and decisions,
to facilitate communication among stakeholders, and to document approved scope, cost and schedule
baseline. This procedure describes the basic and method to be used in controlling the cost through out
the project period, to detect the variance by identifying potential problem and delay as early as possible. This
procedure describes the basis and method to be used in controlling the schedule throughout the project
period, to detect the variance by identifying potential problem and delay as early as possible.
2. SCOPE
This procedure covers detail of Project Execution Plan based on the latest project information. This
document is developed to enhance communication and coordination between the participants and/or the
company. It establishes project execution plant with the following item:
Project Management and Project Control scheme
Engineering Management Plan
Procurement Management Plan
Logistic Management Plan
Construction Management Plan
Labor Recruitment & Labor Relation Plan
Front End Schedule
Project Schedule
Resources Plan
Project Budged
Project Cash Flow
Project Procedure
Data Collection
Input Data into Report
Varian Analysis
Corrective Action
Budget Revision
Update Current Budget
Update Total Expense To Date
Update Total Actual To Date
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 8 of 35
Calculate Forecast To Go
Update Estimate at Completion
Update Project Cash Flow
Update Project Balance
3. DEFINITION
The detail-planned dates for performing activities and the planned dates for meeting milestone, used
as a project control tool.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 9 of 35
3.4. Resources
The manpower, equipment and material required for project in achieving its objective
and implementation.
The real cost for implementing the project, which comes from contract price minus overhead cost,
profit, marketing expenses, corporate cost and contingencies, approved by Vice President and
Operation Manager.
A process of keeping cost within the bounds of budget or standard based upon work
actually performed, including monitoring actual versus budget, variance analysis, integrated
cost/schedule reporting, progress analysis and corrective action.
3.14. Forecast to Go
Predicted cost for finishing the remaining work.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 10 of 35
Support to level-1 work unit that covers all activities using PERT method, showing the critical
path and floats in daily basis.
3.20. Progress
Actual work completed divided by total scope of work. Physical progress measurement is
determined on monthly basis at the monthly cut off date for all specific work units and for the overall
work, the weight of each specific work unit being proportional to its cost value
3.21. Baseline
The original plan ( a project work package or an activity ) plus or minus approved changes. Usually
used with a modifier (e.g., cost baseline, schedule baseline, performance measurement baseline).
4. REFERENCE
These procedure developed refer to the following document :
Quality Manual
Project Management Guideline Procedure
Project Execution Plan Procedure
Project Schedule Control Procedure
Project Progress Report Procedure
Project Change Management Procedure
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 11 of 35
5.1. General
Upon completion of Internal Kick off meeting, Project Manager (PM) and project team coinciding with
the preparation of Client Kick off meeting will review and complete the Project Execution Plan (PEP),
to ensure its completeness and accuracy for field implementation. In case of limited time to prepare
both Client Kick off meeting and PEP, PM should attempt to accelerate the preparation work.
The schedule described in contract document is defined as Master Schedule and become the
original summarized schedule (level 2 or 3). The amount stated in the contract is known as Contract
Price. The real cost for implementing the project named project budget, is the contract price
minus overhead cost, profit, marketing expenses, corporate cost and contingencies.
Due to the wide scope as well as technical challenges, the subcontractor intends to
implements a project organization task force. By this organization all resources needed to
accomplish project will be assigned full time in strict accordance their rule and responsibility for
successful of project. Set up a project organization and its responsibility as following.
Project Manager : who is the number one manager in this project has responsibilities as
follows:
Review and complete the Project Execution Plan
Collect all information related to the Project Execution Plan
Subcontractor contact person / decision maker related to the project
Review and approve Front End Schedule
Review and approve Project Schedule
Review and approve Resources Plan
Complete, review and approve Project Execution Plan Check List
Review and approve Project Plan according to procedure approval process
Monitoring and control of the project cost
Implementation of the project according to the schedule
Liaison with the Company and obtaining necessary information from the owner and
vendors and feeding in the engineering, procurement and construction section
Coordination developing and compiling all project documents as per the agreed documents
list and coordinating with the Company for approval of all relevant documents
Coordination mobilizing requires for maintaining schedule
Coordination Procurement of all items
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 12 of 35
Project Control Manager : who is a manager that has almost all of the project information
has responsibility as follows:
Coordinate Preparing summarize Front End Schedule
Coordinate Preparing summarize Project Schedule
Coordinate Update summarize Resources Plan
Coordinate Update summarize Project Budget
Coordinate Preparing Projected Cash Flow
Coordinate Scheduler and Reporting
Collect all information related to the PEP
Coordinate Prepare detail Front End Schedule
Coordinate Prepare detail Project Schedule
Update manpower, material and equipment plan (detail resources plan)
Update detail Project Budget
Review and complete Project Execution Procedure Check List
Coordinate Preparing and finalizing Project Procedure according to procedure approval
process
Determine the schedule recovery and re-schedule, together with Project Manager
Ensure that all on-going projects are within the schedule
Provide variance analysis and recommend necessary corrective action
Review the proposal budget revision
Update project cash flow
Update project balance
Project Control Engineer : who is the supporting engineer to Project Control Manager has
responsibility as follows:
Input data into monthly cost summary report and project cost status report
Provide variance analysis and recommend necessary corrective action
Prepare budget revision
Update current budget
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 13 of 35
5.2.2.1. Introduction
This section is implemented for correspondence between Company and
Subcontractor.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 14 of 35
prepared and distributed to the parties involved in the telephone discussion with copies to other
parties, as required.
5.2.3.1. Introduction
Project documents to be controlled include official project correspondence, memoranda,
calculations, drawings, design specifications, test records, manufacturer's material certifications
, manufacture's drawing and other such records. Document control procedures are based on the
project file system developed under the supervision of Project Control.
5.2.3.2. Administration
Project Control shall serve as the central point of project document control and shall process or
supervise the processing of documents from outside sources as well as documents generated
from consortium internal distribution or transmitted by Subcontractor to outside sources. The
activities include receiving, application of file numbers, distributing, expediting and releasing all
project documents.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 15 of 35
package shall be returned to Project Control for transmittal of the action and information
copies, and filling of original documents.
Each consortium member shall be responsible for getting approval to own drawing from
Company through Subcontractor Engineering Manager. When distribute the drawing packet to
Company, each consortium member or Supplier shall send a copy of the drawing to Project
Control for drawing control.
5.3.1.1. Introduction
The subcontractor will issue Project Quality Assurance Plan to assure all material,
equipment, fabrication and installation process fulfill the project requirement by referring
to the Quality System requirement. The Document is model of Project Quality Plan that
will be used by subcontractor during perform The Project.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 16 of 35
5.3.1.2. Purpose
This document will describe The Quality System, and subcontractor to assure the
Project requirement will do activities and Quality Standard will be fulfilled. Referring to
The Quality System of subcontractor will develop Project Quality Plan.
5.3.1.3. Terminology
Vendor : The companies that appointed by subcontractor and approved by
subcontractor/company to supply part of product and perform part of subcontractor
scope of work or services for this project purpose.
Project QA/QC Manager under controlled by Project Manager will report The
Project Quality System implementation to QA/QC Division Manager.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 17 of 35
5.3.1.7.1. Responsibilities
Engineering Manager has responsible to control all engineering activities.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 18 of 35
Engineering Manager will approve the design out put to make sure the design
procedure have been followed and approved by authorized personnel and
distributed to other related departments.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 19 of 35
observed by relevant department and design change not deviate from project
contract requirement.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 20 of 35
5.3.1.11.1. Organization
Inspection activities will be performed by personnel that have been
qualified and controlled by Quality Assurance / Quality Control Department.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 21 of 35
Quality Assurance / Quality Control Manager and Logistic Manager will arrange
and supervise inspection activities during receiving material on site to identify
and check the material or equipment condition. Inspection result will be
recorded and reported to Site Manager. Non-conformity was found during
receiving material process will be reported to Project Engineering Manager for
take corrective action.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 22 of 35
5.3.2.1. Introduction
Quality Assurance / Quality Control Department will prepare Quality Control guidance of material
and equipments inspection that will be used during fabrication and repair work.
5.3.2.2. Purpose
Project Quality Control Plan describe work methods and inspection activities as mentioned on
Quality Project requirement. Project Quality control Plan, Inspection & Test Plan and Quality
Control procedure will be prepared to provide inspection activities as mentioned below:
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 23 of 35
5.3.2.3. Terminology
Any terminology related to QC Management plan described as
follows :
Vendor : The company that appointed by subcontractor and approved by
company to supply part of product, performed part of subcontractor scope of work
or services for this project purpose.
Third Party: Subcontractor subcontracted inspection company approved and
appointed to act on behalf of Migas.
5.3.2.4. Responsibility
Responsibility each member described as follows :
Quality Assurance / Quality Control Manager has
responsible:
Ensure that Project Quality Control Plan conform to quality project requirement.
Quality Assurance / Quality Control Department representative to make
coordination with another department during perform the project.
Inspector : Perform Quality Control activities as mentioned on the Inspection and Test
Plan, including internal test and inspection or witnessed by company, prepare and
review inspection and test record.
Document Control : To assist and support Quality Assurance / Quality Control
Manager in the administration and documentation matter.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 24 of 35
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 25 of 35
Repair / rework was need , for pressure vessel that have been
tested on shop.
Subcontractor will propose corrective action to get company
approval.
Design change request
If during construction process found the items cannot be done, or will obstruct
to another facilities, so the construction process will deviate from approval
drawing, the subcontractor will propose the design change to get company
approval.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 26 of 35
5.4.1. Introduction
The aim of emphasize of the Roll and Financial Management plan is to formulate and
recommend steps to be taken by the Project Manager related to the Integrated Tank Repair
Project, particularly to the preparation of planning, implementation and control. The formulation
of financial management plan could be described as follow.
GOAL
FINANCIAL VISION
To Support Project Execution FIGURE SCHEME
OF ROLL AND
FINANCIAL
MANAGEMENT
FINANCIAL MISSION
STRATEGY
Professionalisme of Efficiently Increase of Service
Man Power Organization
FINANCIAL FUNCTION
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 27 of 35
FINANCIAL FUNCTION
ADJUSTMENT/REPLANNING CONTROL /
OF BUDGET TO MEET THE RESULT
QCD TARGET QCD = PLAN
NO
YES
QCD =
PLANNING
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 28 of 35
5.5.1. Introduction
The successful of project implementation is depend in to how to manage the risk's during project
execution, so this risks project Management plan is to provide a management to take any
necessary action based on some factors such as:
Unit price factor
Work volume ( BQ ) factor
Work Schedule factor
Exchange rate factor
Damage factor
Engineering Manager shall manage all engineering activities within this project and
responsible to Project Manager.
Discipline Engineer
Engineer shall do the design each discipline under the coordination of Lead Discipline
Engineer.
Field Engineer
Field Engineer shall support construction activities, accommodate all modification done on
site and implemented those modifications to marked drawings will informed to Discipline
Engineer through Engineering Manager.
Draftsman
Draftsman shall make the drawing and coordinated by Discipline
Engineer.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 29 of 35
Document Control officer also shall act as the central point of engineering document as well as
documents generated from internal subcontractor or transmitted by Company. The activities
include receiving, application of file number, distributing, expediting and releasing all engineering
documents to assure that the document will receiving by related section in same version.
Documents Receipt
Documents may be received from outside sources such as Company and NA or
others.
Document Identification
All engineering mail, including e-mail, telecopy, telegrams and package shall be
identified.
The Document Control shall process the original copy of each incoming document, other than
documents submitted in multiple copies (proposal, instruction manual, etc.) and the
transmittal letter or form for documents submitted in multiple copies.
Identifying shall include stamping document with the engineering routing stamp, dating the
receipt, marking the appropriate file number and indicating action and information parties in
the space provide on the routing stamp, and making required copies for action and
information parties. All documents should use numbering system as per attachment
Document Traffic
The copy of documents transmitted to the responsible action party shall be marked with the
word
ACTION and route directly to the action
party.
The responsible engineer is responsible to review the document and provide the action as
required. The responsible engineer could get additional information from other Lead engineer
under coordination of the engineering manager.
Outgoing Documents
Document Control shall record and forward documents include verification of file numbers,
preparation of documents for mailing, completion of Engineering internal distribution and
distribution of copies to the engineering file.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 30 of 35
5.7.1. Introduction
In order to achieve the aim of project, the procurement section shall be divided into four sub
sections as on organization chart.
Procurement Manager
Procurement Manager has responsible for the procurement of all material,
equipment, electrical and instrumentation as required.
Procurement Manager shall manage all procurement activities and responsible for all
material supplied has bought and ready for installation and construction.
Procurement Manager shall sign all correspondence of procurement activities.
Purchasing Officer
Material requisition for quotation to vendor for sourcing.
Evaluation, clarification and negotiation of quotation with vendor.
Issuing LOI or P/O and inform to QC and traffic for preparing.
Verification of vendor invoice.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 31 of 35
5.8.3. Warehouse
Indoor warehouse is storage place to protect of material, tools and consumables from weather to
prevent material from damage or corrosive.
All material, tools etc should be identified base on its type & size, prior stored on the racks or put
on the floor according to storage system at warehouse as
below
Equipment for large size as panels, pumps, generator power, fittings etc should be stored on the
floor indoor and its gave distance from the floor around 15 cm.
Inflammable material as chemical liquid, painting, gas bottles should be stored at special
place.
This HES Management Plan provides for employees and subcontractors with the basic safety
operating guidelines and rules to be used in their daily activities. The primary objective is to
document the common safety and occupational health guidelines and rules that form the
foundation of all Subcontractor activities, in compliance with the requirements of government
and Company regulations.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 32 of 35
The purpose of this HES Management Plan covers all safety requirements, identify the steps to be
taken by Subcontractor so as to safeguard health and welfare of all Subcontractor employees and
achieve the standards required under the Company safety procedures.
5.10.2. Facility
1. Handy Talky
2. Fire Extinguisher
3. Fire Protection & Breathing Apparatus
4. Pick Up Mobile
5. Etc
5.10.3. Location
1. Office
2. Project Area
3. Etc
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 33 of 35
Each project discipline will breakdown the activities in Mater Schedule by top-down approach into a
detail activities , determine dependencies and estimate the duration for each activities (see Work
Breakdown Structure describing the detail activity for , up to level 3 (sub-system)). Project Control
assisted by each project discipline will summarize the detailed activities and check the front end
schedule then compare the summarized duration with the total duration of a given activities in the
master schedule. Project Manager will review the front end schedule and finalize it for approval , see
attachment.
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 34 of 35
The project budget which has already been defined by management is now used for internal
purposes. PM should detail the project budget according to the following steps.
Project Manager and Project Team Member collect information such as:
project schedule
CPM budgeting structure
breakdown of contract price
calculation of cost estimate for each activities during bid preparation:
Project Management which consist of Project Supervision, Procurement Services, Accounting
Services, Bid Cost and Running Cost
Engineering
Supplies, usually known as material
Transport, usually known as material handling and equipment
subcontractor
Direct Manpower
Site Expenses consist of Administration & Supervision Expenses, Internal/External Equipment
Rental & Spare Parts, Small Tools, Consumables, Spare Parts, etc
Commissioning & Start Up
Other Charges
Estimate Summary Form which is the total calculation of all cost estimate for each activities
Based on the above information, Project Control assisted by each discipline will detail the project
budget for each activities and prepare the Project Execution Budget Summary Form. The cost code
is always prefixed with the project number followed by project cost account number.
Project Manager shall review the Project Execution Budget and finalize for approval.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 35 of 35
Base on the above information, Project Control shall prepare Projected Cash In Flow with
the following step:
In the absence of a cut off date specified in contract document, Project Control
shall determine the Cut off Date for Monthly Report along the project period and propose to
the Client.
Check the contract document regarding the statement of period time between the
issuance of invoice up to the payment from Client, for example, the payment is at least
one month after the received invoice.
Estimate the overall plan progress in every cut off date base on the schedule and budget.
Estimate the total amount of the invoice in every cut off date and when it will be
paid/transferred by the Client.
Check if there is a reduction cost upon the progress claim.
Estimate the total cash in flow in every month for every project cost account
Project Control shall also prepare Projected Cash Out Flow with the following
steps:
Based on the breakdown of project budget, Project Control shall estimate the cost out
for every item of cost account .
For project management, the value of manpower is to multiply the total man-hour/man-
month by weight rate from those manpower, and the value of expenses is base on project
budget that is distributed each monthly accordance to the schedule.
For engineering, the value of manpower is same as manpower of project management and
the value of expense is same as expenses of project management.
For supplies/material, the value is the percentage of payment (term of payment) by
budget for every material. Check also when it will be paid/transferred by the Client.
Doc. No : -
Rev. No : 0
PROJECT EXECUTION PLAN
Page No : 36 of 35
For transport, the value is based on project budget that is distributed into each month in
accordance with the schedule of material and equipment.
For subcontract, this is the same as material notice the percentage of payment is depend on
the subcontract’s progress in each month.
For site expenses, the value of construction equipment is same as subcontractor, the
value of small tools/consumable is same as supplies and the value of expenses is same as
expenses of project management
For commissioning & start up, the value of personnel is same as manpower, the value
of tools/consumables is same as supplies and the value of expenses is same as expenses
of project management.
For other charges, the value is same expenses of project management.
Estimate the total cash out flow in every month for every project cost account
Project Control shall summarize the total cash in flow and cash out flow into Projected Cash
Flow
Form. Project Manager shall review the Projected Cash Flow and finalize for
approval.