1) The document describes the construction details for external and internal strip foundations. 2) For the external strips, it outlines excavating cotton soil, laying 50mm thick lean concrete blinding, and casting 300mm thick reinforced concrete. 3) For the internal strips, it specifies excavating 300mm deep, installing 50mm quarry dust blinding and 250mm compacted hardcore, and constructing a 200mm thick stone wall.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
69 views1 page

Antony Muindi Foundation

1) The document describes the construction details for external and internal strip foundations. 2) For the external strips, it outlines excavating cotton soil, laying 50mm thick lean concrete blinding, and casting 300mm thick reinforced concrete. 3) For the internal strips, it specifies excavating 300mm deep, installing 50mm quarry dust blinding and 250mm compacted hardcore, and constructing a 200mm thick stone wall.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

EXTERNAL STRIP DETAILS INTERNAL STRIP DETAILS

A 4T10-100-B2-02 B 4T10-100-B2-02

T10-300-B1-01
T10-300-B1-01

Plan Plan
A CONSTRUCTION NOTES
1.Mass excavate and remove cotton soil from the building
B
area and dump to spoil for later use.
2.From the excavated level, excavate 300mm deep for the
200x350mm Ground Beam 200x350mm Ground Beam
150 mm thick floor slab strip foundations. 150 mm thick floor slab
4T12 4T12-02
with A142 BRC and dump 3.Prepare and cast 50mm thick lean concrete to the strip with A142 BRC and dump
T8-300-Ring proof membrane 1000 T8-300-Ring proof membrane 1000
Gauge. foundation as blinding. Gauge.
4.Prepare and cast 300mm thick reinforced concrete class
50 150

150
300
350

GL- Level C20-25 to the foundations.

350

50
5.Prepare and place in 25mm thick mortar joint the natural
foundation stone to the structural engineer's approval.
50 mm Quarry Dust Blinding 50 mm Quarry Dust Blinding
250mm Compacted Hardcore 250mm Compacted Hardcore

1200
200mm thick stone wall 200mm thick Stone wall

T10-300-B1-03 T10-300-B1-03
4T10-100-B1 02 4T10-100-B1 02
300

300
50
STRIP FOUNDATION
50

50mm Conc. blinding 50mm Conc. blinding

Section A-A
600
SECTIONS Section B-B
600

(Scale 1:100)
Scale 1:25 Scale 1:25
GENERAL NOTES DRAWN BY: K.A. MARK MADE BY REVISIONS DATE ISSUE
CLIENT
1. All dimensions are in millimeters, unless otherwise stated. 5. The site to be cleared of cotton soil to reduced level before construction.
STRUCTURAL ENGINEER CHECKED BY: ENG. A.O.
2. Only figured dimensions are to be taken from this drawing. 6. Concrete strength to be of class C25/20 unless otherwise stated. MR. ANTONY MUINDI
3. The drawing is to be read in conjunction with the relevant
Gent Consulting Engineers PO BOX ........................ DATE CHECKED: .........................................
7. Deformed ribbed reinforcement bars are to BS4449.
architectural drawings. 8. All the steel reinforcements to be approved by the Structural Engineer.
NAIROBI DRAWING. SCALE: AS SHOWN
4. Cover to reinforcement to be as follows: 9. Foundations to be excavated to rock or stable ground as may be approved by DRAWING NO.
Slabs - 20mm Structural Engineer PROJECT DRAWING TITLE
DWG. 2024-01-18
Beams - 25mm 10. All construction levels to be approved by Structural Engineer. PROPOSED RESIDENTIAL DEVELOPMENT ON PLOT NO. FOUNDATION - STRIP FOOTING RC SHEET NO. SHEET SIZE
Columns - 25mm 11. Any discrepancies to be reported to Structural Engineer. MALILI TOWN MAKUENI COUNTY SECTIONS DETAILS A3
Foundations - 50mm
SHEET 1 of 1 ISO 420x297mm