Tutorial Earned Value Question
Tutorial Earned Value Question
Group:
Damai Sdn Bhd has awarded a contract for the production of LED Advertising Screen to
company Gembira Sdn Bhd .
- LED Screen for Advert A at the rate of 100 per month and
A quick glance reveals that you budgeted RM200 a copy for LED Screen for Advert A
(RM100,000 / 500 copies)
Suppose it’s the end of March, and you’re three months into the project. Here’s what has
happened as of March 31:
1. Determine the planned value (PV), earned value (EV), and actual cost (AC) for
Brochure A and explain your results
PV = RM200 per LED Screen × 100 LED Screen per month × 3 months = RM60,000
AC = RM45,000
2. Determine the schedule variance (SV), cost variance (CV), schedule performance
index (SPI), and cost performance index (CPI) for the production of LED Screen for
Advert A. Explain your results
3. Use SPI to estimate the completion time and how much longer it will take to finish this
project.
The contract also calls for Gembira Sdn Bhd to produce 1,000 LED Screen for Advert B.
It further states that Gembira Sdn Bhd will produce LED Screen for Advert B at the rate of
250 per month.
You budgeted RM100 a copy for LED Screen for Advert B (RM100,000 / 1,000 copies).
Suppose it’s the end of March, and you’re two months into the project. Here’s what has
happened as of March 31:
1. Determine the planned value (PV), earned value (EV), and actual cost (AC) for
LED Screen for Advert B. Explain your results.
2. Determine the schedule variance (SV), cost variance (CV), schedule
performance index (SPI), and cost performance index (CPI) for the production
of LED Screen for Advert B. Explain your results
3. Use SPI to estimate the completion time and how much longer it will take to finish this
project. (budgeted time / SPI)
QUESTION 2
Assume you have to complete project ABC within 6 months. Given the following information
as part of the payment received for one particular phase of a project ABC.
v. Use the schedule performance index (SPI) to estimate the completion time and how
much longer it will take to finish this project.
QUESTION 3
Given the following information on work break down structure project progress. Calculate
the earned value of each task and total.