Ozuri - Revised Pow
Ozuri - Revised Pow
ID Task Name Duration August September October November December January February March April May June
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
0 OZURI GULLY EROSION SITE REHABILITATION/REMEDIATION WORKS 317.5 days
1 Bill 1 GENERAL 120 days
2 Installation of services to houses,demolition,clearing and Grubbing 4 mons
3
4 EXCAVATION & BACKFILING 247.5 days
5 Excavation for Line drain 5.25 mons
6 Excavation in hard materials 5.25 mons
7 Synthetic Fibre 3.75 mons
8 Trimming of excavation for trapezoidal drain in soft materials 6.75 mons
9
10 FORMWORK & CONCRETE LINING 253.5 days
11 Class U2 surface finish to cast insitu rectangular channel including drop 8.25 mons
structure
12 Ditto access slab 8.25 mons
13 Formwork to rectangular channel (Internal F2 finish including drop structure)8.25 mons
14 Rectangular Channel (External F1‐Finish) 8.25 mons
15 1000mm x 1000mm x 150mm Drain ‐ 1725m 4 mons
16 850mm x 850mm x 150mm Drain ‐ 1231m 3.75 mons
17 1500mm x 1200mm x 150mm Drain ‐ 185m 1 mon
18 750mm x 750mm x 150mm Drain (Hospital Road) ‐683m 2.75 mons
19 750mm x 750mm x 150mm Drain (Palace Road) ‐ 160m 1.25 mons
20 750mm x 750mm x 150mm Drain (Hospital to Trapezoidal ) ‐ 138m 1 mon
21 1500mm x 1300mm x 150mm Channel (Pry School Gully 1) ‐ 122m 1.5 mons
22 1500mm x 1300mm x 150mm Channel (Pry School2 Gully 2) ‐ 145m 1.25 mons
23 1500mm x 1300mm x 150mm Channel (Palace Gully)) ‐ 271m 1.5 mons
24 1200mm x 1500mm x 200mm Trapezoidal Channel (Main Road @ Ch 400 to 1.5 mons
River) ‐167m
25 1000mm x 1000mm x 150mm Trapezoidal Channel (Science Secondary 1.75 mons
School) ‐159m
26 3000mm x 1800mm x 150mm Trapezoidal Channel (Main Road @ Ch 985 to 4 mons
River) ‐951m
27 1200mm x 1500mm x 150mm Trapezoidal Channel (Main Road To Gully) ‐ 1.5 mons
212m
28
29 PROTECTON WORKS 165 days
30 Articulated block 4.5 mons
31 Gabion (1.0m x 1.0m x 0.5m) 1 mon
32
33 CULVERTS 164.5 days
34 1500mm x 1200mm Single Box Culvet @ Ch 00+ 310 1 mon
35 1500mm x 1200mm Single Box Culvet @ Ch 00+ 780 1 mon
36 1500mm x 1200mm Single Box Culvet @ Ch 00+ 839 0.75 mons
37 1500mm x 1200mm Single Box Culvet @ Ch 00+ 923 0.5 mons
38 1500mm x 1200mm Single Box Culvet @ Ch 01+520 0.75 mons
39 4000mm x 400mm Single Box Culvert @Ch 00+975 3 mons
40
41 EARTHWORKS 247.5 days
42 Unsuitable 6.5 mons
43 Cut to Spoil in soft excavation 8.25 mons
44 Cut to spoil in intermidiate excavation 8.25 mons
45 Cut to fill along road side drain 3.75 mons
46 Borrow to fill line drain 3.75 mons
47 Cut to fill along trapezoidal Channel 5 mons
48 Cut to fill along rectangular channel 4 mons
49 Rip and compact 3.25 mons
50 Repair and make good existing wearing course to receive base course 3.25 mons
51 Palace Gully Reclamation 1.5 mons
52 Fill under Gully Channels and Trapezoidal Channel 5 mons
53
54 OTHERS 90 days
55 Grassing 3 mons
56 Tree Shrubs and ground Cover 3 mons
57 Hand Rail 3 mons
58 Guard Rail 1 mon
59
60 PAVEMENT 207 days
61 Sub base 5 mons
62 Stone base 12 wks
63 MC1 2 mons
64 Asphalt 6 wks
65 Road Marking (White and Yellow ) 1 wk
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish‐only Critical Split
Project: OZURI GULLY EROSION S
Split Project Summary Inactive Task Manual Task Manual Summary Deadline Progress
Milestone External Tasks Inactive Milestone Duration‐only Start‐only Critical