Feasibility Analysis of Establishing Charging Stations For Electric Cars

This document presents a problem report on a feasibility analysis of establishing electric vehicle charging stations in public facilities. The report was submitted by Vivek Komarina to West Virginia University in partial fulfillment of the requirements for a Master of Science degree in Industrial Engineering. The report aims to develop a decision support system to evaluate the optimal number of charging stations needed at a public facility in a sustainable and cost-effective manner. It considers factors like traffic patterns, weather conditions, and time of year through Monte Carlo simulation to estimate energy consumption and costs of operating the charging stations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
327 views82 pages

Feasibility Analysis of Establishing Charging Stations For Electric Cars

This document presents a problem report on a feasibility analysis of establishing electric vehicle charging stations in public facilities. The report was submitted by Vivek Komarina to West Virginia University in partial fulfillment of the requirements for a Master of Science degree in Industrial Engineering. The report aims to develop a decision support system to evaluate the optimal number of charging stations needed at a public facility in a sustainable and cost-effective manner. It considers factors like traffic patterns, weather conditions, and time of year through Monte Carlo simulation to estimate energy consumption and costs of operating the charging stations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 82

Graduate Theses, Dissertations, and Problem Reports

2018

Feasibility analysis of establishing charging stations for electrical


vehicles in public facilities
Vivek Komarina

Follow this and additional works at: https://researchrepository.wvu.edu/etd

Recommended Citation
Komarina, Vivek, "Feasibility analysis of establishing charging stations for electrical vehicles in public
facilities" (2018). Graduate Theses, Dissertations, and Problem Reports. 4005.
https://researchrepository.wvu.edu/etd/4005

This Problem/Project Report is protected by copyright and/or related rights. It has been brought to you by the The
Research Repository @ WVU with permission from the rights-holder(s). You are free to use this Problem/Project
Report in any way that is permitted by the copyright and related rights legislation that applies to your use. For other
uses you must obtain permission from the rights-holder(s) directly, unless additional rights are indicated by a
Creative Commons license in the record and/ or on the work itself. This Problem/Project Report has been accepted
for inclusion in WVU Graduate Theses, Dissertations, and Problem Reports collection by an authorized
administrator of The Research Repository @ WVU. For more information, please contact
[email protected].
Feasibility Analysis of Establishing Charging Stations For Electrical Vehicles in

Public Facilities

Vivek Komarina

Problem Report Submitted

To the Benjamin M. Statler College of Engineering and Mineral Resources

At West Virginia University

in partial fulfillment of the requirements for the degree of

Master of Science in

Industrial Engineering

Bhaskaran Gopalakrishnan, Ph.D., P.E., Chair

Ashish Nimbarte, Ph.D.

Hailin Li, Ph.D.

Department of Industrial and Management Systems Engineering

Morgantown, West Virginia

2018

Keywords: Electric Vehicle Charging Stations, Plug-in Electric Vehicles, Energy


Consumption and Costs
Copyright [2018] [Vivek Komarina]
Abstract

Feasibility Analysis of Establishing Charging Stations For Electrical Vehicles in Public

Facilities

Vivek Komarina

To overcome the transportation sector’s dependency on fossil fuels, electric vehicles appears to be
a better alternative with a number of impressive benefits. Enhancing the utilization of electric
vehicles not only reduces global gasoline and diesel consumption but also helps in running an
environmentally cleaner road transport system with zero tailpipe emissions. As road transport
involves substantial gasoline and diesel consumption, Plug-in Electric Vehicles (EVs) being more
energy efficient and environment friendly can have direct impact on reduction of fuel reliance.
One of the important limitations influencing the penetration of electrical vehicles in the global
market is the lack of adequate charging infrastructure availability. Considering various challenges
involved in deployment of charging infrastructure, enhancement of public charging infrastructure
can be a successful step resulting in electric vehicle market raise.
This project is focused in developing a decision support system to evaluate optimal number of
charging stations to be established in a public facility, which are sustainable and economically
viable. This system considers a Monte Carlo simulation of a scenario using various pre-recorded
categorical data, depicting traffic arrival patterns and logistic challenges created by variance in
weather severity and time of the year. The simulated data can be used to estimate the energy
consumption and costs incurred by the charging stations in the facility. This work results in a
decision making spreadsheet-based model that enable facilities to explore cost implications of
installing and operating Electric Vehicle Supply Equipment (EVSE).
Acknowledgment

Firstly, I would like to express my sincere gratitude to Dr. Bhaskaran Gopalakrishnan, for his

continued support and encouragement during the course of my research work.

I would like to thank Dr. Ashish Nimbarte for his interest in me at every stage of the research. His

inspiration, timely suggestion with kindness, enthusiasm and energy have enabled me to complete

my problem report.

Also, I wish to thank Dr. Hailin Li for his advice and support.

Finally, I thank God, my family and friends for their constant support.

iii
Table of Contents
Acknowledgment ............................................................................................................... iii

1. Introduction ................................................................................................................. 1

1.1. Transportation ............................................................................................................................... 1

1.1.1. Transportation enabled growth, & Personal transport: ......................................................... 1

1.2. Energy consumption - Transportation sector ................................................................................ 2

1.3. Petroleum resources’ scarcity - Environmental & Economic impact ........................................... 3

1.4. Greenhouse gas emissions ............................................................................................................ 4

1.5. Plug-in electric Vehicles ............................................................................................................... 6

1.5.1. Battery Electric Vehicle (BEV) ............................................................................................ 6

1.5.2. Plug-in Hybrid Electric Vehicle (PHEV) .............................................................................. 7

1.6. Charging Infrastructure for Plug–in Type EVs ............................................................................. 8

1.6.1. AC Level 1 Charging ............................................................................................................ 8

1.6.2. AC Level 2 Charging ............................................................................................................ 9

1.6.3. DC Fast Charging.................................................................................................................. 9

1.7. Electrical Load / Demand billing - Importance............................................................................. 9

1.8. The Plug-In Electric Vehicle (PEV) Market - Need for EVSE Establishment ........................... 10

1.9. Electric Vehicle Battery Life and Reuse ..................................................................................... 11

1.10. Need for Research ....................................................................................................................... 12

iv
1.11. Objectives ................................................................................................................................... 13

1.12. Conclusion .................................................................................................................................. 13

2. Literature Review...................................................................................................... 15

2.1. Introduction ................................................................................................................................. 15

2.2. Lack of adequate Charging Infrastructure as a Prevailing Problem............................................ 16

2.3. Public Charging Infrastructure as a stopgap ............................................................................... 17

2.4. Role of Public incentives in EV adaption ................................................................................... 18

2.5. Different Models forecasting EV arrival And Charging Patterns ............................................... 20

2.6. Conclusion .................................................................................................................................. 22

3. Methodology ............................................................................................................. 23

3.1. Problem Statement ...................................................................................................................... 23

3.2. Approach ..................................................................................................................................... 23

3.3. Methods and Software Tools ...................................................................................................... 24

3.3.1. Heuristic Approach ............................................................................................................. 24

3.3.2. Monte Carlo Simulation ...................................................................................................... 25

3.3.3. Visual Basic for Applications® .......................................................................................... 26

3.3.4. Arena® simulation software ............................................................................................... 26

3.4. Assumptions................................................................................................................................ 27

3.5. Electric Vehicle arrival pattern spreadsheet model ..................................................................... 27

v
3.5.1. Capability ............................................................................................................................ 27

3.5.2. Factors Considered.............................................................................................................. 28

3.5.3. Inputs................................................................................................................................... 30

3.5.4. Model Outcomes ................................................................................................................. 30

3.6. Charging Pattern and Logistics Modelling Simulation ............................................................... 32

3.6.1. Creating EVs as Entities ..................................................................................................... 35

3.6.2. Decision Making ................................................................................................................. 37

3.6.3. Charging Process................................................................................................................. 39

3.6.4. Counters and Writing out Results ....................................................................................... 42

3.7. Annual Energy Costs and Electrical Demand Estimates ............................................................ 44

3.7.1. Energy Consumption and Costs .......................................................................................... 44

3.7.2. Electrical Peak Load and Demand Costs ............................................................................ 45

3.8. Limitations .................................................................................................................................. 47

3.9. Conclusion .................................................................................................................................. 47

4. System Execution and Results Discussion ............................................................... 48

4.1. Energy Assessment at a Public Facility ...................................................................................... 48

4.2. Electric Vehicle arrival pattern spreadsheet model with Sample Inputs ..................................... 48

4.3. Charging Pattern and Logistics Modelling Simulation with Sample Inputs ............................... 51

4.3.1. Energy Consumption........................................................................................................... 51

4.3.2. Electrical Demand ............................................................................................................... 51

vi
4.3.3. Total Electric costs .............................................................................................................. 52

4.4. Sensitivity Analysis .................................................................................................................... 52

4.4.1. Weather Severity ................................................................................................................. 52

4.4.2. Number of Charging Stations ............................................................................................. 54

5. Conclusions and Future Work .................................................................................. 56

5.1. Conclusions ................................................................................................................................. 56

5.2. Future Work ................................................................................................................................ 57

6. References ................................................................................................................. 59

7. Appendix ................................................................................................................... 63

List of Figures

Figure 1.1. 2015 U.S. GHG Emissions by Sector [4] ..................................................................... 5

Figure 1.2. 2015 U.S. Transportation Sector GHG Emissions by Source [4] ................................ 5

Figure 1.3.Components of a BEV [6] ............................................................................................. 7

Figure 1.4. Components of a PHEV [6] .......................................................................................... 8

Figure 1.5. US PEV Sales by Model [8] ....................................................................................... 11

Figure 3.1. Charging Pattern and Logistics Modelling Simulation .............................................. 34

Figure 3.2. Creating EVs as Entities ............................................................................................. 35

Figure 3.3. Create Module ............................................................................................................ 36

vii
Figure 3.4. Assign module ............................................................................................................ 36

Figure 3.5. Entities Split by Type ................................................................................................. 37

Figure 3.6. Decision Making for Both the Types ......................................................................... 38

Figure 3.7. Decide Module for Tesla® EVs ................................................................................. 39

Figure 3.8. Charging Process ........................................................................................................ 40

Figure 3.9. Charging Process Module for Schneider® Type ........................................................ 41

Figure 3.10.Charging Process Module for Tesla® Type .............................................................. 41

Figure 3.11. Resources Involved in the Model ............................................................................. 42

Figure 3.12. Record, Read/Write, and Dispose Modules ............................................................. 43

Figure 4.1. Input Boxes for EV Arrival Pattern ............................................................................ 49

Figure 4.2. EV Arrival Patterns .................................................................................................... 50

Figure 4.3.Histogram representing Monthly EV Arrivals ............................................................ 50

Figure 4.4. Monthly peak Demand Vs Weather Severity ............................................................. 53

Figure 4.5. Energy Consumption Vs Weather .............................................................................. 53

Figure 4.6. Total Monthly Costs Vs Weather ............................................................................... 54

Figure 4.7. Peak Demand Vs Number of Charging Stations ........................................................ 55

Figure 4.8. Energy Consumption Vs Number of Charging Stations ............................................ 55

Figure 4.9. Total Monthly Costs Vs Number of Charging Stations ............................................. 56

viii
List of Tables

Table 3.1: Weather Severity Levels .............................................................................................. 29

Table 3.2: List of US Holidays ..................................................................................................... 29

Table 3.3: Number of Electric Vehicles’ Outcome Levels ........................................................... 31

Table 3.4.Rate structure for the Facility Considered .................................................................... 45

ix
1. Introduction

1.1. Transportation

Transportation is movement of people and goods from one place to another. Over time, it has

become a social utility by lessening the geographical distance. Contribution of transportation in

social, economic, cultural and political grounds facilitated significant development in evolution of

human civilization. It would be a completely different situation if there was no progress in

improving means of transportation.

1.1.1. Transportation enabled growth, & Personal transport:

Proper development of agricultural sector is made possible only with the support of transportation.

Without improvement in transportation, rapid growth in industrialization may not be feasible.

Distribution or mass production is achieved with its promising presence. Also physical distribution

of finished goods to consumers from production location is made easier and hence played an

integral role in marketing. Simultaneously, it has social, cultural and political influence on the

society in addition to the economic growth. Foreign travel is made easier with advancements in

transportation and resulted in improved connections overseas. Improved connections and

globetrotting facilitated broadening knowledge and expertise in various sectors. National

integration is reinforced with expansion of transportation and its presence as a cultural and social

utility.

Personal transport is a luxury in the beginning of the 20th century. Over years, advancements in

mass production and changes in human needs, turned this luxury into an affordable necessity. The

total number of cars used by residents of cities and sub urban areas in United States multiplied

exponentially from 8 thousand cars in 1900 to 8 million in 1920 and more than 220 million by the

year 2000. This generated mobility and accessibility in lives of all sections of people on a scale

1
never known before. And hence has boundless impact on living habits and customs of people

indirectly.

1.2. Energy consumption - Transportation sector

According to United States Energy Information Administration (U.S. EIA) [1], 25% of total global

delivered energy consumption is by transportation sector for moving people and goods. The United

States (US), European countries in the Organization for Economic Co-operation and Development

(OECD), and China are the major transportation energy consumers and together they account for

55% of world transportation energy consumption. The transportation energy consumed by the

United States in 2012 is 26 quadrillion Btu equivalent, representing the above 25% of global

transportation energy demand.

Earth’s transportation energy consumption is being overshadowed by two fuels: gasoline and

diesel. These two fuels collectively accounted for 75% of total delivered transportation energy use

in 2012. The US transportation sector exhibits similar trend in fuel consumption with a major 55%

by gasoline and a significant 21% by diesel. Light-duty vehicles accounting for the largest share

of transportation energy consumption, dominate all modes of transportation in most of the world.

The United States, with ubiquitous on-road passenger travel was the world’s prime transportation

energy consumer in 2012. Light-duty vehicles’ dominate other means of transport in US with

approximately 58.6% [2] of the US petroleum consumption. Petroleum products account for the

largest share of transportation energy use by far, while nonpetroleum fuels account for a small

portion of the world energy mix, with natural gas and electricity together accounting for about 4%

of the world’s total transportation energy consumption.

2
1.3. Petroleum resources’ scarcity - Environmental & Economic impact

Continuous consumption of fossil fuels for transportation, electricity and heat generation needed

for the growing population of the earth can result in scarcity of resources. Most of the mankind’s

vast global needs are being energized by petroleum and other natural resources. The Organization

for Economic Co-operation and Development (OECD) identified that energy system in the present

situation is well dependent on fossil fuels [3]. The need for research and development of alternate

technologies that could help in potential reduction of fossil fuel or energy usage is being

accelerated by the fossil fuel resource scarcity. In the absence of effective natural resource

management with the help of potential technology advancement, economic growth can be greatly

affected in the long run. Not only economic growth, over-utilization and processing of natural

resources for energy needs can cause harmful emissions into the atmosphere resulting in a polluted

environment.

Transportation accounts for significant amount of global petroleum consumption. As 55% of the

US gasoline consumption is being consumed by the transportation sector according to the EIA [1],

alternate transportation technologies can help in reducing the fossil fuel dependency. Failing to

address environmental and economic concerns of fuel scarcity can affect nation’s energy security

and relationship between countries. Geopolitical situations can arise with a resource rich country

supplying the energy demand of developing countries with fuel scarcity. Increasing scarcity of

petroleum resources triggering reliance on foreign energy sources can result in rise of fuel prices.

The increasing vehicle emissions from fossil fuel technologies are also accumulating harmful

gases in the atmosphere adding to the existing pollution. Development of efficient and cleaner

transportation technologies appear to be a promising solution to the problem of energy

requirements and environmental pollution in the existing situation. Among such technologies,

3
electric transmission for vehicles is observed to be a sustainable alternative with improvied

efficiency, reduced emissions, and fuel costs.

1.4. Greenhouse gas emissions

Vehicular emissions are exhaust gases resulting due to fuel combustion in internal combustion

engines. These gases are emitted into the atmosphere through the vehicle flue gas stack depending

on the type of the engine. The emissions from gasoline or diesel run motor vehicles consists of

hydrocarbons as volatile organic compounds (VOC), carbon monoxide, oxides of nitrogen and

significant amounts of carbon dioxide gas. Gasses that entrap and emit radiant heat energy in a

thermal infrared range are termed as Green House gases (GHG). The main GHGs in the

atmosphere are carbon dioxide, water vapor, methane, nitrous oxide and ozone. Many human

activities are resulting in increased atmospheric concentration of carbon dioxide. De-carbonization

of transportation fuels and improving the efficiency of vehicle technologies are some of the routes

to reduce GHG emissions.

According to the U.S. Environmental Protection Agency (EPA) 65% of the global GHG emissions

is carbon dioxide emissions from combustion of fossil fuels for electricity, transportation and heat

uses. Transportation sector contributes a significant 14% of the global GHG emissions as per 2010

statistics. Whereas the rest was contributed by electricity generation, heat production, agriculture

and forestry sectors.

4
Figure 1.1. 2015 U.S. GHG Emissions by Sector [4]

Figure 1.2. 2015 U.S. Transportation Sector GHG Emissions by Source [4]
Among all the major developed countries, United States is the second largest carbon dioxide

emitter after China. The US contributes 15% of the global carbon dioxide emissions [5]. Figure

1.1 transportation sector emits 27% of the total GHG emissions in the country [4]. Passenger

vehicles being the most common means of transport in this country, light duty vehicles contribute

a major 60% of these emissions in 2015 [4] as shown in Figure 1.2.

5
1.5. Plug-in electric Vehicles

Electric Vehicles (EVs) are the vehicles that run on one or more electric motors for propulsion. As

the scope of this research is confined to plug–in charging type EVs, Battery Electric Vehicles

(BEVs) and Plug-in Hybrid Electric Vehicles (PHEVs) that come under Plug-in type EVs are

considered for this work.

1.5.1. Battery Electric Vehicle (BEV)

A Battery Electric Vehicle (BEV) or an all-electric vehicle stores electrical energy with the help

of batteries. These batteries will be convert the chemical energy stored in them to supply the

electrical energy to run the motors for propulsion as shown in Figure 1.3. They are usually

recharged using grid electricity from either a charging station or a home wall socket depending on

the size of the battery and the charging port they have. BEVs can provide better driving experience

when compared to conventional Internal Combustion (IC) engines with the instant torque

generated by the electric motors.

Technologies like idle-off and regenerative braking can minimize the battery energy consumption

involved in daily transportation. Idle - off turns the ignition off when the vehicle is idling whereas

regenerative braking technology enables charging of the battery while applying brakes. Battery

electric vehicles does not need gasoline or diesel combustion for propulsion of the vehicle like

conventional vehicles. So, there will not be any emissions associated with the propulsion of the

vehicle. Hence, they are considered to be Zero Emission Vehicles (ZEVs).

6
Figure 1.3.Components of a BEV [6]

1.5.2. Plug-in Hybrid Electric Vehicle (PHEV)

A Hybrid Electric Vehicle (HEV) has a hybrid vehicle drivetrain combining electric propulsion

with conventional IC engines. They will be having an IC engine running on gasoline or diesel as

a main source for propulsion and to produce electrical energy required to run an electric motor to

complement engine propulsion. The US Environmental Protection Agency (EPA) states that a

HEV can have fuel economy improved by more than 50% and a substantial carbon dioxide

reduction potential when compared to conventional vehicles. The Plug-in Hybrid Electric Vehicle

(PHEV) is a HEV with electric motor supplied by energy storage as a main source of propulsion

as shown in Figure 1.4.

It is supported by an IC engine to reduce the electrical energy consumption and extend the driving

range of a PHEV. So, a PHEV battery can be charged either by plugging into a source of electricity

or from excess engine power. Although PHEVs involve more lifecycle emissions than that of

BEVs, their oil consumption and greenhouse gas (GHG) emissions are lesser when compared to

7
conventional vehicles. So, PHEV could be an alternative in decarbonization of transport energy

consumption.

Figure 1.4. Components of a PHEV [6]


1.6. Charging Infrastructure for Plug–in Type EVs

Charging infrastructure or Electric Vehicle Supply Equipment (EVSE) is classified into three basic

types based on electric charging rate of the EV batteries. The charging rate varies with different

types of charging infrastructure due to differences in operating voltage and type of the electric

current employed. Different types of charging equipment and their operating characteristics as per

international standards stated by Falvo, et al. [7] are mentioned below.

1.6.1. AC Level 1 Charging

This equipment provides Alternating Current with a low 120 Volts (V) supply for EV charging.

This type of EVSE is suitable for EVs with smaller battery capacities and low driving ranges. All

plug - in EVs come with this equipment which is a simple cord set having a standard National

Electrical Manufacturers Association (NEMA) connector on one side and a Society of Automotive

8
Engineers (SAE) J1772 port on the other. This EVSE does not need a special power service at

higher voltages and is typically used for charging EVs at home with a 120 V power outlet for

longer durations at a slow charging rate.

1.6.2. AC Level 2 Charging

This EVSE will provide AC current at 240 V supply for residential charging or at 208 V supply

for commercial charging applications. This equipment can charge an EV overnight, quicker than

a level 1 charger. At the quickest charging rate, this equipment draws a maximum of 80 Amperes

(Amps) operating at 19.2 kilowatts (kW). A lot of residential Level 2 EVSE operate at 7.2 kW

drawing a maximum of 30 Amps. AC Level 2 charger needs a 240 V service and a 40 Amps circuit

for its operation. Most of the public charging facilities have AC Level 2 chargers and they use the

SAE J1772 charging port same as AC Level 1 chargers. EVs manufactured by Tesla®work with

a different port other than SAE J1772 port.

1.6.3. DC Fast Charging

This EVSE is a fast charging Direct Current (DC) supply at 208 or 480 V three phase service. This

can be seen in public and commercial charging stations and can swiftly charge an EV when

compared to Ac Level1 and Level 2 chargers. They use different charging ports like J1772 combo

port, CHAdeMO port or a Tesla® combo port depending on the EV manufacturer. This EVSE

charging ports has two bottom connector pins facilitating DC fast charging. Research and

development to bring the DC fast charging costs down is in place to make them accessible to all

the EV owners. It takes less than two hours to completely charge a typical EV.

1.7. Electrical Load / Demand billing - Importance

Along with energy charges, demand charges are a part of any electricity bill. The electric utility

providers bill the facilities for the electrical load supply based on the electric peak demand.

9
Electrical peak demand is established when the utilization of the resources i.e. charging stations in

our case, is maximum. Different types of facilities are billed on various rate schedules by the utility

provider. It is a good measure to check for the appropriate rate schedule to reduce the electricity

charges for individual cases. Some states in the country have high charges associated with

electrical demand. In California, Rolling peaks established for continuous fifteen minute intervals

are recorded in kW and the maximum of these peaks for each individual month is considered to be

the monthly peak demand on which the facilities get billed.

An unnoticed peak demand established for a 15 min interval can result in whole month’s utilization

at lower demand being charged at higher peak established once or more in that month. Considering

the abundant charges, it is a very important practice to monitor the demand for not allowing a

continuous peak demand in the consumption. A facility with multiple charging stations will have

a maximum electrical demand when most or all the charging stations are occupied and charging.

Electrical demand analysis and understanding is a suggested measure for any facility installing

electrical charging stations. Understanding electrical consumption charges, demand charges and

EVSE regular maintenance charges can help evaluating the financial feasibility of establishing EV

charging stations.

1.8. The Plug-In Electric Vehicle (PEV) Market - Need for EVSE Establishment

With accumulating environmental concerns, the number of people adapting EVs as their means of

transport increased too. Increasing PEVs also appear to be a cleaner, efficient and economical

alternative for fuel driven vehicles. According to Argonne National Laboratory (ANL) [8], 19,396

plug-in vehicles (9,589 BEVs and 9,807 PHEVs) were sold throughout April 2018 in the US, up

46.0% over the sales in April 2017. These recent PEV sales numbers clearly depicts their rising

trend in a very small period. ANL’s monthly trends by models (Figure 1.5) over the past years are

10
depicting a promising continuous rise in PEV sales. In these circumstances, lack of charging

stations appears to be a predominant problem for the gathering PEVs on long duration road trips.

National Renewable Energy laboratory evaluated the requirement of non-residential charging

infrastructure within public facilities like communities and Interstate corridors. Their research

portrayed a strong correlation between PEV and EVSE sales. Prioritizing EVSE establishment

based on driving patterns and vehicle characteristics can optimize the usage and economics

involved.

Figure 1.5. US PEV Sales by Model [8]


1.9. Electric Vehicle Battery Life and Reuse

Another important concern in EV lifecycle is life of the EV battery. Storage capacity can be

degraded over time and the battery needs to be replaced. This battery life can be affected by

problems like high operating temperatures and rapid discharge on usage. The EV battery service

life may end when it loses most of its storage capacity resulting in significant driving range loss

with battery degradation. The lifespan of EV batteries could range from 4 to 14 years. With the

11
increasing number of EVs on road, significant amount of degraded battery waste gets accumulated

too.

Although usage of EVs in an eco-friendly alternative, the increasing degraded battery disposals

can affect the atmosphere and is a growing environmental concern. These batteries are

manufactured using lithium, cobalt, manganese, nickel, and graphite and other rare metals as

primary components. EV batteries can contain electrolytes, metals, rare earth elements, and toxic

materials. These materials can be a potential risk to human health and can adversely affect the

environment. Improper disposition of these wastes can be a fire or shock hazard. These degraded

batteries can be reused after retaining maximum fraction of their original storage capacity at lower

costs. These retained batteries can be used as cheaper energy storage options for alternate purposes

like stationary energy storage systems of various scales, such as residence, commercial facility, or

power grid.

1.10. Need for Research

The rising petroleum derivatives’ prices and environmental pollution associated have augmented

the development of environment friendly Electric Vehicles (EVs) and their establishment in

transport system. Transportation sector being a major energy consumer, leaning towards more

energy efficient EVs will have significant impact in reducing petroleum dependence and

improving transportation sustainability. Concerns about environmental pollution are increasing

day by day over the recent years. Majority of the public facilities and parks’ visitors adapting a ‘go

green’ perspective, share similar concerns. According to International Energy Agency (IEA), the

number of EVs deployed into the automobile market around the globe in the period 2010-16 has

increased rapidly. In this scenario, lack of adequate charging infrastructure is a prevailing problem

for the EV drivers everywhere. Extending the charging infrastructure or Electric Vehicle Supply

12
Equipment (EVSE) in public facilities can be an initial step towards solving the above problem.

This research focuses on operational charges involved in establishing EV charging stations are to

be analyzed to decide on economic feasibility.

1.11. Objectives

This research focused on forecasting the arrival traffic density and charging pattern of Plug-in

Electric Vehicles (PEVs) based on pertinent factors across various seasons and holidays over a

year. Demand analysis of the considered public facility based on electrical supply requirements

over different times of the year is to be performed to curtail demand and save on demand charges.

The simulated data has to be observed to make a decision on the optimal number of charging

stations to be established in a public facility which are sustainable and economically viable. The

objectives of this research are:

 To develop Monte Carlo simulation of a scenario depicting traffic arrival patterns using

various pre-recorded and categorical data and based on following factors.

1. Weather Severity

2. Time of the year

 To develop a discrete event simulation modelling the charging patterns of the EV arrivals.

 To estimate Electrical energy consumption, Demand and costs based on the car arrival

patterns over a year for the above simulated data.

 To perform a sensitivity analysis of electrical demand and supply costs with varying

weather severity and number of charging stations.

1.12. Conclusion

This chapter helps in attainment of a detailed understanding of the existing transportation scenario

and its energy consumption globally and in the US. In the later sections, problems with the existing

13
energy systems and their impacts on the environment due to their GHG emissions were discussed.

Different EVs considered in the study, their components and different EVSE available in the

market were introduced in this chapter. Finally the objectives of this research are stated.

14
2. Literature Review

2.1. Introduction

Over the past few decades, transportation sector is contributing a major portion of global

greenhouse gas (GHG) emissions that entraps heat making the globe warmer. The United States

(US) Environmental Protection Agency (EPA) tracked that approximately 28.5% of the 2016 U.S.

greenhouse gas emissions associated with different human activities is from transportation sector,

involving combustion of fossil fuels. A significant 60 % of these US transportation sector’s GHG

emissions are from light duty vehicles fleet which is the most common means of transportation in

US [4]. The International Energy Agency (IEA) believes that de-carbonization of energy sector by

electrification can be a pathway to lower emissions. Transport electrification supporting cleaner

energy sources and greater efficiencies can help in achieving de-carbonization of energy sector to

a great extent.

Influence on hybrid EV purchase and use by denotations and connotations of typical customers

were observed by Heffner, et al. in their study [9]. The data was collected by conducting semi

structured ethnographic interviews in detail for about two hours each with 25 hybrid EV owning

households living in California, US. The large scale data collected in this study are statistically

modelled employing Semiotic theory methods. Qualitative analysis of the collected data was

performed considering the assumptions of the rational actor model from economics. This study

depicts the increasing concerns to preserve the environment and their influence on EV purchases

and use. Public parks may have visitors with environmental, and social values. Public parks are

one of the best recreation choices for the people with bio centric environmental ideals. Also nine

of every ten lengthy trips in US are preferably using personal vehicles according to Bureau of

15
Transportation statistics [10]. Increasing environmentally concerned visitor arrivals to public parks

with EVs substantiates both the above discussed surveys.

Substantial emissions are involved in different vehicle production, distribution, utilization, and

disposal processes in their life-cycle. Emissions from EV battery disposal can be reduced

considerably by extending the existing recycling and reusing procedures. EVs powered by

electricity has significant emissions involved with electricity production using different fuels

depending on their geographical location and resources’ availability. But, EVs in a sense help

releasing lesser tailpipe emissions than regular fuel run vehicles. Unlike fuel run vehicles, full

electric vehicles with battery run powertrain has zero tailpipe emissions. EVs with zero tail pipe

emissions are termed as Zero Emission vehicles (ZEVs). In 2012, California state government

issued an executive plan to support the ZEV market in the state by calling for 1.5 million ZEVs by

2025. The state increased the ZEV adaption with the help of the California Zero Emission Vehicle

Regulation. Clean Air Act allowed states Connecticut, Maine, Maryland, Massachusetts, New

Jersey, New York, Oregon, Rhode Island and Vermont to follow California ZEV regulations to

increase ZEV sales. All these steps towards sustainability results in escalation of the number of

EVs not only in the country, but also round the globe.

2.2. Lack of adequate Charging Infrastructure as a Prevailing Problem

With this escalation in EVs on road, and considering the limited driving range of even the recent

EV designs, lack of adequate charging infrastructure is a major barrier for the adaption of EVs. In

2012, Ona Egbue and Suzanna Long [11] worked together in analyzing potential EV customers’

knowledge, interests, attitude and perceptions to observe different factors that are restricting the

adoption of EVs to find out if their acquirement decision is influenced by sustainability matters.

They developed an internet based survey program to collect interests and opinions of EV owner

16
sample population covering students and employees of a university. To broaden the scope of their

research, they extended the sample population to technology enthusiasts and EV owners having

expertize in diverse areas like science, technology, and engineering. In different sections of the

survey, socio-economic details, perceptions, attitudes, environmental and sustainability concerns

of the respondents in detail were enquired and statistical analysis of the responses was done. This

work employed a Chi-squared test for analyzing the responses from around 500 respondents to

explore the differences in each of their concerns and ideas. Evaluation of these numerous responses

from their study, they identified that lack of adequate charging infrastructure is bigger barrier for

more number of people adapting EVs along with limited battery range and cost parameters.

2.3. Public Charging Infrastructure as a stopgap

Research and development of different EV technologies to improve powertrain efficiency, battery

size and selection, vehicle design, charging systems and direct current (DC) fast charging etc. are

in place to support the EV adaption. In the present situation, expenditure in improving or extending

the existing charging infrastructure appears to be insufficient. In an analysis of geographical

distribution of EVSE, IEA observed a positive relationship between public charging infrastructure

and global EV adaption. Identifying this urgent need to finance for charging infrastructure and

escalate EV adaption, state and federal governments research was done to improve electric vehicle

technologies. To measure gains of extending the deployment of publicly available charging

infrastructure Wood et al. [12] at the National Renewable Energy Laboratory (NREL) used

advanced simulation tools. For this, NREL developed the Battery Lifetime Analysis and

Simulation Tool for Vehicles (BLAST-V) with the support of U.S. Department of Energy’s

Vehicle Technologies Office (VTO). In their research, they discussed the spatial capabilities of

Level 2 EVSE in Seattle, Washington area and evaluated the incremental utilization by observing

17
different real time and simulated EVSE usage scenarios. In this process, travel profiles, driver

behavior, vehicle performance, battery attributes, environmental conditions, and charging

infrastructure were considered as simulation parameters for detailed understanding and analysis.

As a part of their work, it was observed that 15% of all charge events are happening in locations

away from home elucidating the need of more public charging infrastructure.

To meet this, government is encouraging various public and private organizations to deploy EV

charging corridors in multiple number at public facilities. The US Department of Transportation

(DOT) developed an action plan for establishment of several national EV charging corridors

covering more than 40 states in the country. Similarly state governments, vehicle manufacturers

and utilities are also committing programs to accelerate the deployment of EV charging

infrastructure in those corridors. Along with all these government measures that are encouraging

establishment of EV charging stations in public facilities, incentive programs for EV owners have

their own impact on EV adaption. Rebates to support EV charging infrastructure investment and

installations are also available to encourage public facilities.

2.4. Role of Public incentives in EV adaption

Considering the environmental conditions and the need for EV adaption, different researchers have

explored multiple options encouraging EV adaption. Sierzchula, et al. explored the impact of

financial incentives and other social, economic and demographic factors on the EV adaption and

sales in their study [13]. EV adaption and charging infrastructure data regarding Battery Electric

Vehicles (BEVs) and Plug-in Hybrid Electric Vehicles (PHEVs) in 30 countries is collected. As a

part of it, different variables including federal financial incentives, 2012 EV market share, EVSE

per capita, fuel and electricity costs, education, income, urban density and environmentalism

indicator (EI) data were statistically analyzed. With the help of regression analysis, significant

18
correlation is observed between BEV, PHEV sales and federal incentive programs, EVSE

availability, ample existence of EVSE production and support facilities around the area. The results

from this work clearly support the influence of enough charging infrastructure availability on EV

adaption in a country. They also discovered that the BEV and PHEV market share did not have

significant dependence on different socio-economic variables. This study have not considered the

EVSE density in particular, instead a homogeneous distribution of charging station scenario was

assumed while collecting the charging infrastructure data. Narassimhan and Johnson (2014)

presented a macroeconomic analysis [14] of policy incentives, charging station density and HOV

exemption in place effects on PHEV and BEV registrations per capita for eligible driver

population. Different demographic variables’ like median household income, residential energy

consumption per capita, age, and percentage of graduates’ data was collected and regression

analysis is performed separately for both types of EVs. Database from Alternative Fuels Data

Center (AFDC) laws and incentives to boost EV market and registration data from 2008 to 2014

through the first quarter are analyzed as a part of this study. In addition to the above mentioned

variables the effect of gasoline price increase is also considered in the study. This work concluded

that PHEV market is being more influenced by non-monetary incentives like HOV exemptions

than by state monetary incentives like tax credits, rebates etc. It also concludes that the EV

charging infrastructure availability greatly impacts both BEV and PHEV purchases and extension

of EVSE can reduce the EV limited range concerns and lift EV market.

Along with federal incentives, most of the states in the US are offering decent incentives too.

Maryland Energy Administration has an EVSE rebate program [15] through which government,

businesses organizations and residents can acquire rebates for purchase and installation of EVSE.

In addition to this program they provide EV incentives in the form of Federal income tax credits,

19
Maryland excise tax credit and HOV lane utilization to encourage EVs on their roads. Most other

states have similar incentive programs and National Conference of State Legislature (NCSL) has

a database of all the available incentives in the country in their website.

2.5. Different Models forecasting EV arrival And Charging Patterns

To obtain a stochastic storage capacity needed for an EV parking lot, Guner et al. modelled the

arrival and departure patterns of EVs in their work [16] . Modelling is done by Monte Carlo

simulation using different stochastic and deterministic variables. Using statistical data from a

parking lot in Istanbul, Turkey that can accommodate 500 vehicles, each car arrival and departure

time data is generated and a kernel density estimation of probability distribution for the car parking

duration variable is performed. The simulated data on analysis results the fraction or percentage

of available storage at different times of the day.

Xi et al. [17] developed a simulation model to determine optimal location for maximum utilization

of level 1 and level 2 EV chargers in central-Ohio region. The model employs a linear function of

different socio-economic and demographic variables to estimate EV acquiring probabilities in the

fixed sub regions. Sensitivity analyses are performed to understand the effect on EV charger

location by different vehicle charging decisions. The model helps in optimizing location of slow

chargers in the considered region and the sensitivity analyses predicted that slow chargers are on

the economical side compared to fast direct current chargers. This model is limited due to a fixed

consideration of study region, EV driving range and efficiency measured in electrical energy per

each mile in the simulation.

Cao et al. designed an optimization method to curtail the EV charging electrical loads based on

the time of use charges associated. In this research [18], the involved charging costs were defined

as a function of charging power of an EV battery and its state of charge. A model minimizing these

20
charging costs was developed to simulate an optimal charging pattern. Comparison of the electrical

demand at time intervals and final charging costs has been done between model generated

optimized charging pattern and representative charging pattern. They showed that the optimized

charging pattern created by their model resulted in lesser loads and hence the costs when compared

to a typical pattern.

A dynamic rolling optimization approach [19] for personal PHEV owners has been developed by

Kong et al. that helps in deciding an ideal time schedule to charge. This approach was driven by

two considerations, fluctuation in electricity costs with time slots in a day and varying driving

routines. A driving model to statistically analyze the energy demands based on historical driving

records of PHEV owners was made using an algorithm developed employing heuristics. An

extensive driving data of 1047 PHEV owners’ driving records for 246 representative days was

collected and analyzed in their work.

To decide on a finest network of EV charging stations for a community, Faridimehr et al. [20]

developed a two stage stochastic programming model. The research focused on the variations in

EV battery state of charge, arrival times, charging times, type of vehicles, driving range associated,

demand during weekends and weekdays, charging preferences of an EV driver and EV adaption

rate in the community. They collected data performing sample average approximation surveys

regarding different variations mentioned on a sample of scenarios. This vast data set is analyzed

quickly for an optimal solution employing heuristics that involved a scoring measure. Optimal

solution generated is evaluated using computational experimentation using various public data

services.

Alizadeh et al. [21] proposed a stochastic model to forecast the electrical demand involved in

charging activity of EVs to help in demand response management using actual metered data and

21
varying demand prices. As a part of the forecast, the electrical load is modeled analyzing the

random EV arrival employing queuing theory. The model simulates the random arrivals using a

non – homogenous Poisson distribution and a cumulative distribution function based on required

charge for charging times. The model developed is capable of taking historical data as input to

forecast the EV charging demand.

2.6. Conclusion

In this chapter, literature regarding the existing EV situation and the problem involved is discussed

in detail in the initial paragraphs. Lack of adequate charging infrastructure is established as a

prevailing problem and how public charging infrastructure deployment can be a stopgap for the

problem is elucidated with the help of existing literature. Federal and State governments’ actions

for encouraging the establishment of public EVSE are mentioned in the later sections. Also the

role played by the public incentives in increasing the EV adaption is discussed using existing

literature. Wide research forecasting the arrival and charging patterns of EVs and their approaches

are discussed to explain and distinguish their methodologies.

22
3. Methodology

3.1. Problem Statement

Substantial research and development was done to improve electric vehicle technologies in

different areas like battery selection, electric motors, vehicle design, transmission systems and

direct current (DC) fast charging etc. Various implementation and operational charges involved in

establishing EV charging stations are to be analyzed to decide on economic feasibility.

Considering the requirement of EV charging stations, there is a need for more research in the

direction of economic feasibility and costs involved. The objective of this research is to develop a

decision support system that helps and enables facilities or organizations to analyze the cost

implications of installing and operating the Electric Vehicle Supply Equipment (EVSE). As a part

of it, to forecast the public facilities’ EV arrival traffic density and charges associated, a Monte

Carlo Simulation has been developed. The EV traffic arrival patterns to a public facility with

multiple charging stations considering weather severity and time of the year can be generated. This

can be done using a spreadsheet model developed using Visual Basic for Applications® (VBA).

A scenario depicting the charging patterns of the EVs arrived to that public facility can be

dynamically simulated using a discrete event simulation model developed using Arena®

simulation software based on the generated arrival pattern. A detailed energy cost based sensitivity

analysis mainly with electrical demand and charges associated with electricity consumption can

be done using this data for the simulated scenario.

3.2. Approach

The simulation required for this research is performed in two parts due to the complexity and

programming challenges involved in the work. Each simulation run depicts the EV arrival and

23
charging patterns for a year. The first half which is the generation of EV arrival pattern to a public

facility decided by the following factors.

i) Probability of weather severity in the geographical area of the facility considered and

ii) Busy days of a public facility which includes United States (US) list of holidays,

weekends, spring-break, Thanks-giving week and the summer months.

The second half of the work is simulating the charging pattern of the arrived EVs based on the

arrival pattern generated before. This simulation can depict the complex logistics problem involved

in the charging process. It is capable of representing a visual in which EVs arrive to the charging

stations, decide to get charged or leave if all the available stations are occupied for given significant

amount of time and get processed according to the decision made. Simulated data of different

process variables involved in the simulation run is then used to estimate electrical energy

consumption, demand charges and perform detailed sensitivity analysis This simulation is done

using a VBA based spreadsheet model and Arena® simulation software, discussed below.

3.3. Methods and Software Tools

This research involves a Monte Carlo Simulation of EV arrival and charging patterns at a public

facility based on a heuristic approach and estimate the operational charges resulting. The EV

arrival pattern spreadsheet model is generated using Visual Basic for Applications®® in Microsoft

Excel®. Whereas the discrete event simulation of the charging pattern based on the arrivals is

visualized using Arena® Simulation Software.

3.3.1. Heuristic Approach

Heuristics are flexible techniques that are employed to solve a complex problem. So, a heuristic

approach can be defined as a technical approach in problem solving, learning or discovery

employing a practical method developed on general understanding which can give an approximate

24
and immediate solution but may not be optimal. It is a decision making approach in which

procedural decisions are made based on general understanding. It is employed when classic

methods take longer durations and fail to give exact solutions. A number of understanding and

learning researches in science and technology employ heuristic approach to define strategies [22].

3.3.2. Monte Carlo Simulation

Monte Carlo Simulation is modeling the probability of different results in a procedure,

mathematical or a statistical model that cannot be simply estimated because of the involvement of

random variables using different set of random numbers as sampling data. This method involves

calculation of several outcomes of different variables involved in the method with multiple sets of

input values generated with randomness based on a probability distribution or its function. This

method is extensively used in development of statistical methods, modification and comparison of

methods.

Monte Carlo Simulation is capable to show the changes in set of outcomes of variables or an

equation with variables that undergo discrete events. A Monte Carlo Simulation which progresses

some amount of time after one event is executed is called as an event driven Monte Carlo

Simulation. Whereas one which processes discrete events involved in a method in fixed given time

interval is called as a time driven Monte Carlo Simulation. They can be differentiated based on

how the modelled values are tracked as the simulation progresses.

Indirectly, it performs risk analysis by modelling probable results by substituting different sets of

random values generated using probability distributions, in the equation or method involving

variables. Further, it calculates outcomes over and over each time using different patterns of input

25
values. Based on number of uncertainties involved, simulation requires hundreds and thousands of

recalculations to be done before generating results.

3.3.3. Visual Basic for Applications®

Visual Basic for Applications® (VBA) is a programming language that allows automation and

customization of detailed computer processes and calculations. VBA being a potential feature in

Microsoft Excel®, allows users to create user-defined functions, access Windows APIs and

use dynamic-link libraries (DLLs) and customize the application. VBA is the tool enabling people

to code programs they require to control Excel®. It has several pre-defined functions and has the

ability to call the functions in the application it is being used for. These features help the user in

automating a time consuming program or process the data has to undergo with just a simple click.

This can be done either by using macros simply or by writing a code to program data, the way user

wants.

3.3.4. Arena® simulation software

Arena® Simulation Software is a potential tool that helps the user predict, evaluate and validate

system or process strategies for effective and optimized performance. Discrete event modelling

that can optimize complex processes can be done without much effort using Arena® software. It

follows a flowchart modelling method with multiple process variables defined as per several pre-

defined or user-defined functions or statistical distributions.

This software can represent the actions of a complex system as a set of well-defined and ordered

events virtually in any variable process with limited resources involving complicated interactions.

Its ability to two dimensionally or three dimensionally visualize the simulation run of the whole

process is of great help in demonstrating the simulation. This software can process multiple

26
variables for the certain period of time, for multiple replications. Different statistical analyses can

be done and detailed reports can be generated with all the results.

3.4. Assumptions

1. The charging times of EV in the simulation model are assumed to be following a Triangular

distribution.

2. It is assumed that only one EV will be waiting to get charged when all the charging stations

are occupied and the next EV arrived will leave the facility without charging.

3. It is assumed that the days before and after the Spring break, Thanks giving break and the US

list of holidays will be having maximum EV arrivals to the public facility.

4. EV arrivals were modelled assuming that minimum number of EVs arrive to charge, in severe

weather conditions even on a busy day for a public facility.

5. The EV arrival density to the facility is assumed to be uniform at different times of the day.

6. The study considers multiple arrivals of the same EV as different EV arrivals.

7. The effects of vehicle’s climate control system on EV energy consumption in different seasons

are not considered in this study.

3.5. Electric Vehicle arrival pattern spreadsheet model

The EV arrival pattern spreadsheet model is a user friendly model which enables the user to

generate EVs arrival to a public facility. The VBA code for the whole arrival pattern spreadsheet

model is attached in appendix at the end.

3.5.1. Capability

This model is intended to generate random EV arrivals for each separate simulation run. This

spreadsheet model gives the number of EVs arrived to a public facility on each day in a 365 day

calendar year. The number of EVs for a year is given in individual cells for 365 rows in a column

27
of the spreadsheet. Based on the simulated number of EVs arrived on each day for a year, the

model divides them into number of Tesla® model EVs and regular EVs arrived in a year taking

user’s input. Random arrival times based on these number of different types of EVs for each day

in a calendar year can be generated by this model.

3.5.2. Factors Considered

The number of EVs arrived on each day to the public facility can be influenced by different factors

such as weather effect on visitor arrivals, visitor arrivals at different times of the year, population

density and places of interest in public facility’s location etc., in several ways. The first two factors

among the mentioned influencing factors has a direct impact on visitor arrivals to a public facility.

Whereas the latter two factors are dependent on the demographics of the considered public

facility’s location and needs environmental monitoring using Geographic Information Systems

(GIS). Although, they have a partial influence over the visitor arrivals to a public facility, due to

the complexities involved in quantifying accurately the model is developed based on two factors.

The two important factors considered by this simulation model that influence the visitor arrivals

to a public facility are:

3.5.2.1.Weather Severity

Seasonal Weather has a pronounced influence on the visitor arrivals to a public facility. So, the

EV arrivals to the public facility will be depended on weather severity on the day of a year. Hence,

probability of weather severity in the geographical location of the facility considered is taken into

account in generation of the number of EVs with the severe weather data from National Oceanic

and Atmospheric Administration (NOAA) [23]. This NOAA data for a particular region represents

weather behavior and changing patterns in that area. In this model, two levels of weather severity

represented as Weather Factors (WF) are considered as shown in Table 3.1 below.

28
Table 3.1: Weather Severity Levels

Severity Level Weather Factors (WF)

Comfortable Weather 1
Severe Weather 0

3.5.2.2.Time of the year

Public facility visitor arrivals are dependent on day of the week and school vacations in particular

times of the year [24]. So, the busy days of a public facility includes United States (US) list of

holidays, weekends, spring-break, Thanks-giving week and the summer months. It is considered

that all the above mentioned times of the year have more arrivals compared to the rest of the days

in a year. The model represents all the holidays mentioned above with Holiday Factor (HF) as ‘1’

in the spreadsheet model generated. Rest of the days are represented with HF as ‘0’ in the model

indicating less number of visitor arrivals on different days of a year to the public facility. As our

research is focused on a public facility in US, the list of US calendar holidays as shown in Table

3.2 below are considered.

Table 3.2: List of US Holidays

Holiday Date

New Year Day 1-Jan


Martin Luther King Jr. Day 16-Jan
President Day 20-Feb
Memorial Day 28-May
Independence Day 4-Jul
Labor Day 3-Sep
Columbus Day 8-Oct
Veterans Day 11-Nov

29
Christmas Day 25-Dec

3.5.3. Inputs

The model generates different number of EVs for each day of a year based on multiple input values

from the user operating the model. The two important inputs the user needs to provide the model

are the minimum and maximum number of EV arrival data. First, the model requests the user to

enter minimum number of EVs arriving per day in an input box as a dialogue. This should be an

integer value from ‘0’ to ’30,000’. After entering the value in the first input box, the model

similarly requests for an integer value in the second input box asking for maximum number of EVs

arriving per day as a dialogue.

The model also requests the user to provide a fraction of Tesla® EVs among the total EVs arriving

round the year to their public facility after entering the maximum arrivals as another input box.

The value entered in this input box will be used as a probability in the model to generate random

number of Tesla® EVs. The fraction entered can be observed in the form of number of Tesla®

EVs arrived to that public facility in a year among the total number of EVs arrived in a year. All

these three inputs given at the beginning of the model before the simulation are displayed in the

first spreadsheet (Arrival Pattern).

3.5.4. Model Outcomes

The model generates three different levels of arrivals randomly based on the weather severity in

the geographical location of the facility and time of the year. The first level of outcome is number

of EVs arriving per day will be equal to the minimum number of EV arrivals per day to that facility.

The outcome number of EVs will be minimum in two cases when the weather factor is ‘0’ and

holiday factor is either ‘0’ or ‘1’. This indicates that the public facility visitors and EV arrivals will

30
be minimum in severe weather conditions (WF is ‘0’) irrespective of time of the year (i.e. whether

it is a holiday or not).

The second level of outcome is the number of EVs arriving per day being an average of the

minimum number of EV arrivals per day and the maximum number of EV arrivals per day to that

facility. This case can be represented on a day when the WF is ‘1’ and the HF is ‘0’, indicating a

working day with comfortable weather conditions. This represents a moderately busy day at a

public facility.

The third level of outcome is number of EVs arriving per day will be equal to the maximum number

of EV arrivals per day to that facility. The outcome number of EVs will be maximum in the case

when the weather factor is ‘1’ and the holiday factor is ‘1’, indicating maximum EV arrivals to

that facility on a beautiful holiday. This indicates that the public facility visitors and EV arrivals

will be maximum with comfortable weather conditions on holiday times of the year representing

a typical busy day at a public facility. All three possible outcomes and the conditions considered

are tabulated below in Table 3.3.

Table 3.3: Number of Electric Vehicles’ Outcome Levels

Weather Weather Time of the Holiday


No. of Cars
severity Factor Year Factor
Working
Severe 0 0 Minimum
Day
Severe 0 Holiday 1 Minimum
Working
Comfortable 1 0 Average of Max and Min
Day
Comfortable 1 Holiday 1 Maximum

Based on the above outcome, a set of EV arrivals per each day for a year in 365 rows are generated

respectively. The model then simulates the number of Tesla® EV arrivals and regular EV arrivals
31
using the probability of Tesla® EVs among the total EVs arriving round the year to their public

facility input from the user. Further steps in the model involves simulating these EV arrival times

separately for both Tesla® EVs and Regular EVs. The praiseworthy capability of this spreadsheet

model developed is the generation of random arrival times for all the simulated number of EVs of

both the types. The model creates two separate spreadsheets of EV arrival times, one for Tesla®

EVs and the other for Regular EVs on each and every day of a 365 day simulated calendar year.

The total number of EV arrivals, individual EV arrivals of each type, percentages of total EV

arrival for each type and the weather conditions are also displayed in the first spreadsheet of the

model (Arrival Pattern). Whereas the arrival times are displayed in different sheets one for each

type named ‘Regular Numbers’ and ‘Tesla® Numbers’.

3.6. Charging Pattern and Logistics Modelling Simulation

The model is a discrete event simulation designed to replicate and visualize the charging pattern

of the EVs coming to a public facility with multiple charging stations of two types. The Arena®

Simulation Software mentioned in section 3.3.4 is used to generate a flowchart based model to

simulate EVs as per the given input pattern and predict the charging times as shown in Figure 3.1.

The simulated data generated by the Electric Vehicle arrival pattern spreadsheet model, mentioned

in the previous section serves as the input for each simulation run. The model developed is capable

of handling data cells as input from the spreadsheet model for the simulation.

This model simulates the charging pattern of the EVs arrived to the public facility in four sections

taking care of different discrete events involved in the logistics of vehicle charging. The four

sections of the simulation discussed below separately in detail are:

1. Creating EVs as Entities

32
2. Decision Making

3. Charging Process

4. Counters and Writing out Results

The simulation model developed in Arena® Simulation Software is shown in Figure 3.1 below.

33
Figure 3.1. Charging Pattern and Logistics Modelling Simulation

34
3.6.1. Creating EVs as Entities

The first section in the simulation is the creation of EVs as entities arriving into the model. This

section involves generation of entities and then assigning time variables and pictures to each entity

type for further processes and entity related modules. The assigned entities are then input to a

module and channeled to respective processes. All the steps involved in this section are shown in

Figure 3.2.

Figure 3.2. Creating EVs as Entities


The generation of entities is done using a Create module in the software which enables us to push

entities into the model with certain time intervals. These time intervals can be input as random

exponential values, as a pre-defined schedule, as a constant value or as an expression. In our case,

schedule for Regular EVs and Tesla® EVs from EV arrival pattern spreadsheet model named as

‘Schedule 1’ and ‘Schedule 2’ respectively are given as a schedule input selected from the drop

down menu in the create module as shown in Figure 3.3. This schedule is two columns of integers

representing each EV arrival as ‘1’ in one column and every hour of 8760 hours in a simulated

year in the other. The ‘Schedule 1’ data is available from the ‘Regular Numbers’ spreadsheet and

‘Schedule 2’ data is available from the ‘Tesla® Numbers’ spreadsheet in the model. The entity

type is also allocated in the create module as shown in Figure 3.3 for further assignments.

35
Figure 3.3. Create Module
The required variables in the simulation are assigned to both the allocated entities using an Assign

module in the software. The current simulation time is assigned as a variable to each passing entity

in this section. The software enabled the model, assigning a picture from the picture library of the

software to each entity. Figure 3.4 shows the assignment of time variable and one picture to each

type of entity.

Figure 3.4. Assign module

36
Further, the assigned entities are split using a decision module in the software which separates

them based on type of entity. The decision module’s condition by type is used to split the entities

into individual channels. The condition considered is whether the incoming entity is of type

Schneider® or not. This condition pushes the Schneider® type entities to Schneider® charging

process if true and Tesla® type entities to Tesla® charging process if false. Figure 3.5 shows how

the entities are split using a decision module.

Figure 3.5. Entities Split by Type


3.6.2. Decision Making

The entities created, assigned and split by type are pushed to the next section of the simulation for

decision making. Both the entities have different charging process modules. Each entity has to

pass the decision making section to decide whether to charge or leave the facility. This is done

using a decide module in the software. The rhombus shaped module in Figure 3.6 is the decide

module and two different channels from it are also shown. The type on which this module has to

choose is two way by condition. The deciding condition is based on a work in process (WIP)

variable with an extension ‘.WIP’, one for each entity type. The WIP variable for the entities of

37
Schneider® type are named as ‘Schneider® charging.WIP’ and for the entities of Tesla® type ae

named as ‘Tesla® charging.WIP’.

Figure 3.6. Decision Making for Both the Types


The WIP variable is an integer which indicates the number of entities on which the work is in

process. So the condition is based on the number of entities that are in the charging process and

those waiting to be charged after the decision making. This condition is developed on an

assumption, considering the long charging durations. It is assumed that only one EV will be

waiting to get charged when all the charging stations are occupied and the next EV arrived will

leave the facility without charging. This assumption is modeled using a WIP variable and the

decision module in the software. The entities waiting after the occupied charging stations are

represented with a picture in queue on top of charging module as shown in Figure 3.6.

The facility considered in our research has one charging station to charge EVs of Tesla® type and

two other charging stations for all the other type of EVs with universal charging port. So, the

condition for decision making whether to charge or not for Tesla® EVs is formulated as the

38
variable ‘Tesla® charging.WIP’ is less than or equal to 1. And the condition for decision making

whether to charge or not for other type EVs is formulated as the variable ‘Schneider®

charging.WIP’ is less than or equal to 2. The decide module input is shown below in Figure 3.7.

The false condition of the decide module represents the scenario of an entity leaving the simulation

without charging when all the available charging stations are occupied and one more entity waiting

to be charged. Whereas the true scenario represents an unoccupied charging station or an available

waiting spot for the entity and hence enters the process module.

Figure 3.7. Decide Module for Tesla® EVs


3.6.3. Charging Process

Based on the input conditions, the entities that are decided by the model to charge are pushed into

the charging process section and the rest are pushed out of the simulation as shown in Figure 3.8.

The charging process is designed as a seize, delay and release action in the model with the help of

a process module in the software. So, the process module logic performs seize, delay and release

activities on each and every entity that passes through. The delay action in the module is a value –

added delay i.e., the time taken to process the entity. Hence, the time taken to charge the EV is

modeled using this module, representing by the delay step in the process. This delay is a random

39
variable time for every passing entity and can be input as a distribution using the pre-defined

distributions in the process module.

Figure 3.8. Charging Process


The charging times for any EV varies with the electrical operating characteristics mainly the

maximum power. The calculations in this research are based on the operating details on the EVSE

by its manufacturer at the public facility considered. Using these details, the charging duration for

a Tesla® charger is estimated to be between 3 hours and 6 hours depending on the required charge

in kilowatt-hours (kWh). Whereas the charging duration for the Schneider® type of charger can

vary from 2 to 6 hours. The required charge generally varies with the size of EV battery, the amount

of charge left in the battery and the desired time an EV owner wants to charge. These times can

vary randomly and hence this random variable is decided by the model dynamically using a

triangular distribution (T- distribution). This can be shown for Schneider® type charging station

and Tesla® type charging stations in Figure 3.9 and Figure 3.10 respectively.

40
Figure 3.9. Charging Process Module for Schneider® Type

Figure 3.10.Charging Process Module for Tesla® Type

41
Triangular distribution is a distribution similar to uniform distribution with a minimum value, a

maximum value and a most likely value. It is employed in cases where the distribution of the

random variables involved are vaguely known and with an understanding about the most likely

outcome. The industry practice of using a uniform distribution can be improved by using the

triangular distribution which gives lower probabilities of coming below the “most likely” value,

higher probabilities of most likely value, and the possibility of maximum value. As the upper and

lower limits of charging times are well known and their average being the most likely outcome in

the distribution, T - distribution is considered to be closely representing the overall charging times.

The number of charging stations can be added as resources for a process module. Each entity will

be processed by one resource in this model. Figure 3.11 shows two different types of resources of

the model one for each type of entity. These represents the EVSE scenario in the public facility

considered. So, the entities are seized, delayed by resources and released after the charging process

modeling the charging pattern required. User can input the number of resources required in the

simulation in this module.

Figure 3.11. Resources Involved in the Model


3.6.4. Counters and Writing out Results

The whole simulation run generates entities, decides to charge or not, and gets charged or leave

the model replicating a charging pattern. But all the simulated data with values of different

variables at times has to be counted and read out for further analysis. The entity and time interval

counting is done using record modules in the software. The recorded data is written out to a

42
spreadsheet with the help of read/write modules in the software. A read/write module and two

record modules, one for counting entity numbers and the other for recording time interval data are

included in each path of the model. All the entities that are proceeded to charge and those decided

not to charge by the model leaves the simulation after recording and writing results through dispose

modules in the software. All the modules involved in the final section of the simulation are shown

in Figure 3.12 below.

Figure 3.12. Record, Read/Write, and Dispose Modules


Simulated data from different variables like entity Id, Arrival times, wait times, Charging times,

and total time stayed are written into a spreadsheet for further estimations and analysis. A cyclical

process is created to record resource utilization data in each hour of a simulated year and are

written out to another spreadsheet for estimating monthly energy consumption, electrical demand

and charges associated with them for both types of entities.

43
3.7. Annual Energy Costs and Electrical Demand Estimates

In this model, energy consumption and cost estimates per entity, per each simulated hour and per

each month for a year are estimated. Electrical load in terms of Demand in kilowatts (kW) is also

simulated for each hour to understand the load pattern.

3.7.1. Energy Consumption and Costs

The model is capable of estimating the kilowatt hour (kWh) energy consumption and costs for two

different types of EVs separately for each simulated entity. In this estimation charging time in

hours from the ARENA® simulated data output spreadsheet and operating power of the charging

station in the facility considered based on the type of EV are used. The charging stations at the

facility considered are supplied with 240 V single phase AC current. As per the manufacturing

details, both types of AC Level 2 charging stations considered operate on single phase electric

supply and the operating power is estimated using the operating characteristics like maximum

amperage and operating voltage on the manufacturer’s name plate. The operating power of the

Schneider® charging station is 7.2 kilowatts (kW) and that for Tesla® charging station is 17.2 kW.

In this model, the energy consumption (kWh) of each simulated entity based on type in kWh is

obtained by multiplying Charging time (TC) of the entity in hours with the Operating power (P) of

respective charging station. Energy costs (EC) are obtained by multiplying the obtained kWh with

energy charge ($/kWh) from the rate structure (Table 3.4). The relations used for estimation are

shown below.

kWh = TC x P

EC = kWh x $/kWh

The energy consumption and costs for each month of a calendar year can also be estimated using

this model. For this, the hourly data generated using a cyclical process in the model is used. The

44
simulated percent utilization data of the resources i.e. charging stations in our case, Operating

power (P) of respective charging station and one hour of duration are multiplied together to obtain

the energy consumption of each hour in an year. Operating powers used for Schneider® and

Tesla® charging stations are 7.2 kW and 17.2 kW respectively. The hourly energy consumption

data obtained is briefed for 12 individual calendar months. This monthly kWh consumption

obtained is multiplied with the energy rate as per Table 3.4 to estimate the monthly energy costs

resulted after charging the simulated EV arrivals for respective times following a T-distribution.

Table 3.4.Rate structure for the Facility Considered

Rate structure for the Facility Considered


$/kWh 0.0526
Electricity
$/kW 11.508

3.7.2. Electrical Peak Load and Demand Costs

For estimating the monthly peak demand on which the facilities are billed, rolling peaks are

needed. In this model, the rolling peaks established by all the facility buildings together and those

by charging stations for every one hour are estimated due to data constraints. Demand peak by the

buildings is simulated based on the user input on maximum and minimum monthly demand peaks

in kilowatts established over the past year. Whereas the charging station demand estimates are

based on the simulated utilization data of the charging stations obtained using a cyclical process.

Electrical load at the time of use for each hour is estimated by multiplying the number of resources

in utilization at the time (NR) of each type with the Operating power (P) of respective charging

station. Monthly peak demand is the maximum of the rolling hourly total demands, which is the

sum of demand peaks established by buildings and charging stations in that hour for a month. Peak

demand for each month on which the facilities are billed on this peak total demand obtained.

45
To estimate the effect of charging stations on the demand and demand costs, load contributed by

the charging stations in use at the time of peak total establishment is to be obtained. To obtain this

load contribution, time at which simulated demand data of each month is maximum has to be

known. Demand developed at that particular point of time will be the demand contributed by the

charging stations. Demand costs (DC) are obtained by multiplying the obtained monthly peak total

demands with Demand charge ($/kW) from the rate structure (Table 3.4). Demand costs

contributed by the charging stations (DCCS) can be estimated by multiplying their load contribution

at the peak total demand hour (LP) with demand charges. The relations used for estimation are

shown below.

kW = NR x P

DC = Peak total demand x $/kW

DCCS = LP x $/kW

Using the Energy Costs and the Demand Costs, the total costs for the electricity supplied to charge

all the simulated EV arrivals for corresponding charging times is estimated. The total costs (TC)

in dollars are the sum of Energy Costs (EC) and the Demand Costs (DC) as shown in the following

relation.

TC = EC + DC

Using this relation, total costs for charging Tesla® and other regular EV arrivals are calculated

separately and also the total costs for the facility considered with three charging stations are

estimated for individual months for a year.

46
3.8. Limitations

This section explains different assumptions made in various stages of the model and the limitations

of the overall model developed.

1. Simulation of EV arrivals depending on weather severity and time of the year on the basis of

maximum and minimum EV arrivals in the past.

2. The model is capable of simulating only a large time slot of one hour instead of a few minutes.

3. Demand analysis is performed for one hour rolling peaks instead of 15 minute rolling peaks.

3.9. Conclusion

This chapter explains the problem this research is addressing to, and the approach we are following

to simulate the EV arrival and charging patterns in the initial sections. Various methods and

software tools used to meet the objectives in this work are discussed in the later sections. All the

steps involved in development of the first half of the work, the EV arrival pattern spreadsheet

model are elucidated. The capabilities of this spreadsheet model and various factors considered in

the process are discussed in detail. Charging pattern model by simulation using ARENA®

simulation software and different modules in the simulation model are explained with the help of

figures and tables. The calculations involved in Energy consumption, monthly peak demand and

electricity supply costs associated for the simulated year are explained. Assumptions made in the

development of the models and their limitations are listed in the end of this chapter.

47
4. System Execution and Results Discussion

This chapter considers a sample simulation to explain the models and how a user should proceed

till the end of the simulation. Different results obtained and corresponding graphs are presented.

Sensitivity analysis of electrical demand and supply costs with varying weather severity and

number of charging stations.

4.1. Energy Assessment at a Public Facility

Electric utility providers bill the facilities on a commercial rate schedule which decides the rate

structure charges for the energy consumption, demand charges and other charges. The facility

considered in this study has an energy consumption of 7,516,720 kWh in the year 2015. The

purpose of this energy assessment is to evaluate the possibility of getting into a better rate schedule

by reducing their baseline energy consumption. As a part of the energy assessment, utility bill

analysis was performed to understand their energy consumption by the major energy consumers

in different months and estimate the average costs of energy consumption and demand. The rate

structure obtained was reported in Table 3.4 for cost estimates after the simulation.

4.2. Electric Vehicle arrival pattern spreadsheet model with Sample Inputs

The first part of the simulation is the EV arrival pattern generation using the spreadsheet model

developed by giving inputs to the model. The first step of the simulation is to clear the existing

data in the spreadsheet model. The simulated data from the previous runs can be cleared by clicking

the button saying ‘Clear data’. After clearing the data from previous runs, user can start the

simulation by clicking the button saying ‘Generate EV Arrivals’. This generates a message box

requesting for minimum number of EVs arriving on any day over the past. Once the minimum

number of EV arrivals are entered, the model promptly requests for maximum number of EVs

arriving on any day over the past in a message box. After answering the maximum arrivals, it

48
requests for probability of Tesla® EV arrivals around a year as a fraction. Once the fraction input

was given, another message box appears requesting for probability of weather severity as a

fraction. On answering the last input, model simulates the EV arrival pattern with number of EV

arrivals of each type per each day for a year. Consider the inputs for minimum arrivals, maximum

arrivals, probability of Tesla® EVs and Weather severity probability as 0,10,0.4 and 0.3

respectively as shown in Figure 4.1.

Figure 4.1. Input Boxes for EV Arrival Pattern

Arrival patterns as plots with number of EV arrivals of each type against 365 days in a year are

also generated a shown in Figure 4.2. After generating the EV arrivals, the user have to generate

arrival times for Regular EV and Tesla® EVs by clicking on ‘Generate Regular EV Times’ button

and ‘Generate Tesla® EV Times’ button respectively one after the other. This generates the arrival

times for both types of EVs in separate sheets. Histogram showing monthly EV arrivals with both

type EVs and total EVs data will be generated as shown in Figure 4.3. After getting arrival times,

user is supposed to generate schedule for ARENA® simulation based on the generated arrival

times by clicking ‘Generate Arena Input’ button on ‘Arrival Pattern’ spreadsheet.

49
Figure 4.2. EV Arrival Patterns

Monthly Arrivals

250
235
205
185 190
175
150 150 140 144 145 145 150
135
114 106 105 114
98 91 92 95 92 92 91 100
85 83 75
59 71 67
52 43 53 53

No. of Cars No. of Teslas No. of Regular

Figure 4.3.Histogram representing Monthly EV Arrivals

50
4.3. Charging Pattern and Logistics Modelling Simulation with Sample Inputs

The input schedule generated for EVs of both the types has to be input in schedule module of the

charging pattern simulation model. Resources i.e. charging stations can be modified in the resource

module of the model. For our simulation, two Schneider® charging stations and a Tesla® charging

station are reflected as in the facility considered for our work. The simulation is then run which

generates two output files at the end.

4.3.1. Energy Consumption

The first output spreadsheet file gives the energy consumption and the energy costs associated per

each EV for both the types. It displays the data for arrival times, wait times, and charging times

beside each EV entity for all the EVs charged in individual spreadsheets for each type of EV. The

second output file has the resource utilization and energy consumption for each hour for a

simulated year. The model also generates monthly energy consumption for charging stations of

both the types. Total facility energy consumption and costs are also generated for each month in a

year and a histograms were plotted separately.

4.3.2. Electrical Demand

The spreadsheet ‘Demand’ in the second output file displays the electrical load by the charging

stations of each type and the total demand for each hour for a year. Building load is simulated and

total demand is estimated automatically in the same spreadsheet alongside for every hour in a

simulated year. Rolling total demand is generated and plotted for each hour in a year. Monthly

peak demand is the maximum of rolling one hour total peaks for that month. Demand costs

contributed by the charging stations (DCCS) can be estimated by multiplying their load contribution

at the peak total demand hour (LP) with demand charges. Monthly peak demands and costs

associated with them are also generated and plotted separately.

51
4.3.3. Total Electric costs

The model is capable of estimating the total electric supply costs as the sum of energy and demand

costs.

4.4. Sensitivity Analysis

The effects on energy consumption, demand and total costs with variation of probabilities of

weather severity and different number of charging stations are analyzed. The results generated by

keeping all the other variables constant and other than the required one are plotted and analyzed.

4.4.1. Weather Severity

To observe the effect of weather severity variation on energy consumption, demand and costs

associated a graphs showing monthly energy consumption, demand and total costs are plotted

varying the probability of weather severity keeping same number of minimum arrivals, maximum

arrivals and probability of Tesla® EVs constant. Two simulation runs are performed with

probability of weather severity values considered to be 0.5 and 0.4 with number of minimum

arrivals, maximum arrivals and probability of Tesla® EVs to be 0, 5 and 0.3 respectively. The

graphs for Monthly peak demand, demand costs and monthly costs for the considered number of

charging stations are plotted below as Figure 4.4, Figure 4.5 and Figure 4.6 respectively.

52
Peak Demand
55
50
45
40
35
30
25
20

WF =0.5 WF=0.4

Figure 4.4. Monthly peak Demand Vs Weather Severity

Energy Consumption, kWh


4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
-

WF = 0.5 WF = 0.4

Figure 4.5. Energy Consumption Vs Weather

53
Total Monthly Costs
$800
$700
$600
$500
$400
$300
$200
$100
$-

WF = 0.5 WF = 0.4

Figure 4.6. Total Monthly Costs Vs Weather

4.4.2. Number of Charging Stations

To observe the effect on energy consumption, demand and costs associated by varying number of

charging stations, graphs showing monthly energy consumption, demand and total costs are

plotted varying number of charging stations keeping the number of minimum arrivals, maximum

arrivals, probability of Tesla® EVs and Weather severity constant. Three simulation runs are

performed with probability of weather severity values considered to be 0.3 and with number of

minimum arrivals, maximum arrivals and probability of Tesla® EVs to be 0, 5 and 0.3

respectively.

1. One Tesla® Charging Station and One Schneider® Charging Station

2. Two Tesla® Charging Stations and Three Schneider® Charging Stations

3. One Tesla® Charging Station and Two Schneider® Charging Stations

The graphs for Monthly peak demand, demand costs and monthly costs for the considered number

of charging stations are plotted below as Figure 4.7, Figure 4.8 and Figure 4.9 respectively.

54
Peak Demand
80
75
70
65
60
kW

55
50
45
40
35
30

One Schneider One Tesla One Schneider Two Tesla Three Schneider Two Tesla

Figure 4.7. Peak Demand Vs Number of Charging Stations

Energy Consumption
5,000
4,500
4,000
3,500
3,000
kWh

2,500
2,000
1,500
1,000
500
-

One Schneider One Tesla One Schneider Two Tesla Three Schneider Two Tesla

Figure 4.8. Energy Consumption Vs Number of Charging Stations

55
Total Monthly Costs
$1,200

$1,000

$800

$600

$400

$200

$-

One Schneider One Tesla One Schneider Two Tesla Three Schneider Two Tesla

Figure 4.9. Total Monthly Costs Vs Number of Charging Stations

5. Conclusions and Future Work

5.1. Conclusions

This research focused on forecasting the arrival traffic density and charging pattern of Plug-in

Electric Vehicles (PEVs) based on pertinent factors across various seasons and holidays over a

year. A Monte Carlo simulation of a scenario depicting traffic arrival patterns using various pre-

recorded and categorical data and based on weather Severity and time of the year. A discrete event

simulation modelling the charging patterns of the EV arrivals based on the arrival pattern

generated.

Demand analysis of the considered public facility based on electrical supply requirements over

different times of the year is performed to curtail demand and save on demand charges. The

56
possibility of rate schedule change to reduce demand charges with the addition of charging stations

can be evaluated using the simulated data. The facility considered in the study was already being

billed on the utility provider’s largest demand drawing facilities’ rate schedule. The kilowatt

demand data from multiple simulation runs performed is more than the existing larger peak

demand and hence can only be billed on the same rate schedule. So it is observed that, this facility

cannot reduce demand charges by changing the existing rate schedule.

It is observed that the electrical peak demand established by the facility for a month depends not

only on the number of existing charging stations, number of cars charging at the same time, but

also on the peak demand established by rest of the buildings. In this study, there are times, in which

charging stations and the buildings together contribute the peak demand and those in which

buildings alone establish the peak. This tool is capable of estimating the total demand generated

and demand drawn by the charging stations and the buildings separately for every hour in a

simulated year. This demand analysis helps the user understand the demand behavior at different

times and take appropriate strategic decisions to curtail the monthly peak demand. The simulated

energy consumption, demand and costs associated obtained can support a decision on the optimal

number of charging stations to be established in a public facility which are sustainable and

economically viable.

5.2. Future Work

Influence of other factors like availability of historic places, public attractions and commercial

facilities near the public facility can be evaluated. EV arrival density at different time slots is

considered constant in the model. Variations in arrival density with different times of the day can

be evaluated further. Demand analysis is performed for one hour time intervals due to the

constraints in data size. This can be improved by estimating demand for fifteen minute intervals

57
for even accurate estimates of peak demand and costs incurred. Capital, installation and

maintenance costs involved with establishment of charging infrastructure can be evaluated along

with operational costs to perform a detailed cost analysis further.

The effects of vehicle’s climate control system on EV energy consumption in different seasons are

not considered in this study and is an area to be focused on in future. Detailed study on the

influence of battery ambient temperature on battery discharge and degradation can also help in

better understanding of the EV energy consumption. This study considers multiple arrivals of the

same EV as different EV arrivals. Depending on the type of public facility, whether a gas station

or a place of interest, multiple arrivals of the same EV makes a difference in the EV arrival pattern

and future studies should consider its effect.

58
6. References

[1] International Energy Outlook 2016, U.S. Energy Information Administration, Information

publication, Pg 13, 2016 [2] U. Energy Information Administration, “Monthly Energy

Review – July 2018,” 2018.

[2] “Monthly Energy Review – July 2018,” U. S. Energy Information Administration,

Information publication, Table 2.5, Pg 39, 2018.

[3] Towards Green Growth, OECD Green Growth Studies, The Organisation for Economic Co-

operation and Development (2011), OECD Publishing, Paris, 2011.

[4] Fast Facts-U.S.Transportation Sector Greenhouse Gas Emissions 1990 –2016, Office of

Transportation and Air Quality, United States Environmental Protection Agency, July 2018.

[5] T.A.Boden, G.Marland, and R.J.Andres, (2017), National CO2 Emissions from Fossil-Fuel

Burning, Cement Manufacture, and Gas Flaring: 1751-2014, Carbon Dioxide Information

Analysis Center, Oak Ridge National Laboratory, U.S. Department of Energy, 2017.

[6] Alternative Fuels Data Center, Office of Energy Efficiency & Renewable Energy, US

Department of Energy, “How Do All-Electric Cars Work?,” 2018.

[7] M. C. Falvo, D. Sbordone, I. S. Bayram, and M. Devetsikiotis, “EV Charging Stations And

Modes: International Standards,” in 2014 International Symposium on Power Electronics,

Electrical Drives, Automation and Motion, 2014, pp. 1134–1139.

[8] D.Gohlke, & Y.Zhou, Impacts of Electrification of Light-Duty Vehicles in the United

States, 2010 – 2017, Argonne National Lab. (ANL), Technical Report, Argonne, IL United

States, Jan 2018.

59
[9] R. R. Heffner, K. S. Kurani, and T. S. Turrentine, “Symbolism In California’s Early Market

For Hybrid Electric Vehicles,” Transportation Research Part D: Transport and

Environment, vol. 12, no. 6, pp. 396–413, Aug. 2007.

[10] Research and Innovative Technology Administration, U.S. Department Of Transportation,

and Bureau of Transportation Statistics, “National Transportation Statistics,” pp. 1–470,

2015.

[11] O. Egbue and S. Long, “Barriers to Widespread Adoption of Electric Vehicles: An Analysis

of Consumer Attitudes and Perceptions,” Energy Policy, vol. 48, pp. 717–729, Sep. 2012.

[12] E. Wood, J. Neubauer, and E. Burton, “Measuring the Benefits of Public Chargers and

Improving Infrastructure Deployments Using Advanced Simulation Tools Preprint,”

National Renewable Energy Laboratory, Information Publication, February, 2015.

[13] W. Sierzchula, S. Bakker, K. Maat, and B. Van Wee, “The Influence Of Financial Incentives

And Other Socio-Economic Factors On Electric Vehicle Adoption,” Energy Policy, vol. 68,

pp. 183–194, May 2014.

[14] E. Narassimhan and C. Johnson, “The Effect of State Incentives on Plug-in Electric Vehicle

Purchases,” National Renewable Energy Laboratory, Office of Energy Efficiency and

Renewable Energy, U.S. Department of Energy, Information Publication, August 21, 2014.

[15] “Electric Vehicle Supply Equipment (EVSE) Rebate Program 2.0.” [Online]. Available:

http://energy.maryland.gov/transportation/Pages/incentives_evserebate.aspx. [Accessed:

09-Jun-2018].

[16] S. Guner, A. Ozdemir, and G. Serbes, “Impact Of Car Arrival/Departure Patterns On EV

60
Parking Lot Energy Storage Capacity,” in 2016 International Conference on Probabilistic

Methods Applied to Power Systems (PMAPS), 2016, pp. 1–5.

[17] X. Xi, R. Sioshansi, and V. Marano, “Simulation–Optimization Model For Location Of A

Public Electric Vehicle Charging Infrastructure,” Transportation Research Part D:

Transport and Environment, vol. 22, pp. 60–69, Jul. 2013.

[18] Y. Cao, S. Tang, C. Li, P. Zhang, Y. Tan, Z. Zhang, and J. Li , “An Optimized EV Charging

Model Considering TOU Price and SOC Curve,” IEEE Transactions on Smart Grid, vol. 3,

no. 1, pp. 388–393, Mar. 2012.

[19] F. Kong, J. Jiang, Z. Ding, J. Hu, W. Guo, and L. Wang, “A Personalized Rolling Optimal

Charging Schedule for Plug-In Hybrid Electric Vehicle Based on Statistical Energy Demand

Analysis and Heuristic Algorithm,” Energies, vol. 10, no. 9, p. 1333, Sep. 2017.

[20] S. Faridimehr, S. Venkatachalam, and R. B. Chinnam, “A Stochastic Programming

Approach for Electric Vehicle Charging Network Design,” IEEE Transactions on

Intelligent Transportation Systems, pp. 1–13, 2018.

[21] M. Alizadeh, A. Scaglione, J. Davies, and K. S. Kurani, “A Scalable Stochastic Model for

the Electricity Demand of Electric and Plug-In Hybrid Vehicles,” IEEE Transactions on

Smart Grid, vol. 5, no. 2, 2014.

[22] T. S. Hoon, K. L. Kee, and P. Singh, “Learning Mathematics Using Heuristic Approach,”

Procedia - Social and Behavioral Sciences, vol. 90, pp. 862–869, Oct. 2013.

[23] “Severe Weather Data | National Centers for Environmental Information (NCEI) formerly

known as National Climatic Data Center (NCDC).” [Online]. Available:

61
https://www.ncdc.noaa.gov/data-access/severe-weather. [Accessed: 11-Jun-2018].

[24] T. Aikoh, R. Abe, R. Kohsaka, M. Iwata, and Y. Shoji, “Factors Influencing Visitors to

Suburban Open Space Areas near a Northern Japanese City,” Forests, vol. 3, no. 2, pp. 155–

165, Apr. 2012.

62
7. Appendix
Private Sub CommandButton1_Click()

Dim min, max As Integer

Dim F As Single

Dim D, S, HF, i, j, l, m, a, b As Integer

Dim k, c As Double

min = InputBox("Minimum number of Electric Vehicles arriving per day? Please enter a number between

0 and 30,000", "Minimum arrivals") 'Asking Minimum number of Electric cars arriving per day

max = InputBox("Maximum number of Electric Vehicles arriving per day? Please enter a number

between 0 and 30,000", "Maximum arrivals") 'Asking Maximum number of Electric cars arriving per day

F = InputBox("Probability of Tesla® Vehicles arriving round the year? Please enter a fraction between 0

and 1", "Fraction of Tesla® vehicles ") 'Asking fraction of Tesla® cars arriving

a = min

b = max

b = (a + b) / 2

Worksheets(1).Range("F:G") = ""

Worksheets(1).Cells(1, 1) = "Date"

Worksheets(1).Cells(1, 2) = "Day"

Worksheets(1).Cells(1, 3) = "Weather Factor"

Worksheets(1).Cells(1, 4) = "Holiday Factor"

Worksheets(1).Cells(1, 5) = "No. of Cars"

Worksheets(1).Cells(1, 6) = "No. of Tesla®s"

Worksheets(1).Cells(1, 7) = "No. of Regular"

Worksheets(1).Cells(5, 10) = min

Worksheets(1).Cells(6, 10) = max

63
Worksheets(1).Cells(8, 10) = F

For i = 2 To 366

Worksheets(1).Cells(i, 1) = i - 1

Worksheets(1).Cells(i, 2).Formula = "=Weekday( A" & i & ", 1 )"

k = Rnd()

If (i - 1 > 59 And i - 1 <= 335) Then

If (k <= 0.7) Then '<<< CHANGE AS DESIRED

Worksheets(1).Cells(i, 3) = 1

ElseIf (k > 0.7) Then '<<< CHANGE AS DESIRED

Worksheets(1).Cells(i, 3) = 0

End If

ElseIf (i - 1 < 60 Or i - 1 > 335) Then

If ((i - 1) Mod 3 = 1) Then

If (k <= 0.7) Then '<<< CHANGE AS DESIRED

D=1

Worksheets(1).Cells(i, 3) = D

ElseIf (k > 0.7) Then '<<< CHANGE AS DESIRED

D=0

Worksheets(1).Cells(i, 3) = D

End If

ElseIf ((i - 1) Mod 3 >= 0) Then

Worksheets(1).Cells(i, 3) = D

End If

End If

64
Worksheets(1).Cells(i, 4).Formula = "=IF(OR(AND(99<A" & i & ",A" & i & "<111),AND(121<A" &

i & ",A" & i & "<214),AND(320<A" & i & ",A" & i & "<331),B" & i & "=6,B" & i &

"=7,COUNTIF($K$21:$K$46,A" & i & "))=TRUE,1,0)"

If Worksheets(1).Cells(i, 3) = 0 Then

Worksheets(1).Cells(i, 5) = min

ElseIf Worksheets(1).Cells(i, 3) = 1 And Worksheets(1).Cells(i, 4) = 0 Then

Worksheets(1).Cells(i, 5) = Application.WorksheetFunction.RoundUp(b, 0)

ElseIf Worksheets(1).Cells(i, 3) = 1 And Worksheets(1).Cells(i, 4) = 1 Then

Worksheets(1).Cells(i, 5) = max

End If

l=1

m=1

For j = 1 To Worksheets(1).Cells(i, 5)

c = Rnd()

If c <= (1 - F) Then '<<< CHANGE AS DESIRED

Worksheets(1).Cells(i, 7) = l

l=l+1

ElseIf (c > (1 - F)) Then '<<< CHANGE AS DESIRED

Worksheets(1).Cells(i, 6) = m

m=m+1

End If

Next j

If Worksheets(1).Cells(i, 6) = "" Then

Worksheets(1).Cells(i, 6) = 0

End If

If Worksheets(1).Cells(i, 7) = "" Then

65
Worksheets(1).Cells(i, 7) = 0

End If

Next i

End Sub

Private Sub CommandButton2_Click()

Dim i, a, cars, k, l As Integer

Dim j As Long

Dim Low As Double

Dim High As Double

Dim Wk As Workbook

a=2

Low = 1 '<<< CHANGE AS DESIRED

High = 24 '<<< CHANGE AS DESIRED

ActiveWorkbook.Sheets.Add After:=Worksheets(Worksheets.Count)

Sheets(ActiveSheet.Name).Name = "Regular Ex1"

ActiveWorkbook.Sheets.Add After:=Worksheets(Worksheets.Count)

Sheets(ActiveSheet.Name).Name = "Regular Numbers"

Worksheets("Regular Numbers").Cells(1, 1) = "Arrival time (hours)"

Worksheets("Regular Numbers").Cells(1, 3) = "Inter Arrival time (hours)"

Worksheets("Regular Numbers").Cells(1, 8) = "Date"

Worksheets("Regular Numbers").Cells(1, 9) = "No. of Regular cars"

For i = 1 To 365

Worksheets("Regular Numbers").Cells(i + 1, 8) = i

Worksheets("Regular Numbers").Cells(i + 1, 10) = "--------->"

Worksheets("Regular Numbers").Cells(i + 1, 9) = Worksheets(1).Cells(i + 1, 7)

66
cars = Worksheets("Regular Numbers").Cells(i + 1, 9)

If (cars = 0) Then

GoTo ErrorHandler:

Else

For j = 1 To cars

Worksheets("Regular Numbers").Cells(i + 1, j + 10) = Round((i - 1) * 24 + (High - Low + 1) *

Rnd(), 0)

Worksheets("Regular Ex1").Cells(j, 1) = Worksheets("Regular Numbers").Cells(i + 1, j + 10)

Next j

Worksheets("Regular Ex1").Range("A1:A" & j).Sort Key1:=Worksheets("Regular Ex1").Range("A1:A"

& j), Order1:=xlAscending, Header:=xlNo

For j = 1 To cars

Worksheets("Regular Numbers").Cells(i + 1, j + 10) = Worksheets("Regular Ex1").Cells(j, 1)

Worksheets("Regular Numbers").Cells(a + 1, 1) = Worksheets("Regular Numbers").Cells(i + 1, j +

10)

Worksheets("Regular Ex1").Cells(j, 1) = ""

Worksheets("Regular Numbers").Cells(a + 1, 3) = Worksheets("Regular Numbers").Cells(a + 1, 1) -

Worksheets("Regular Numbers").Cells(a, 1)

a=a+1

Next j

End If

Worksheets("Regular Numbers").Cells(2, 3) = 0

ErrorHandler:

Next i

Worksheets("Regular Ex1").Delete

Worksheets(1).Activate

67
End Sub

Private Sub CommandButton3_Click()

Dim i, a, cars, k, l As Integer

Dim j As Long

Dim Low As Double

Dim High As Double

Dim Wk As Workbook

a=2

Low = 1 '<<< CHANGE AS DESIRED

High = 24 '<<< CHANGE AS DESIRED

ActiveWorkbook.Sheets.Add After:=Worksheets(Worksheets.Count)

Sheets(ActiveSheet.Name).Name = "Tesla® Ex1"

ActiveWorkbook.Sheets.Add After:=Worksheets(Worksheets.Count)

Sheets(ActiveSheet.Name).Name = "Tesla® Numbers"

Worksheets("Tesla® Numbers").Cells(1, 1) = "Arrival time (hours)"

Worksheets("Tesla® Numbers").Cells(1, 3) = "Inter Arrival time (hours)"

Worksheets("Tesla® Numbers").Cells(1, 8) = "Date"

Worksheets("Tesla® Numbers").Cells(1, 9) = "No. of Tesla® cars"

For i = 1 To 365

Worksheets("Tesla® Numbers").Cells(i + 1, 8) = i

Worksheets("Tesla® Numbers").Cells(i + 1, 10) = "--------->"

Worksheets("Tesla® Numbers").Cells(i + 1, 9) = Worksheets(1).Cells(i + 1, 6)

cars = Worksheets("Tesla® Numbers").Cells(i + 1, 9)

If (cars = 0) Then

GoTo ErrorHandler:

Else

68
For j = 1 To cars

Worksheets("Tesla® Numbers").Cells(i + 1, j + 10) = Round((i - 1) * 24 + (High - Low + 1) *

Rnd(), 0)

Worksheets("Tesla® Ex1").Cells(j, 1) = Worksheets("Tesla® Numbers").Cells(i + 1, j + 10)

Next j

Worksheets("Tesla® Ex1").Range("A1:A" & j).Sort Key1:=Worksheets("Tesla® Ex1").Range("A1:A" &

j), Order1:=xlAscending, Header:=xlNo

For j = 1 To cars

Worksheets("Tesla® Numbers").Cells(i + 1, j + 10) = Worksheets("Tesla® Ex1").Cells(j, 1)

Worksheets("Tesla® Numbers").Cells(a + 1, 1) = Worksheets("Tesla® Numbers").Cells(i + 1, j +

10)

Worksheets("Tesla® Ex1").Cells(j, 1) = ""

Worksheets("Tesla® Numbers").Cells(a + 1, 3) = Worksheets("Tesla® Numbers").Cells(a + 1, 1) -

Worksheets("Tesla® Numbers").Cells(a, 1)

a=a+1

Next j

End If

Worksheets("Tesla® Numbers").Cells(2, 3) = 0

ErrorHandler:

Next i

Worksheets("Tesla® Ex1").Delete

Worksheets("Monthly Data").Activate

End Sub

Private Sub CommandButton4_Click()

Worksheets(1).Range("A1:G366").ClearContents

69
Worksheets(1).Range("J5:J6").ClearContents

Worksheets(1).Range("J8").ClearContents

Worksheets("Tesla® Numbers").Delete

Worksheets("Regular Numbers").Delete

Worksheets("Tesla® for Arena").Delete

Worksheets("Regular Cars for Arena").Delete

End Sub

Private Sub CommandButton5_Click()

Dim i, x, y, j, a, b As Integer

ActiveWorkbook.Sheets.Add After:=Worksheets(Worksheets.Count)

b = Worksheets("Arrival Pattern").Cells(6, 14)

x = Worksheets("Arrival Pattern").Cells(6, 15)

Sheets(ActiveSheet.Name).Name = "Tesla® for Arena"

ActiveSheet.Cells(3, 1).Formula = "='Tesla® Numbers'!A3"

ActiveSheet.Range("A3").Copy

ActiveSheet.Range("A4:A" & b).Select

ActiveSheet.Paste

ActiveSheet.Cells(3, 2).Formula = "='Tesla® Numbers'!C3"

ActiveSheet.Range("B3").Copy

ActiveSheet.Range("B4:B" & b).Select

ActiveSheet.Paste

ActiveWorkbook.Sheets.Add After:=Worksheets(Worksheets.Count)

Sheets(ActiveSheet.Name).Name = "Regular Cars for Arena"

ActiveSheet.Cells(3, 2).Formula = "='Regular Numbers'!C3"

ActiveSheet.Range("B3").Copy

ActiveSheet.Range("B4:B" & x).Select

70
ActiveSheet.Paste

ActiveSheet.Cells(3, 1).Formula = "='Regular Numbers'!A3"

ActiveSheet.Range("A3").Copy

ActiveSheet.Range("A4:A" & x).Select

ActiveSheet.Paste

Worksheets("Arrival Pattern").Activate

Worksheets("Tesla® for Arena").Activate

For a = 1 To 2

If a = 2 Then

Worksheets("Regular Cars for Arena").Activate

End If

j=3

b = Worksheets("Arrival Pattern").Cells(6, 13 + a)

For i = 3 To b

x = ActiveSheet.Cells(i, 2)

If (x = 0) Then

If (i = b + 1) Then

If (j = 8762) Then

GoTo ErrorHandler:

Else

For j = j To 8762

ActiveSheet.Cells(j, 3) = 0

Next j

End If

Else

ActiveSheet.Cells(j - 1, 3) = ActiveSheet.Cells(j - 1, 3) + 1

71
End If

Else

For y = 1 To x - 1

ActiveSheet.Cells(j, 3) = 0

j=j+1

Next y

If (x > 0) Then

ActiveSheet.Cells(j, 3) = 1

j=j+1

End If

End If

Next i

ErrorHandler:

Next a

Worksheets("Tesla® for Arena").Cells(1, 3) = "Tesla® Arena Input"

Worksheets("Regular Cars for Arena").Cells(1, 3) = "Schneider® Arena Input"

End Sub