5. Storage
If the motor is not installed immediately, it must be stored in a dry and clean environment, with relative humidity
not exceeding 60%, with an ambient temperature between 5 ºC and 40 ºC, without sudden temperature
changes, free of dust, vibrations, gases or corrosive agents. The motor must be stored in horizontal position,
unless specifically designed for vertical operation, without placing objects on it. Do not remove the protection
grease from shaft end to prevent rust.
If the motor are fitted with space heaters, they must always be turned on during the storage period or when the
installed motor is out of operation. Space heaters will prevent water condensation inside the motor and keep
the winding insulation resistance within acceptable levels. Store the motor in such position that the condensed
water can be easily drained. If fitted, remove pulleys or couplings from the shaft end (more information are given
on item 6).
The space heaters should never be energized when the motor is in operation.
ENGLISH
Packaging type Frame sizes Maximum stacking quantity
IEC 63 to 132 Indicated on the top side of
Cardboard box
NEMA 143 to 215 the cardboard box
IEC 63 to 315
06
NEMA 48 to 504/5
IEC 355
Wood crate 03
NEMA 586/7 and 588/9
HGF IEC 315 to 630
Indicated on the packaging
HGF NEMA 5000 to 9600
Notes:
1) Never stack larger packaging onto smaller packaging;
2) Align the packaging correctly (see Figure 5.1 and Figure 5.2);
3) The feet of the crates above should always be supported by suitable wood battens (Figure 5.3) and never stand on the steel tape or
without support (Figure 5.4);
4) When stacking smaller crates onto longer crates, always ensure that suitable wooden supports are provided to withstand the weight
(see Figure 5.5). This condition usually occurs with motor packaging above IEC 225S/M (NEMA 364/5T) frame sizes.
ENGLISH
5.3 Bearings
5.3.1 Grease lubricated bearings
We recommend rotating the motor shaft at least once a month (by hand, at least five revolutions, stopping the
shaft at a different position from the original one). If the motor is fitted with shaft locking device, remove it before
rotating the shaft and install it again before performing any handling procedure. Vertical motors may be stored
in the vertical or in horizontal position. If motors with open bearings are stored longer than six months, the
bearings must be relubricated according to item 8.2 before commissioning of the motor.
If the motor is stored for longer than 2 years, the bearings must be replaced or removed, washed, inspected
and relubricated according to item 8.2.
ENGLISH
The oil must always be removed when the motor has to be handled. If the oil mist system is not operating after
installation, fill the bearings with oil to prevent bearing rusting. During the storage period, rotate the shaft by
hand, at least five revolutions, stopping it at a different position from the original one. Before starting the motor,
all bearing protection oil must be drained from the bearing and the oil mist system must be switched ON.
The insulation resistance must be measured with a megohmmeter. The machine must be in cold state and
disconnected from the power supply.
To prevent the risk of an electrical shock, ground the terminals before and after each measurement.
Ground the capacitor (if any) to ensure that it is fully discharged before the measurement is taken.
It is recommended to insulate and test each phase separately. This procedure allows the comparison of the
insulation resistance between each phase. During the test of one phase, the other phases must be grounded.
The test of all phases simultaneously evaluates the insulation resistance to ground only but does not evaluate
the insulation resistance between the phases.
The power supply cables, switches, capacitors and other external devices connected to the motor may
considerably influence the insulation resistance measurement. Thus all external devices must be disconnected
and grounded during the insulation resistance measurement.
Measure the insulation resistance one minute after the voltage has been applied to the winding. The applied
voltage should be as shown in Table 5.3.
Table 5.3 - Voltage for the insulation resistance
Winding rated voltage (V) Testing voltage for measuring the insulation resistance (V)
< 1000 500
1000 - 2500 500 - 1000
2501 - 5000 1000 - 2500
5001 - 12000 2500 - 5000
> 12000 5000 - 10000
The reading of the insulation resistance must be corrected to 40 °C as shown in the Table 5.4.
Measuring temperature Correction factor of the Measuring temperature of Correction factor of the
of the insulation insulation resistance the insulation resistance insulation resistance
resistance (°C) corrected to 40 °C (°C) corrected to 40 °C
10 0.125 30 0.500
11 0.134 31 0.536
12 0.144 32 0.574
13 0.154 33 0.616
14 0.165 34 0.660
15 0.177 35 0.707
16 0.189 36 0.758
17 0.203 37 0.812
18 0.218 38 0.871
19 0.233 39 0.933
20 0.250 40 1.000
21 0.268 41 1.072
22 0.287 42 1.149
23 0.308 43 1.231
24 0.330 44 1.320
25 0.354 45 1.414
26 0.379 46 1.516
27 0.406 47 1.625
28 0.435 48 1.741
29 0.467 49 1.866
30 0.500 50 2.000
The motor insulation condition must be evaluated by comparing the measured value with the values
indicated in Table 5.5 (corrected to 40 °C):
Table 5.5 - Evaluation of the insulation system
Limit value for rated voltage Limit value for rated voltage
Situation
up to 1.1 kV (MΩ) above 1.1 kV (MΩ)
Dangerous. The motor can not
Up to 5 Up to 100
be operated in this condition
5 to 100 100 to 500 Regular
100 to 500 Higher than 500 Good
Higher than 500 Higher than 1000 Excellent
The values indicated in the table should be considered only as reference values. It is advisable to log all
measured values to provide a quick and easy overview on the machine insulation resistance.
If the insulation resistance is low, moisture may be present in the stator windings. In this case the motor
should be removed and transported to a WEG authorized Service Center for proper evaluation and repair
(This service is not covered by the warranty). To improve the insulation resistance through the drying
process, see section 8.4.