4 - Project Cost Management
4 - Project Cost Management
24/08/2022
Cost Estimation vs. Pricing
Cost estimating:
Assessing how much it
will cost the organization
Cost
to provide the product
or service
Price
Profit
Pricing:
Assessing how much
the organization will
charge for the
product or service
PROJECT COST MANAGEMENT
Project cost management includes the processes involved
in estimating, budgeting, and controlling costs so that the
project can be completed within the approved budget
3
Project Management Process Groups
Knowledge Areas
Monitoring and Controlling Closing Process
Initiating Process Group Planning Process Group Executing Process Group
Process Group Group
4- Project Integration 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project 4.5 Monitor and Control Project 4.7 Close
Management Work Work Project
4.4 Manage Project Knowledge 4.6 Perform Integrated Change
Control
5- Project Scope Management 5.1 Plan Scope Management 5.5 Validate Scope
5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
7- Project Cost Management 7.1 Plan Cost Management 7.4 Control Costs
7.2 Estimate Costs
7.3 Determine Budget
8- Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9- Project Resource 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
Management 9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
10- Project Communications 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications
Management
11- Project Risk Management 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12- Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
13- Project Stakeholder 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
Management Engagement Engagement 4
We are about to produce 20 tables in 20 days cost is $20 for each.
How much BAC = ???
BAC = $20 * 20 tables = $400
Today is day 4 How much is the PV ?
PV = $20 x 4 tables = $80
At day 4 I earned only 3 tables, how much is the EV ?
EV = $20 x 3 tables = $60
AC = ??? X 3 tables = $90
SV = EV – PV = 60 – 80 = -$20
CV =EV – AC = 60 – 90 = -$30
SPI = EV / PV = 60 / 80 = 0.75
CPI = EV / AC = 60 / 90 = 0.666
5
FORECASTING
EAC forecast for ETC at new estimate
EAC = AC+ETC
90+ 300 = 390
EAC forecast for ETC work performed at the budgeted rate
EAC = AC+(BAC-EV )
= 90+ (400-60)=430
EAC forecast for ETC work considering both SPI and CPI factors
EAC =AC+((BAC-EV) /(CPI*SPI))
=90 +((400 – 60 )/ (.495 )) = 770
EAC forecast for work performed at the percent CPI
EAC = BAC/ CPI
=400 / .66 = 600
EACt forecast for the Duration of the project
EACt = ED/SPI
=20 / .75 = 27 Days
Variance at Completion (VAC)
8
Wall Construction
Wall Construction
Time = 1 week per wall
Cost = $ 1,000 per wall,
materials and labor
Total Schedule = 4 weeks
Total Cost = $ 4,000
Working days 5 day per
week starting on Sunday
and finish on Thursday by 5
PM
Assume production is liner
9
5 pm Wednesday, Week 2
10 %
What is the budgeted
value of actual work - EV?
EARNED
Wall 1 100% = $ 1,000
Wall 2 50% = $ 500
Wall 3 10% = $100
Wall 4 0% = 0
50 % EV = $1,600
5 pm Wednesday, Week 2
Schedule Variance = EV - PV
= $1,600 - $1,800
= ($200)
Cost Variance = EV - AC
= $1,600 - $2,250
= ($650)
5 pm Wednesday, Week 2
Performance Indices
PV $1,800
EV $1,600
AC $2,250
SPI = EV / PV
= $1,600 / $1,800
= .9
CPI = EV / AC
= $1,600 / $2,250
= .7
QUESTIONS & ANSWERS EV
1. You are a project manager working on a project that requires 100 widgets to be
built in five weeks. You have just begun week three, with an overall budget of
US $10,000. To date you have spent US $2,000 with 40 widgets successfully
built. What does the cost variance tell you in this circumstance?
2. You are a project manager for a small construction project. Your project was
budgeted for US $72,000 over a six week period. As of today, you've spent US
$22,000 of your budget to complete work that you originally expected would
cost US $24,000. According to your schedule, you should have spent US
$21,000 by this point. Based on these circumstances, your project could be
BEST described as:
A. Over budget
B. On budget
C. Under budget
D. Not having enough information provided
QUESTIONS & ANSWERS EV
A. At this time, we expect the total project to cost 89% more than
planned.
B. When the project is completed we will have spent 89% more
than planned.
C. The project is only progressing at 89% of that planned.
D. The project is only getting 89 cents out of every dollar invested.
QUESTIONS & ANSWERS EV
Given:
BAC = 200
AC = 120
EV = 80
CPI = 0.666
Assuming that current
variances are typical of
future variances, the
estimate at completion
(EAC) is:
A. 220.
B. 260.
C. 300.
D. 320.
19
Questions & Answers EV
1. Given:
BAC = 200
AC = 120
EV = 80
CPI = 0.666
Assuming that current
variances are atypical , the
estimate at completion (EAC)
is:
A. 120.
B. 160.
C. 300.
D. 240.
20
Types Of Costs
Direct Costs
Indirect costs
Fixed costs
Variable costs
Opportunity costs
Sunk costs
Working Capital
21
DEPRECIATION
Accelerated Depreciation
There are two forms of accelerated
depreciation:
1. Double Declining Balance
2. Sum of the Years Digits.
They depreciate faster than straight line.
You do not have to know what these two
forms means or do any calculations.
Present Value
Budgeting technique that debates the
future value of money based on inflation,
Year FV PV
etc.
0 $50,000 $50,000
PV = FV 1 $35,000 $31,819
2 $15,000 $12,397
(1 + r)t
This Means the total benefits (income or revenue) less the cost. To calculate
NPV you need to calculate the present value of each of the income and
revenue figures then add up the present values.
0 0 0 200 200
1 50 45 100 91
2 100 83 0 0
3 300 225 0 0
NPV =353-291=62
PAYBACK PERIOD
Compares the cost to the benefits of The interest (discount) rate where the
different projects. A BCR of > 1 means present value of the benefits exactly
the benefits are grater than the costs. A equals the costs.
BCR of < 1 means the costs are grater The higher the rate, the better the
than the benefits. A BCR =1 means the project.
costs and benefits are the same.
An IRR of 0.15 means that you expect
If the BCR of project A is 2.3 and BCR of the project to return an average of
project B is 1.7 which project would you 15% on your investment over a given
select? time period (usually a number of
years).
sub1 Sub2
costs costs
Project Cost Management
30
Plan Cost Management
Inputs Tools & Techniques Outputs
.1 Project charter .1 Cost management
.1 Expert judgment
.2 Project management plan
plan .2 Data analysis
• Schedule .3 Meetings
management plan
• Risk management
plan
.3 Enterprise
environmental
factors
.4Plan Cost Management is the process of defining how the project costs
Organizational
willprocess
be estimated,
assets budgeted, managed, monitored, and controlled.
The key benefit of this process is that it provides guidance and
direction on how the project costs will be managed throughout the
project.
31
PLAN COST MANAGEMENT
• the project charter provides the preapproved financial resources from which the detailed project costs
are developed. The project charter also defines the project approval requirements that will influence the
management of the project costs.
DATA ANALYSIS:includes but is not limited to alternatives analysis. Alternatives analysis can include
reviewing strategic funding options such as: self-funding, funding with equity, or funding with debt. It
can also include consideration of ways to acquire project resources such as making, purchasing, renting,
or leasing.
the cost management plan can establish the following:
Units of measure, Level of precision, Level of accuracy,
Control thresholds, Rules of performance measurement,
Reporting formats,
Estimate Costs
34
Determine budget
Inputs Tools & Techniques Outputs
.1 Project management plan .1 Cost baseline
.2 Project funding requirements
• Cost management plan
• Resource management plan
.1 Expert judgment .3 Project documents updates
.2 Cost aggregation • Cost estimates
• Scope baseline
.3 Data analysis • Project schedule
.2 Project documents
• Reserve analysis • Risk register
• Basis of estimates
.4 Historical information review
• Cost estimates
.5 Funding limit reconciliation
• Project schedule
.6 Financing
• Risk register
.3 Business documents
• Business case
• Benefits management plan
.4 Agreements
.5 Enterprise environmental
factors
.6 Organizational process assets
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages
to establish an authorized cost baseline.
The key benefit of this process is that it determines the cost baseline against which project performance can
be monitored and controlled.
DETERMINE BUDGET: TOOLS AND TECHNIQUES
COST BASELINE:The cost baseline is the approved version of the time-phased project
budget, excluding any management reserves, which can only be changed through formal
change control procedures.
DETERMINE BUDGET: OUTPUTS
baseline.
Funding often occurs in incremental amounts, and may not be evenly distributed, which appear as steps.
Cost estimates are updated to record any additional information.
Project schedule Estimated costs for each activity may be recorded as part of the project schedule.
Risk register. New risks identified during this process are recorded in the risk register and managed using the risk
management processes.
Control Costs
Inputs Tools & Techniques Outputs
.1 Project management plan
• Cost management plan .1 Work performance
• Cost baseline .1 Expert judgment information
• Performance measurement .2 Data analysis .2 Cost forecasts
baseline • Earned value analysis .3 Change requests
.2 Project documents • Variance analysis .4 Project management plan
• Lessons learned register • Trend analysis updates
.3 Project funding requirements • Reserve analysis • Cost management plan
.4 Work performance data .3 To-complete performance • Cost baseline
.5 Organizational process assets index • Performance measurement
.4 Project management baseline
information system .5 Project documents updates
• Assumption log
• Basis of estimates
• Cost estimates
• Lessons learned register
• Risk register
Control Costs is the process of monitoring the status of the project to update the project costs and managing changes to
the cost baseline . 40
The key benefit of this process is that it provides the means to recognize variance from the plan in order to take corrective
action and minimize risk.
Project Performance Management
Cost
EAC
Data date
BAC
AC
PV CV= EV - AC
SV= EV - PV
EV
Time
To-Complete Performance index
(TCPI)
43
1- HALF WAY THROUGH THE EXECUTING PROCESSES OF YOUR
PROJECT, A TEAM MEMBER ALERTS YOU TO A POTENTIAL COST
OVERRUN FOR A SPECIFIC DELIVERABLE. WHAT DO YOU DO
FIRST?
A ) Direct
B ) EV
C ) Indirect
D ) fixed
45
3- A PROJECT MANAGER HAS COMPLETED A DETAILED WBS AND
COST ESTIMATES FOR EACH WORK PACKAGE. TO CREATE A COST
BASELINE FROM THIS DATA, THE PROJECT MANAGER WOULD :
46
4- YOU ARE HAVING DIFFICULTY ESTIMATING THE COST OF YOUR
PROJECT. WHISH OF THE FOLLOWING BEST DESCRIBES THE MOST
PROBABLE CAUSE OF YOUR DIFFICULTY?
A ) Earned value
B ) Planned value
C ) Actual cost
D ) Estimate to complete
48
6- IF EARNED VALUE (EV) IS U.S.$300000, ACTUAL COST
(AC) IS U.S.$350000, AND PLANNED VALUE (PV) IS U.S.
$375000, WHAT DOES THE SCHEDULE PERFORMANCE
INDEX (SPI) INDICATE?
49
7- THE FORMULA, EAC = BAC/CPI, ASSUMES THAT:
50
8- FEASIBILITY STUDY ANSWERS THE QUESTION “CAN WE DO
IT?” COST BENEFIT ANALYSIS ANSWER THE QUESTION---------
A ) Should we do it?
B ) Are the safety risks acceptable?
C ) Is it beneficial to have a high level sponsor?
D ) Does the technology exist?
51
9- WHAT TOOL MUST PROJECT MANAGERS RELY UPON TO
ACCURATELY IDENTIFY THE COSTS ASSOCIATED WITH THE
PROJECT?
A ) A bill of materials
B ) A Gantt chart
C ) A precedence diagram network
D ) A work breakdown structure
52