Continuous Beam Example
Continuous Beam Example
Figure above shows a plan view of a school building. It is constructed using cast in-situ
method and the slab spans 3 x 8 m each. Prepare a complete design of beam 2/A-D.
Design data:
Solution
2. Draw the shear force (SFD) and bending moment diagram (BMD).
The coefficients from Table 3.5 can only be applied to continuous beam analysis when
all this provisions are fulfilled.
Beam 2/A-D
w = 39.04 kN/m
8m 8m 8m
+ + +
- - -
+ + +
F = wL = ( 39.04 ) x ( 8 ) = 312.32 kN
w = 39.04 kN/m
8m 8m 8m
+ + +
- - -
+ + +
Assume bar = 20 mm
link = 8 mm
d
h
d = h – c - link - bar/2 = 450 – 25 – 8 - 20/2
= 407 mm
CONTINUOUS BEAM EXAMPLE 3.2
3000 mm 3000 mm
bw = 250 mm
bw = 250 mm bw = 250 mm
Section A-A
Lo values
Flanged beam
Design the main reinforcement.
use = 0.98d
CONTINUOUS BEAM EXAMPLE 3.2
Calculate d’
CONTINUOUS BEAM EXAMPLE 3.2
Flanged beam
Design the main reinforcement.
Calculate VRd,c
= 43.24 kN
VRd.c = 81.26 kN
Calculate VRd,max
@ 22,
CONTINUOUS BEAM EXAMPLE 3.2
> o
From table 7.4N, K = 1.3 (end span of continuous beam) – where the moment is
maximum
CONTINUOUS BEAM EXAMPLE 3.2
a) Calculate (L/d)actual
5H20
mm2
S1 S1
Taking wk = 0.3 mm
OK!