RPA Calculator v.3.0
RPA Calculator v.3.0
12/24/2023
for
Process name: Create Sales Order GM t choose process from the list
Deployment complexity
0 2 4 6 8 10 12 14 16 18 20
weeks
Estimated implementation
Transaction volume Estimated FTE savings
[weeks]
20 1.0 10
Process suitability
69%
Development,
Business
Processes name Complexity testing &
analysis
deployment
Cylinder Error Log COMPLEX 2 14
Total 5 39
Role model
Role Grade
Lead Architect C1
Business Analyst B2
Developer B1
Infra Specialist B2
Expert pool D1
for
Total
implementation
effort
16
23
44
Contingency [%]
(time buffer)
10%
203
28
265
27
40
28
591
Multiple process comparision
up to 15 opportunities for
Processes comparision
2.00
Cylinder Error Log
(P2P)
FTE benefit
1.50
Upload Delivery Slips
(O2C)
1.00
Create Sales Order
GM (O2C)
0.50
TQ Account Statement
(HR)
Not suitable
0.00
2 4 6 8 10 12 14 16 18 20
UiPath Implementation assessment calculator
Below assement is used in order to calculate approximate effort required to deliver RPA automation. Given times are refering to Business Analyst for
and Developer effort needed to complete Analyze 2 Deploy phase. Please note that hypercare period, as well as effort for core project roles (Lead
Architects, Peer Reviewer, Expert poll) is not included. For that purpose please use tab "Project Roles"
Number of Number of Number of Number of Number of Number of Number of Number of Number of Number of Number of Number of Number of Number of Number of
Major applications or Non structured or
screens
based on complex, Data must be
1 O2C Upload Delivery Slips Daily 200 1.5 Yes COMPLEX 287 401 9 2 2 13 NO Business process flow Highly manual process Multi Source Based Scanned text or Yes 2 2 2 6
conditional rules- converted/translated
changes Image
based logic
Standard applications
Transactional Process already including Not required or Only
screens
update, no business Not Required or Structured Electronic
2 O2C Create Sales Order GM Weekly 20 1 No MEDIUM 206 288 6 2 2 10 YES repetitive processing multiple scripting No data format changes 1 22 2 25
process changes Single Format Based text
using simple rules solutions required
planned
Applications under Transactional
Partially structured, Data must be
screens
development or processing based on Partially automated
3 P2P Cylinder Error Log Daily 40 2 No COMPLEX 384 537 12 2 2 16 NO Multi Source Based standard format - Partially extracted, converted 1 20 2 23
Business process being simple rules-based process
Electronic text and translated
defined logic
Standard applications
Transactional
screens
update, no business Structured Electronic Data must be
4 HR TQ Account Statement Monthly 10 0.5 No SIMPLE 82 114 3 1 1 5 YES repetitive processing Highly manual process Multi Source Based Yes 1 2 2 2 7
process changes text converted/translated
using simple rules
planned
Standard applications Processing activity
Non structured or Not required or Only
screens
update, no business based on complex, Not Required or
5 O2C Collection Tracking Daily 100 1.5 Yes COMPLEX 613 858 19 2 2 23 NO Highly manual process Scanned text or Yes data format changes 2 30 25 15 72
process changes conditional rules- Single Format Based
Image required
planned based logic
screens
6 1 1
screens
7 1 1
screens
8 1 1
screens
9 1 1
screens
10 1 1
screens
11 1 1
screens
12 1 1
screens
13 1 1
screens
14 1 1
screens
15 1 1
Project Role Model
for
Process name: Create Sales Order GM t choose process from the list
Area: O2C
Complexity MEDIUM
2 8 10
Contingency [%]
Hypercare
Hypercare[weeks] Contingency
[weeks] (time buffer) [%]
Role model
Lead Architect C1 26
Business Analyst B2 13
Developer B1 72
Infra Specialist B2 16
Senior Dev / QA / Code
control
C1 11
Expert pool D1 6
144
FTE Calculator
Working Days per Month 20
Working Hours per day 18.0
50% 0.185
100% 0.833
70% 0.324
30% 0.319