CMT Program - CMT PLUG - 4240 M

The cementing program proposes cementing operations on well AZNS-175 to set a cement plug at 4240 meters measured depth. Dry blend cement with silica flour will be used to cement inside the 7-inch liner. A 118 pounds per cubic foot cement slurry will be pumped from 4240 to 4179 meters to set the cement plug. Safety policies and procedures will be reviewed before operations begin.

Uploaded by

abbas ansari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views11 pages

CMT Program - CMT PLUG - 4240 M

The cementing program proposes cementing operations on well AZNS-175 to set a cement plug at 4240 meters measured depth. Dry blend cement with silica flour will be used to cement inside the 7-inch liner. A 118 pounds per cubic foot cement slurry will be pumped from 4240 to 4179 meters to set the cement plug. Safety policies and procedures will be reviewed before operations begin.

Uploaded by

abbas ansari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Cementing Program

Client: NIDC-Project
Field: S.Azadegan
Well Location: S.Azadegan
Well Name: AZNS-175
Rig Name: 43 FATH

Date: 12/16/2023
Type of Job: Cement Plug
Cementing Method: Remedial Cementing
Proposal Number: 1
Contract Number: 99-982
Made By: NIDC Cement Engineering and
Planning Department

District Phone Number: 061-341-43513

NOTICE:
THE CEMENT PROGRAM WILL BE CHANGED ACCORDING TO NEW WEL
CONDITION SUCH AS DEPTH AND TEMPERATURE.
THE VOLUME OF DISPLACEMENT SHOULD BE CALCULATED IN RIG SITE BY
COMPANY MAN AND TO ALL THE EXECUTIVE GROUPS TO BE ANNOUNCED.

Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

Executive Summary
Enclosed are our recommendations for NIDC Cement Engineering and Planning Department
intervention on the referenced well. The proposal includes well data, materials and resources
requirements.

NIDC has established a safety policy to which all NIDC personnel must adhere. A pre-job safety
meeting will be held with client representatives and other on location personnel to familiarize
everyone with existing hazards and safety procedures. We would appreciate close cooperation
between the client representative and the NIDC representative to ensure a safe operation.

Cement plug will be set at 4240.0 m MD. Dry blend cement with silica flour designed will be
used to cement inside 7" liner; 118 pcf main cement slurry will be cemented from 4240.0 m to 4179.0
m .The calculated cement main slurry volume is based on client request gives 7.0 bbl.

2 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

Contents

Executive Summary ........................................................................................................ 2


I. Document Control ........................................................................................................ 4
II. Well Data Summary..................................................................................................... 5
III. Geothermal Temperature Profile ................................................................................ 6
IV. Fluids Sequence ........................................................................................................ 6
V. Cementing Program .................................................................................................... 7
VI. Spacer Program ......................................................................................................... 7
VII. Laboratory Report ..................................................................................................... 8
VIII. Vertical Well Survey Data ........................................................................................ 9
IX. Cementing Procedure .............................................................................................. 10
X. Attachment ................................................................................................................ 10

3 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

I. Document Control
Document Name and Version:

Once approved by NIDC Cement Engineering and Planning Department and the Client, any
deviation from this program requires document agreement.

Request Information
Date Received Request Number Description Client
12/14/2023 3170804(CPR4) Cement Plug NIDC-Project

Approvals
Cell Phone
Description Name Signature Date
Number

Prepared by M.Soroushmehr 12/16/2023 +98-916-621-1247

Confirmed by Sh.Jalili 12/16/2023 +98-917-142-1265

Approved by M.Beiranvand 12/16/2023 +98-916-617-2019

Revision History
Date Version Description Author
12/16/2023 0 Cement Plug M.Soroushmehr

4 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

II. Well Data Summary


The cementing program incorporates the following data:

Tubular and Casing Hardware


MD Size ID Joint Weight Grade Collapse Burst
Description
m in in m lb/ft - psi psi
Previous Casing 155.0 20" 18.730 12.2 133.0 - - -
Previous Casing 2030.0 13 3/8" 12.415 12.2 68.0 - - -
Previous Casing 4050.0 9 5/8" 8.681 12.2 47.0 - - -
Liner 4468.0 7" 6.184 12.2 29.0 - - -
C.T 4240.0 - - - - - - -
Open hole - - - - - - - -
Drilling Fluid Data
Mud Type WBM Mud Weight 103 pcf
Plastic Viscosity(cp) 60 cp Yield Point(lb/100ft^2) 16 lb/100ft^2

Depth(m) Well Schematic Casing Size/Depth(m)

0
20" CSG @ 155.0 M

13 3/8" CSG @ 2030.0 M

9 5/8" CSG @ 4050.0 M

CMT PLUG @ 4240.0-4179.0 M

7" LNR @ 4468.0 M


4600

5 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

III. Geothermal Temperature Profile


Temperature
MD (m) TVD (m) BHST (degF) Gradient (degF/100ft)
4240.0 4240.0 268 1.35

m degF
m
0 0.5 1.0 0 100 200 300
0

Hori. Depart. Geoth.Prof ile


1000
2000
TVD (m)
2500.0

3000
4000
5000.0

5000

Hori. Depa rtur e Temperature

NOTE 1: The Calculated Temperature is based on True Vertical Depth.

IV. Fluids Sequence

Fluids
Cumulated
Density Volume Pump Rate Duration
Type Name Time
(lb/ft3) (bbl) (bbl/min) (hr:mn)
(hr:mn)
Spacer Ahead Salt Saturated Water 75 5.0 0.8-1.2 00:05 00:05

Main Slurry Cement Slurry 118 7.0 0.8-1.2 00:07 00:12

Spacer Behind Salt Saturated Water 75 1.0 0.8-1.2 00:01 00:13

Displacement Fluid Mud 103 26.0* 0.8-1.2 00:26 00:39

NOTE 2: Densities are Displayed at P=1 atmosphere and T=70 degF.

NOTE 3: Max Pumping Time for Slurry & Displacement with Safety Factor is 120 min.

NOTE 4: The Volume of Displacement Should Be Calculated at Rig Site

6 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

V. Cementing Program
Main Cement Slurry Data
Volume 7.0 bbl Slurry Weight 118 pcf
Bottom 4240.0 m Top 4179.0 m
Yield 1.795 cuft/sk Solution 3.9 bbl

Main Cement Slurry Blend Data


Item Name Material Type sks or lbs lbs / sk
1 G Delijan Cement 21.9 sk 110.0
2 Silica Flour CS Stabilizer 843.1 lb 38.5

Main Cement Slurry Additives Data


lbs or gal
Item Name Material Type lbs or gal (lbs or gal)/sk (lbs or gal)/bbl
(with dead Vol.)
1 O-UniFLC5 Fluid Loss Contoller 14.5 0.660 3.716 18.6
2 JP-450 Dispersant 1.2 0.055 0.307 1.5
3 O-R12 H.T Retarder 2.4 0.110 0.614 3.1
4 Defoamer Anti Foam 0.2 gal 0.01 gal/sk 0.052 gal/bbl 0.3 gal

NOTE 5: Mix above Additives in 5.0 bbl Fresh Water at Pump Truck Tanks.

VI. Spacer Program


Spacer Data
Volume 5.0 bbl Weight 75 pcf
Item Name Material Type lbs or gal or bbl (lbs or gal)/ bbl
1 Fresh Water Water 6.0 bbl -
2 Salt NaCl 726.0 lb 121.0

7 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

VII. Laboratory Report


Main Cement Slurry Results

Test Basic Data


BHST 268 degF Mud Density 103 pcf
BHCT 213 degF Slurry Density 118 pcf
Yield 1.795 ft3/sk BHSP 9950 psi
Mix Fluid 7.571 gal/sk Base Fluid 7.488 gal/sk
Solution Density 62.4 pcf

Conventional
Material Type Code Lot Number Concentration Design Unit Mass (g/600 mL)
Cement G Delijan 1400-082 100.0% BWOB 589.0
Silica Flour CS Stabilizer JP 35.0% BWOC 206.0
795.0

Additives
Material Type Code Lot Number Concentration Design Unit Mass (g/600 mL)
Fluid Loss Controller O-UniFLC5 1422 0.60 % BWOC 3.53
Dispersant JP-450 99122 0.05 % BWOC 0.29
H.T Retarder O-R12 1413 0.10 % BWOC 0.59
Anti Foam Defoamer QCO20431A38 0.01 gal/sk VBWOC 0.44
Water Fresh Water Lab Sample 1.0 BWOW 334.0
338.9
NOTE 6: Fresh water means calcium in the 400 ppm range and salt in the 3000 ppm range.

Rheology Test
Temperature Tstart: Surface Tstart: degF Tstart: 213 degF
Ramp-Down Ramp-Up Ramp-Down
RPM
(deg) (deg) (deg)
300 - - 118
200 - - 72
100 - - 54
60 - - 31
30 - - 20
6 - - 7
3 - - 5
Pv (cP) - - 106.650
Ty (lbf/100ft2) - - 09.74
10 Sec Gel (deg) - - 7
10 Min Gel (deg) - - 16

NOTE 7: The Result of Rheology Test is based on Bingham Model.

8 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

Free Water Test Fluid Loss Test


Test Temperature 70 degF Test Temperature 213 degF
Collected (90° angle) 0.0 ml in 250 ml @ 2hr Test Pressure 1000 psi
Collected (45° angle) - Collected @ 30 Min 40.0 ml
Settling - API Fluid Loss 80.0

Thickening Time Test


Condition Test Start Enter Time
Temp Pressure Initial Temp Initial 30 BC 50 BC 70 BC
Time Cell
(degF) (psi) (degF) Pressure hr:mm hr:mm hr:mm
213 9950+1000 70 Surface 09:30 1 02:59 03:05 03:09
NOTE 8: Surface Sample After 13 hr Observe Hard.

Compressive Strength Test


Temp - CRUSH Temp 268 degF
UCA Condition Condition
Pressure - TEST Pressure Surface
Time
09:00 12:00 24:00 Force (lbf) 12355 12510 12600 12870
(hr:mm)
Area
CS (psi) - - - 4 4 4 4
(in^2)
24 hour Elapsed Time & Total Compressive Strength is 3146 psi (Water Bath)

VIII. Vertical Well Survey Data


Directional Survey Data
MD TVD Deviation Azimuth Dogleg Sev.
(m) (m) (deg) (deg) (deg/m)
0 0 0 0 0
4240.0 4240.0 0 0 0
NOTE 9: The Well is Considered Vertical.

9 of 10
Code: AP-F-01-02/00
Engineering Affair
Drilling Engineering Department

IX. Cementing Procedure


1. Clean up pump truck tanks and preparing chemicals for mixing fluid.
2. Fill up pump truck tanks with 5.0 bbl Fresh Water for mixing fluid.
3. Before start running Coiled tubing, starts mixing cement additives and preparing mixing fluids
according to below cement mixing procedure.
Main Cement Solution mixing procedure:
Add Defoamer to Fresh water and allow mixing for 5 minutes.
Add O-UNIFLC5 and allow mixing for 10 min.
Add JP-450 and allow mixing for 10 min.
Add O-R12 and allow mixing until the cement operation will finish.
4. After running coiled tubing to 4240.0 m, start circulation at least one pipe cap volume.
5. Pre job safety meeting with involved Personal.
6. Test cement line W/4000 psi
7. Pump 5.0 bbl Salt saturated water as spacer ahead.
8. Mix and pump 7.0 bbl Main cement slurry. (118 pcf)
9. Pump …. bbl Salt saturated water as spacer behind.( calculate at well site)
10. Displace cement with … bbl drilling fluid. (calculate at well site)
11. POOH coiled tubing to … m. (At least 30 m above top of cement).
12. Start Circulation at optimum rate.
13. POOH coiled tubing to surface.
14. Close the well and wait on cement to get hard.

Note: Coiled Tubing volume calculation and back pressure operation should be done by Coiled
tubing operation supervisor before the cement job.

X. Attachment

10 of 10