1.0 SCOPE:
As per the Electrical Transformer (Quality Control) Order, 2014, it is mandatory
that No Electrical Transformers shall be manufacture or store for sale, sell or
distribute which do not confirm to the specified standard and do not bear standard
Mark of the Bureau. Moreover, as per the Guidelines of Bureau of Energy
Efficiency (BEE), labeling of distribution transformer is mandatory & cannot be sold
in the market without star label. Accordingly, the bidder shall have to submit valid
BIS license of the quoted item or higher as per approved scheme of BIS and star
rating certificate from BEE for 16 KVA to 500 KVA Transformers.
2.0 STANDARDS:
2.1 The materials shall conform in all respects to the relevant Indian /
International Standard Specification, with latest amendments thereof, some
of them are listed below:
Indian Standard Title International &
Internationally
recognized
standard
ISS – 1180 / Part-I/ 2014 Outdoor/Indoor type Oil immersed
with latest amendments distribution Transformer upto and including
2500 kVA, 33KV Specifications Mineral Oil
Immersed
ISS - 16585:2016 Magnetic materials - specifications for individual
materials - Fe based amorphous strip delivered in
the semi processed state
5484 Specifications for Aluminum wire rods ASTM B-233
649 Testing of Steel sheet and strips for magnetic
circuits
191: 2007 Copper
335 : 1993 New insulating oils BS 148, D-1473,
D-1533- 1934
IEC Pub 296-
1969
554 : 1999 Pipe threads where pressure-tight joints are
made on the threads — Dimensions,
tolerances and designation
1576 : 1992 Solid pressboard for electrical purpose IEC 641
1608 : 2005 Mechanical testing of metals — Tensile
testing
1747 : 1972 Nitrogen
1885 (Part 38) :1993 Electro technical vocabulary: Part 38 Power
transformers and reactors
1897 : 2008 Copper strip for electrical purpose
2026 Power transformers : IEC 76
(Part 1) : 2011 General
(Part 2) : 2010 Temperature rise
(Part 3) : 2009 Insulation levels, dielectric tests and external
Signature of Tenderer Company’s Round Seal Date Place
Page 2 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
6. Line current LV 20.0 A 13.3 A 21.33 A 33.33 A 84.0 A 133.0 A 266.0 A 665.0 A
7. Frequency 50 c/s +/- 50 c/s +/- 50 c/s +/- 50 c/s +/- 50 c/s +/- 50 c/s +/- 50 c/s +/- 50 c/s +/-
5% 5% 5% 5% 5% 5% 5% 5%
8. No. of Phases Single Three Three Three Three Three Three Three
10. Connection LV Individual Star Star Star Star Star Star Star
(Neutral (Neutral (Neutral (Neutral (Neutral (Neutral (Neutral
brought brought brought brought brought brought brought
out) out) out) out) out) out) out)
11. Vector group -- Dyn-11 Dyn-11 Dyn-11 Dyn-11 Dyn-11 Dyn-11 Dyn-11
12. Type of cooling ONAN ONAN ONAN ONAN ONAN ONAN ONAN ONAN
out.
8. Clamping and Tie-rods shall be made from HT Bright Bars steel & shall
be painted with hot oil resistant paint.(IS 1180 table 12)
B. AMORPHOUS :
i. The core shall be high quality Amorphous ribbons having very low loss
formed into wound cores of rectangular shape, bolted together to the
frames firmly to prevent vibration or noise. The complete design of core
must ensure permanency of the core loss with continuous working of the
transformers. The value of the flux density allowed in the design shall be
clearly stated in the offer. Curve showing the properties of the metal shall
be attached with the offer.
be ensured.
(b)Inter layer insulation shall be Epoxy dotted Kraft Paper.
Test for bonding strength shall be conducted.
5. Internal Clearances& Number of HV/LV coils :
5.2.1 TAPS:
correspond to the maximum plus tapping. Each tap change shall result in
variation of 2.5% in voltage. Provision shall be made for locking the taping
switch handle in position. Suitable aluminum anodized plate shall be fixed
for tap changing switch to know the position number of tap.
5.2.2 OIL :
The insulating oil shall comply with the requirements of IS 335. Use of recycled
oil is not acceptable. The specific resistance of the oil shall not be less than 35
X1012 ohm-cm at 27⁰C when tested as per IS 6103.
Oil shall be filtered and tested for break down voltage (BDV) and moisture
content before filling.
The oil shall be filled under vacuum of 250 Tor +/- 5 %.
The design and all materials and processes used in the manufacture of the
transformer, shall be such as to reduce to a minimum the risk of the
development of acidity in the oil.
Losses of the Transformer should not exceed following values and for transformers having
tapings shall be guaranteed at maximum current tap and it should not exceed following
values.
LOSSES of LABELLED TRANSFORMERS IN WATTS
*Total Losses in watt at 100 % loading = No Load losses in watt + Full Load losses in watt at
75 Deg. C
Bids with higher losses than above specified values would be treated as non responsive.
While in case of tapped transformer, Bids with higher losses than above specified values at
maximum current tap, would be treated as non responsive.
However, the manufacturer can offer losses lower than above.
NOTE: -
Offer without BIS and BEE certification will be out rightly rejected without any
correspondence.
Bids not meeting the above limits of temperature rise will be treated as non-
responsive.
5.6 PENALTY FOR NON PERFORMANCE:
A. During testing, if it is found that the actual measured losses are more than
the values quoted by the bidder, the purchaser will have right to exercise
Signature of Tenderer Company’s Round Seal Date Place
Page 14 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
C. TESTS AT SITE:
The purchaser reserves the right to conduct all tests on Transformer after
arrival at site and the manufacturer shall guarantee test certificate figures
under actual service conditions.
In order to ensure quality the acceptance test shall be carried out even
after installation of transformer within grantee period. If acceptance test
standards are not met during such field test, 5% penalty may be imposed
on all transformers supplied as per that proto type design.
5.7 TANK :
Transformer tank construction shall conform in all respect to clause 15 of IS
1180(Part-1):2014.The transformer tank can be with radiator fins/ rounded
or elliptical cooling tubes or made of corrugated panels.
A. FOR RECTANGULAR PLAIN TANK:
i. The transformer tank shall be of robust construction rectangular in shape
and shall be built up of tested MS sheets.
The tank shall be made of prime quality MS sheet of thickness stated below
with necessary stiffener to withstand the pressure built in during the
expansion of oil due to temperature rise.
The exterior of the transformer tank and other ferrous fitting shall be
thoroughly cleaned , scraped /sand blasted and given a priming coat and
Signature of Tenderer Company’s Round Seal Date Place
Page 15 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
two finishing coats of durable oil and weather resistant paint of dark
admiral grey conforming to color code No. 632 of IS-5/1961.
The internal clearance of tank shall be such that, it shall facilitate easy lifting
of core with coils from the tank without dismantling LV bushings.
ii. All joints of tank and fittings shall be oil tight and no bulging should occur
during service. The tank design shall be such that the core and windings
can be lifted freely. The tank plate shall be of such strength that the
complete transformers when filled with oil may be lifted bodily by means of
lifting lugs. Inside of tank shall be painted with Hot oil resistive paint.
iii. Manufacturer should carry out all welding operations as per the relevant
ASME standards and submit a copy of the welding procedure qualifications
and welder performance qualification certificates to the customer.
iv. Up to 200 KVA Transformers, the four walls of the rectangular tank shall be
made of Two “L” shaped sheets (without joints) fully welded at the corners
from inside and outside of the tank for withstanding a pressure of 80 kPa
for 30 minutes and vacuum of 250 mm of mercury for 30 Min.
(OR)
One “U” shaped bend sheet with straight plate and welded outside the tank
at 2 corners for withstanding a pressure of 80 kPa for 30 minutes”. While
500 KVA Transformer withstanding a pressure of 80 kPa for 30 minutes and
vacuum of 500 mm of mercury for 30 Min. There should be no air leakage
at any point.
Under operating conditions the pressure generated inside the tank should
not exceed 0.4 kg/ sq. cm positive or negative. There must be sufficient
space from the core to the top cover to take care of oil expansion. The
space above oil level in the tank shall be filled with dry air or nitrogen
conforming to commercial grade of IS 1747.
v. Up to 500 KVA Transformers, the permanent deflection of flat plates, after
pressure/ vacuum has been released, shall not exceed 5 mm up to 750 mm
length and 6.5 mm up to 1250 mm length.
vi. For single phase transformers, minimum Oil level mark shall be embossed
inside the tank (at 250 C).
vii. The Single Phase transformer shall be provided with two mounting lugs
suitable for fixing the transformer to a single pole by means of 2 bolts of 20
mm diameter as per ANSI C 57.12.20-1988. The circular bottom plate edges
of the tank should be folded upward, for at least 25 mm, to have sufficient
overlap with vertical sidewall of the transformer.
viii. TANK SEALING for Single Phase:
The space on the top of the oil shall be filled with dry air or nitrogen. The
nitrogen plus oil volume inside the tank shall be such that even under
extreme operating conditions, the pressure generated inside the tank does
not exceed 0.4 kg/sq. cm positive or negative. The nitrogen shall conform to
commercial grade of the relevant standards.
ix. For single phase transformers, round tank shall withstand pressure of 100
Signature of Tenderer Company’s Round Seal Date Place
Page 16 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
The Bidder may offer Elliptical tanks for 10 &16 KVA transformers, robust in
construction with adequate strength to withstand the pressure built in
during the expansion of oil due to temperature rise. The tank sheet shall be
electrically welded to impart proper mechanical strength and to plug
leakage of oil. All joints of tank and fittings shall be oil tight and no bulging
shall occur during service. The tank sheets shall be of such strength that the
complete transformer when filled with oil may be lifted by means of lifting
lugs provided. All the welding shall be continuous.
The elliptical tank constructed by two welding joints only, one is at bottom
cover and another is at the tank shell so that the leakages due to joints can
be reduced. The tank shall withstand a pressure of 80 kPa for 30 minutes and
vacuum of 250 mm of mercury for 30 Min and the permanent deflection
after pressure/ vacuum has been released, shall not exceed 5 mm.
The inside diameter of the pipe connecting the conservator to the main tank
should be within 30 to 50 mm and it should be projected into the
conservator so that its end is approximately 20 mm above the bottom of the
conservator so as to create a sump for collection of impurities. The
minimum oil level (corresponding to -5 deg C) should be above the sump
level.
E. DEHYDRATING BREATHER:
Breather shall be screwed type. It shall have die cast aluminum body &
further, inside container for silica gel shall be of tin sheet. Inverted U-shape
pipe shall be used for connection of breather. The dehydrating agent shall be
silica gel. The moisture absorption shall be indicated by a change in the
colour of the silica gel crystals which should be easily visible from a distance.
Volume of breather shall be suitable for 500g of silica gel conforming to IS
3401 for transformers upto 200 kVA and 1 kg for transformers above 200
kVA. The make and design of breather shall be subject to approval of
DISCOM, Gujarat.
Breather: Individual Breather shall be packed in a cotton bag shall be bound
with individual transformer in a clear visible position.
ii. Steel surfaces shall be prepared by shot blast cleaning (IS9954) to grade Sq.
2.5 of ISO 8501-1 or chemical cleaning by Seven Tank process including
phosphating of the appropriate quality (IS 3618).
iii. The pressure and volume of the compressed air supply for blast cleaning
shall meet the work requirements and shall be sufficiently free from all water
contamination to ensure that the cleaning process is not impaired.
iv. Chipping, scraping and steel wire brushing using manual or power driven
tools cannot remove firmly adherent mill-scale shall only be used where blast
cleaning is impractical. Manufacturer to explain such areas in his technical
offer clearly.
C. PROTECTIVE COATING
As soon as all items have been cleaned and within four hours of the
subsequent drying, they shall be given suitable anti-corrosion protection.
D. PAINT MATERIAL:
i. The color of the finishing coats shall be dark admiral gray conforming to No.
632 of IS-5 of 1961.
ii. Inside of tank shall be painted with oil resistance paint of colour shade
yellow/green. For external surfaces, one coat of thermosetting powder paint
shall be used.
iii. For highly polluted areas, chemical atmosphere or for places very near to the
sea coast, paint as above with one coat of high build Micaceous iron oxide
(MIO) as an intermediate coat may be used.
iv. To the maximum extent practicable the coat shall be applied as a continuous
film of uniform thickness and free of pores. Overspray, skips, runs, sags and
drips should be avoided. Each coat of paint shall be allowed to harden
before the next is applied.
v. Particular attention must be paid to full film thickness at edges.
vi. The requirements for the dry film thickness (DFT) of paint and the materials
to be used shall be as given below.
Sr. Paint Type Area to No. of Total Dry film
No be coats thickness (min.) in
painted microns
1. Thermo setting powder paint Outside 01 60
OR Liquid paint
a) Epoxy (Primer)
b) Polyurethane(finished coat)
2. Thermo setting powder paint Inside 01 30
OR
Liquid paint
Hot oil resistant paint of Inside 01 35
colour shade yellow/green
E. PAINTING PROCEDURE:
i. All painting shall be carried out in conformity with both Specification and
with the paint manufacturer’s recommendation. All paints in any one
particular system, whether shop or site applied, shall originate from one
paint manufacturer.
ii. Particular attention shall be paid to the manufacturer’s instructions on
storage, mixing, thinning and pot life. The paint shall only be applied in the
manner detailed by the manufacturer e.g. brush, roller, conventional or
airless spray and shall be applied under the manufacturer’s recommended
condition.
iii. All prepared steel surfaces should be primed before visible re-rusting occurs
or within 4 hours, whichever is sooner. Chemical treated steel surfaces shall
be primed as soon as the surface is dry and while the surface is still warm.
iv. Where the quality of film is impaired by excess film thickness (wrinkling, mud
cracking or general softness) the Supplier shall remove the unsatisfactory
paint coating and apply another. As a general rule, dry film thickness should
not exceed the specified minimum dry film thickens by more than 25%.
v. Paint applied to items that are not be painted shall be removed at Supplier’s
expense, leaving the surface clean, unstained and undamaged.
F. DAMAGED PAINTWORK:
i. Any damage occurring to painting of any part shall be made good to the
same standard of corrosion protection and appearance as that originally
employed, within guarantee/ warrantee period at free of cost.
ii. Any damaged paint work shall be made good as follows:
a) The damaged area, together with an area extending 25 mm around its
boundary, shall be cleaned down to bare metal.
b) A priming coat shall be immediately applied, followed by a full paint
finish equal to that originally applied and extending 50 mm around the
perimeter of the original damage.
c) The repainted surface shall present a smooth surface. This shall be
obtained by carefully chamfering the paint edges before and after
priming.
G. TESTSFOR PAINTED SURFACE:
i. The painted surface shall be tested for paint thickness.
ii. The painted surface shall pass the cross hatch adhesion test and impact test
as acceptance tests and Salt spray test and Hardness test as type test as per
the relevant ASTM standards.
For 11 KV Transformers – 17.5 KV class bushings shall be used and further for
LV side, viz. 250/433 volts, 1KV terminal bushing shall be used. Bushing of the
same voltage class shall be interchangeable bushing with plain shed as per IS
3347. Bushings shall be mounted on top plate only.
OR
HT bushing should be kept in such a way that minimum air clearances should
be maintained by tilting the same.
Suitable insulating shrouds shall be provided on the HT bushing terminals.
The HV bushings shall have to be installed on top plate on turret, flange and
gaskets to prevent eventual entry of water. The turret height for HV bushing
should be minimum 25 to 30mm. In LV side bushing, turret of minimum 10
mm should be provided.
Dimensions of the bushings of the voltage class shall conform to the Standards
specified and dimension of clamping arrangement shall be as per IS 4257.
Bushing can be of porcelain material.
The cross section of the connecting rods on LV side shall be as per IS 3347
Part1/Sec 2 1979and shall be adequate for carrying the rated currents. On the
HV side the terminal rod shall have a diameter of not less than 12 mm of brass
up to 200 KVA as per IS 3347 Part3/Sec 2 1982and above200 KVA shall be of
Copper.
Note : For 5 KVA Single Phase & 10 KVA, 16 KVA and 25 KVA, Three Phase
transformer having provision of MCCB, hence LV Bimetallic clamps are not
required.
HV AND LV TERMINALS:
The LV and HV bushing stems shall be provided with suitable terminal
connectors as per IS 5082 so as to connect the jumper without disturbing the
bushing stem. Terminal connectors shall be type tested as per IS 5561.
Signature of Tenderer Company’s Round Seal Date Place
Page 22 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
B. INTERNAL CONNECTION:
1. HV WINDING:
i. In case of HV winding all jumpers from winding to bushing shall have cross
section double the winding conductor.
ii. Inter coil connection shall be done by brazing as per ASME, section-IX.
iii. In case of AL/CU winding Delta joint shall be with brazing only.
iv. Lead from Delta joint shall be connected to bushing rod by brazing only.
v. Current density in any of the conductor (in Delta connections also) shall
not exceed 1 Amp/sq.mm and 2Amp/sq.mm for aluminum conductor and
copper conductor respectively.
2. LV WINDING:
LV star point shall be formed of AL/CU flat of sufficient size and length. Lead
from winding shall be connected to the flat by brazing.
Firm connection of LV winding to bushing shall be made of adequate size of
“L” shape flat. Connection of LV coil lead to “L” shape flat shall be made by
brazing. The "L" Shape flat shall be of copper for copper winding &
Aluminum of Aluminum winding. “L” shape flat/lug shall be clamped to LV
bushing metal part by using nut, locknut and washer.
The transformers shall be suitable for loading as per IS: 6600 / 1972with
latest amendment if any.
The under base of all transformers shall be provided with holes to make them
suitable for fixing on a platform or plinth.
p. Non return valve (NRV) -1 No (mandatory for sealed transformer with inert
gas, otherwise optional).
q. Anti-theft stainless steel fasteners with breakaway nut at Top Cover – 4 Nos.
for 3 Phase and 2 nos. for 1 Phase
r. Oil filter valve (1.25 Inch, nominal size thread) -1 No. at top of tank for 500 KVA
s. Drain-cum-sampling metallic valve with plug(1.25 Inch, nominal size thread) -
1no.for 200 KVA & above transformer at bottom of tank with anti theft
protection cover
t. Off circuit tap changer switch with handle and locking device for 200 KVA &
500 KVA Transformers – 1 No
u. LV Cable holding clamp with accessories for 63 KVA and above.
v. LV earthing arrangement for single phase transformers (LV neutral terminal to
be brought out for earthing)
w. Inspection hole for 500 KVA
x. Prismatic Oil level gauge indicating the position of oil marked with background
of yellow color) as follows.
Min. ( -5 deg.C), 30 deg. C, Max. 90 deg.C
NOTES:
1. Minimum and maximum positions correspond to the operating
temperature of–5°C and 90°C respectively (for non-sealed type
transformer).
2. Only Minimum position corresponds to the operating temperature
of 30°C (for sealed type transformers).
5.13 OVER LOAD PROTECTION:
5.13.1 The transformer shall have external mounted LT circuit breaker on the
secondary side up to 25 KVA capacity of transformer. The breaker shall be
housed in an enclosure confirming to IP44 as per IS: 13947 forming integral
part of the transformer. Suitable louvers fitted with wire gauze shall be
provided to ensure circulation of air but not to allow ingress of rain water. An
operating handle shall be provided outside the enclosure in such a way that
ON & OFF operation of the breaker can be conveniently performed from the
ground level by means of an operating rod. The ON & OFF position of the
handle shall be clearly and bodily mark on the enclosure.
5.13.2 The breaker box shall be mounted on side wall (short side) of the tank
opposite side of the name plate for comfortable wiring at site.
5.13.3 The manufacturer will provide 1.1KV; Stranded PVC insulated armored
Aluminum cable from Transformer terminal to Incoming of MCCB having
below mentioned cable size and the purchaser will connect LT cable to the
outgoing terminals of MCCB after installation of the transformer at site.
Detachable gland plate with bellow mentioned sized cable shrinkable PVC
gland to be provided at the bottom of the enclosure.
Signature of Tenderer Company’s Round Seal Date Place
Page 25 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
5.13.4 The circuit breaker shall generally confirm to the requirement of IS: 13947.
The electrical characteristics of the breaker shall be mentioned by bidder as
follows.
Transformer Full load LV current of Transformer terminal to Breaker cable
rating (KVA) the transformer (Amp) size (minimum)-Alum.
5 16.2 2.5 mm²
10 13.33 4 mm²
16 21.33 6 mm²
25 33.33 10 mm²
The circuit breaker shall confirmed to IS: 13947 part-II and certificate from
government approved laboratory for short circuit test at a power factor
not exceeding 0.4 (lagging) shall be submitted with the offer.
5.13.5 MCCB Make mentioned in Schedule A or other makes having type tested as
per relevant IS and approved by the GUVNL/PGVCL/MGVCL /DGVCL /UGVCL
shall only be used & are acceptable. Bidder shall have to mention the make of
MCCB to be provided with the offer. The bidder shall also submit the type test
certificate. However any other make of MCCB having valid BIS Certificate of ISI
mark shall be acceptable only at the discretion of the Purchaser. The decision
of Purchaser shall be final & binding in this regard. For other make of MCCB,
Bidder shall also have to submit certificate of satisfactory operation from
other two Utilities.
The successful bidder shall be required to furnish the guarantee certificate of
05 (five) year obtained from the MCCB manufacture on Rs. 100/- non-judicial
stamp paper.
5.13.6 The circuit breaker shall have the following time v/s current characteristics
and same shall be tested with all the 3 Ph. Loaded. The reference calibration
temperature of the breaker shall be 50 degree centigrade. The test certificate
for the same of NABL accredited laboratory shall be produced with bid as well
as at the time of inspection.
Multiple of normal Tripping time
current setting
The above drawings/ details are illustrative. However, the bidder may
submit their own drawing/ details if they so desires. Offer without
drawings/ details shall not be considered.
The proto type shall be subjected to following test conforming to IS 1180 Part-
1 2014 & IS 2026 and all relevant IS with latest amendments.
1) Verification of core laminations material documents and quality.
2) Verification of internal parameters with respect to approved
drawings and GTP.
3) All Routine tests/ acceptance test as per clause 6
4) Temperature rise test as per clause no.6
5) Verification of Air pressure and vacuum test certificate from
manufacturer of tank.
On completion of proto type sample inspection and scrutinizing the reports,
approval will be accorded by the respective DISCOM. On getting approval
from respective DISCOM, bulk production shall be commenced by the
supplier.
If any observation/ deviation found during proto inspection, supplier shall
have to re-offer proto inspection with rectification/ new sample. However,
inspection charges for un-successful proto sample will be borne by the
supplier.
6.0 TESTS:
a. All the equipment offered shall be fully type tested by the bidder or his
collaborator as per the relevant standards including the additional type
tests mentioned at clause 6.2. The type test must have been conducted on
a transformer of same design. The Bidder shall furnish four sets of type
test reports along with the offer. All the required Type test reports for the
tendered items as under should invariably furnish a Notarized Copy. Offers
without type test reports will be treated as Non-responsive.
1. Temperature rise test for determining the maximum
temperature rise after continuous full load run.
2. Lightening Impulse voltage test: As per Clause No. 13 (With
chopped wave) of IS – 2026- part-III latest version. BIL for 11
kV shall be minimum 95 KV Peak.
3. Vacuum Test: As per IS - 1180 / part-I/2014
4. Air Pressure Test: As per IS - 1180 / part-
I/2014ORTransformer tank together with its radiator and
other fittings shall be subjected to pressure corresponding to
twice the normal pressure or 0.35 kg / sq.cm whichever is
lower, measured at the base of the tank and maintained for
an hour. The permanent deflection of the flat plates after the
excess pressure has been released, shall not exceed the
figures for vacuum test.
5. Short Circuit withstand test: Thermal and dynamic ability.
6. Magnetic Balance Test.
7. Noise-level measurement.
The testing shall be carried out in accordance with IS: 1180Part-1 2014 and
IS:2026 latest amendment& CEA Guideline as applicable.
6.4 TOLERANCES:
Unless otherwise specified herein the test value of the transformers supplied
would be within the tolerance permitted in the relevant standards. No
positive tolerance is allowed on guaranteed losses.
7.0 INSPECTION:
All tests and inspection shall be made at supplier works mentioned in A/T. The
manufacturer shall afford the inspector representing the purchaser all
reasonable facilities, without charge to satisfy him that the material is being
furnished in accordance with specification.
The manufacturer shall provide all services to establish and maintain quality of
workman ship in his works and that of his sub-contractors(for bought out
material/equipments)to ensure the mechanical / electrical performance of
components, compliance with drawings, identification and acceptability of all
materials, parts and equipment as per latest quality standards of ISO 9000.
Along with the bid the manufacturer shall prepare Quality Assurance Plan
identifying the various stages of manufacture, quality checks performed at
each stage and the Customer hold points. The document shall also furnish
details of method of checking, inspection and acceptance standards / values.
However, purchaser or his representative shall have the right to review the
inspection reports, quality checks and results of manufacturer’s in house
inspection department which are not customer hold points and the
manufacturer shall comply with the remarks made by purchaser or his
representative on such reviews with regards to further testing, rectification or
rejection etc. Manufacturer should submit the list of equipment for testing
along with valid calibration certificates from NABL accredited laboratory to
the purchaser along with the bid.
Purchaser shall have every right to appoint a third party inspection to carryout
the inspection process. The purchaser has reserved the rights to have the test
carried out at his own cost by an independent agency at NABL accredited
laboratory, wherever the dispute regarding the quality of supplies arise.
vii. Quality Assurance Plan (QAP) with all points for purchaser’s inspection.
8.2 The successful Bidder shall within 30 days of placement of order, submit
following information to the purchaser.
i. List of raw materials as well as bought out accessories and the names of sub-
suppliers selected from those furnished along with offer.
ii. Type test certificates of the raw materials and bought out accessories.
8.3 The successful Bidder shall submit the routine test certificates of bought out
accessories and central excise passes for raw material at the time of routine
testing.
9.0 DOCUMENTATION:
The Bidder shall furnish along with the bid the dimensional drawings of the
items offered indicating all the fittings.
i) Dimensional tolerances
ii) Weight of individual components and total weight
The tenderer shall submit the list of orders for similar type of equipments,
executed or under execution during last three years, with full details to enable
the purchaser to evaluate the tender.
The test results will be binding on the suppliers. DISCOM in general will not allow re-
sampling. If the material fails in any of the acceptance tests/type tests carried out
(except for no load and load losses), the full lot of materials will be considered as
rejected, and if replacement is not possible due to consumption of the materials, in
that case for whole of the rejected lot, DISCOM will deduct penalty as per below
mentioned details. If the same are not utilized / consumed, Company at sole
discretion may ask for replacement or may accept with penalty having details as
under and all these will be binding on the supplier.
To reject the complete lot OR recovery of penalty up to 30% in line with commercial
condition clause of audit testing.
1.Up to 30% penalty in line with commercial condition clause of audit testing.
Schedule A
H.V. BUSHINGS
1) JAYASHREE
2) BEPCO.
3) W.S. INSULATORS
4) ASSOCIATED PORCELAIN (11KV ONLY)
5) JAIPUR GLASS
6) SESHASAYEE
7) LUSTER CERAMICS
8) AGRAWAL SALT CO., BIKANER.
9) B.P.P.L., BIKANER.
10) VENKATESHWARA CERAMICS P.
11) CJI PORCELAIN INDIA LTD.
12) MAXWELL CERAMIC, WADHWAN, (ONLY 11KV)
13) RAVIKIRAN (ONLY 11KV)
14) VISHAL MALLEABLE LTD.
Signature of Tenderer Company’s Round Seal Date Place
Page 37 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
15) AS INSULATOR
16) REAL INSULATOR
17) REDIANT CERAMIC
18) SUN INSULATOR
19) PRIME INSULATOR
20) GENESIS ENTERPRISES PRIVATE LIMITED
L.V. BUSHINGS:
1) J.S.I. (RISHRA)
2) LUSTER CERAMICS
3) JAIPUR GLASS
4) AGRAWAL SALT CO., BIKANER.
5) B.P.P.L., BIKANER.
6) VENKATESHWARA CERAMICS, PVT. LTD.
7) CJI PORCELAIN
8) MAXWELL CERAMIC, WADHWAN.
9) RAVIKIRAN
10) VISHAL MALLEABLE LTD.
11) AS INSULATOR
12) REAL INSULATOR
13) REDIANT CERAMIC
14) SUN INSULATOR
15) PRIME INSULATOR
16) GENESIS ENTERPRISES PRIVATE LIMITED
MCCB:
1) Siemens
2) L&T
3) ABB
4) GE POWER
5) Schneider
6) Crompton Greaves
7) Havells
8) HPL
Annexure I
GUARANTEED TECHNICAL PARTICULARS
11 Losses
i Core loss Watts
a) at Normal Voltage Watts
b) at Maximum Voltage Watts
ii Full Load losses at 75 deg.C. Watts
iii Total losses at 50 % loading at 75 deg.C. Watts
iv Total losses at 100 % loading at 75 deg.C. Watts
12 Percentage Impedance at 75 deg.C. %
13 Maximum temperature rise of
a) Windings by resistance method 40 deg C
(35 deg C for 5KVA)
b) Oil by Thermometer 35 deg C
(30 deg C for 5KVA)
14 Clearances
a) Core & LV mm
b) LV & HV mm
c) HV Phase to Phase mm
d) End insulation clearance to Earth mm
e) Any point of winding to tank mm
Signature of Tenderer Company’s Round Seal Date Place
Page 39 of 44
SHORT NOTICE TENDER No. UGVCL/SP/I/CPP/884/16KVA Star 1 DTR.
Annexure II
Digit/letter Details TIN Remark
No.
Name of
1 M First letter of DISCOM name
Company
for 5/10/16/25/63/100/200/500
2 KVA rating 5 KVA ratings digits will be
respectively 1/2/3/4/5/6/7/8
Type of Core
3 1 CRGO-1,Amorphous-2
Material
Core
4 1 Stack-1, Wound-2
construction
5 1 each supplier will be given 2
Supplier Name
digit code no.
Code
6 5 e.g. M/s XYZ given code no.15
7 0
Month of 2 digits for Month of
manufacturing manufacturing
8 2
9 1
Year of 2 digits for Year of
manufacturing manufacturing
10 7
11 9
12 0
CPP Tender
4 digits for CPP tender no.
No.
13 3
14 2
5 digits for transformer sr. no.
15 0
given by supplier
Sr. No. of
16 0 (e.g. M/s XYZ will give
transformer
17 0 transformer sr. no. from 00001
given by
18 0 to 00260 for P.O. of 260 no.
Supplier
transformers issued to them vide
19 1 CPP tender no.9032 )