Project Report
Project Report
PROJECT REPORT
ON
CIVIL ENGINEERING
TABLE OF CONTENTS
1 FRONT PAGE 1
2 CANDIDATE DECLARATION 3
3 ACKNOWLEDGEMENT 4
4 APPROVAL OF PROJECT 5
6 ABSTRACT 9
7 INTRODUCTION 10
10 CONCLUTION 27-28
11 RECOMMENDATION 29
`
I, GINNY PALIWAL declare that the project “SEISMIC RETROFITTING OF EXISTING LOAD
BEARING STRUCTURE:” is of my own ideas and words and where
others ideas or words have been included, I have adequately cited and referenced the original
sources. I also declare that I have adhered to all principles of academic honesty and integrity and
have not misrepresented or fabricated or falsified any idea/data /fact /source in my submission.
I understand that any violation of the above will be cause for disciplinary action by the institute
and can also evoke action from the sources which have thus not been properly cited or from
whom proper permission has not been taken when needed.
ACKNOWLEDGMENT
i (MIE) for their guidance and supervision as well as for providing necessary information regarding the project
and also for their support in completing the project .
I would like to express my parents and my family members for their kind co-operation and
encouragement which help me in completing this project.
I have taken efforts in this project However; it would not have been possible without the kind support and
help of many individuals and organizations I would like to extend my sincere thanks to all of them.
I am highly indebted to DR. ITRAT AMIN SIDDHIQUE
My thanks and appreciation also go to my colleague in developing the project and people who willingly
helped me out me with their activities.
GINNY PALIWAL
ST-636180-9
`
APPROVAL OF PROJECT
This is to certify that the GINNY PALIWAL, Membership No. ST-636180-9 has completed his project work
SUMMARY OF PROJECT
TITLE-
Now we are here discussed on this project about retrofitting load bearing structure in existing building
ABSTRACT
- Earthquakes are the induction of transformation in the earth internal structure .Seismic activity is
common in most part of the world ,through the frequency of its occurrence is a function of local
tectonic setup. The part earthquake experiences have demonstrated huge loss of life and building
stock, affecting the social and economic conditions of a country .Through it is not possible to prevent
an earthquake ,the least can be achieved in reducing the damage is to make the building earthquake
resistant .With the advancement in our understanding of the earthquake ,most of the countries have
mandated the incorporation of seismic provision in building design and architecture.
In the event of an earthquake, the seismic waves originating from the focus is transmitted in all the
possible directions.These shocks waves are propagated in the form of body waves and surface waves
through earth’s interior and are highly random in nature .These ground motion cause structure to
vibrate and induce the inertia forces in the structural elements .In the absence of seismic design ,the
building may fail ,leading to a catastrophe.The seismic design philosophy aim to primarily ensure life
safety and secure functionality of the building.
No region in the whole of the india can be considered as earthquake free due to the ongoing
subduction of the Indian plate under the Eurasian plate. The paper aim to create an awareness about
the earthquake safe building various seismic zones. This study investigates the contraction practices
wherever found necessary with the revelance to the codal provisions in addition the possible future
trend in the earthquake resistant technology has also been discussed.
NEED OF PROJECT
A large number of existing buildings in India is severely deficient against earthquake forces and the
number of such buildings are growing very rapidly. This has been highlighted in the past earthquake.
Retrofitting of any existing building is a complex task and requires skill, retrofitting of RC buildings is
particularly challenging due to complex behaviour of the RC composite material. The behaviour of the
buildings during earthquake depends not only on the size of the members and amount of
reinforcement, but to a great extent on the placing and detailing of the reinforcement. The
construction practices in India result in severe construction defects, which make the task of retrofitting
even more difficult. Appropriate maintenance prolongs the life span of a structure and can be used to
prevent such damages can help to avoid failures which may result due to these damages. Higher
operational loads, complexity of design and longer life time periods imposed to civil structure make it
increasingly important to monitor the health of these structures.
.Due to revision of code
.Well designed but poor construction
.Improving performance of building for higher earthquakes
`
INTRODUCTION
Large stocks of existing structures and infrastructure are deteriorated with use and time and
might have passed their design life and require retrofitting and rehabilitation. The cost of
retrofitting various infrastructures is estimated in the lakhs of rupees. To overcome the ill effects
caused by these deteriorated buildings Repair and Rehabilitation works are carried out from time
to time. Many of the existing structures were designed to codes that have since been modified
and upgraded. Change in use or higher loads and performance demands require modifications
and strengthening of structural elements. Concrete construction is generally expected to give
trouble free service throughout its intended design life.
However, these expectations are not realized in many constructions because of structural
deficiency, material deterioration, unanticipated over loadings or physical damage. Premature
material deterioration can arise from a number of causes, the most common being when the
construction specifications are violated or when the facility is exposed to harsher service
environment than those expected during the planning and design stages.
PROBLEM STATEMENT
STEP 1: It is imperative that we must have Architectural and Structural plans of the buildings. It will
be helpful if we have detailed structural calculations including assumptions for the structural design.
`
STEP 2: If the Architectural plans and Structural plans are not available, the same can be prepared by
any Engineer.
STEP 3: Inspection of the Building - A detailed inspection of the building can reveal the
Following:
Concrete disintegration and exposed steel reinforcements photographs can be helpful. Slight
Corrosion in reinforcement.
Cracks in walls indicating swelling in R.C.C. members or deflection or corrosion. Leakages from
Leakages & dampness in walls resulting into cracks and corrosion. Status of
STEP 4: Preparation of Audit Report: On the basis of inspection of building an Audit Report is
prepared.
STEP 5: Tests Recommended: It is important that various tests are carried out in the old buildings.
This will give an idea about the extent of corrosion, distress and loss of strength in concrete &
steel.
The need for retrofitting is to solve problem raised due to excessive loading, seismic
effects, poor workmanship or poor construction material. If building is in out dated
condition according to IS codes there is need to be retrofitted.
Damage to the structural members.
Excessive loading.
Errors in design or construction.
Seismic damage
Structural failure.
Corrosion due to penetration honeycombs.
Change in use of building
Upgradation of code
Definition
Efflorescence in Walls
Bonding
REPAIR
The main purpose of repair is to bring back the architectural shape of the building so that all services
start working and the functioning of building is resumed quickly. Repair does not pretend to improve
the structural strength of the building .
Checking and repairing gas pipes, water pipes and plumbing services.
material, which is strong in tension into the cracks in walls, column, beam and footing
RETROFITTING
Retrofitting is the seismic strengthening of existing damaged or undamaged buildings. It is an
improvement over the original strength when the evaluation of the building indicates that the
strength available before the damage was insufficient and restoration alone will not be
adequate in future quakes.
(a ) PLAN OF A BUILDING
The building as a whole or its various blocks should be kept symmetrical about both the
axes. Asymmetry leads to torsion earthquake and is dangerous.
Simple and regular shapes behave better during earthquake than shapes with many
projections.
If longer lengths are required two separate blocks with sufficient gap 25 to 40 mm in
between should be provided.
The projection in plan shall not exceed L/3 or B/3 in length or width respectively.
Length of block in plan should not exceed
For single storey building, wall thickness shall not be less than 1 brick (190 MM) For
Three storey building, wall thickness in ground storey shall not be less than 1 1 2 brick
and in the upper floors wall thickness shall not be less than 1 brick.
Wall thickness shall not the less than 1/16 of the distance between two cross walls. The floor
height shall not exceed 3.0 m.
A, B, C 3
D 2
In walls the size of opening shall be small and located in the middle of the wall. Opening
Shall be located at minimum distance of ¼ into height of opening from the inner corner. This
distance shall not be less than 60cm
Total length of openings in a wall shall not exceed :
One Storey Building = 50% of the distance between two cross walls. Two
Storey building = 42% of the distance between two cross walls. Three Storey
building = 33% of the distance between two cross walls.
The horizontal distance between two nearby openings shall not be less than 0.5 x height of
opening and not less than 60cm.
The vertical distance between two openings shall not be less than 0.5 x Width of opening
and not less than 60cm.
If above criteria are not satisfied, the opening shall protected by 2-8mm diameter of bars.
PLINTH BAND- Plinth bands are provided when soil is soft or uneven in their
properties. This band also acts as DPC
LINTEL BAND- This is most important band and will in corporate in itself all doors
and window lintels. It must be provided in all storeys in buildings. The
reinforcement of lintels should be provided extra.
ROOF BAND- This band will be required at eaves level of trussed roofs and also
below or in the level with such floors which consists of joists.
GABLE BAND- Masonry gable ends must have the triangular portion of masonry
enclosed in a band, the horizontal part will be continuous with the eave level band.
`
In some cases, it is needed to reduce the load on the beam that needs strengthening before
implementing the previous steps, either partial or complete unloading. This is made by putting steel
beams on top or below the concrete beams, as shown in Fig5.
The following photos were taken during strengthening an existing building; they present the practical
The structure must be shored and jacked if it is desire to relieve the member’s dead load stresses
so that new reinforcing will resists the original dead load. Several bonding materials may be used.
Portland cement grout, epoxy, and other chemicals adhesives have been successfully installed
within the annular space between the dowel and sides of the predrilled hole.
The dowels may be deformed steel reinforcing bars, stainless steel rods or bolts. Coating steel
dowels with either zinc galvanizing or fused epoxy is acceptable. If all components are chemically
compatible with the bonding material.
`
The horizontal distance between two nearby openings shall not be less than 0.5 x height of
opening and not less than 60cm. The vertical distance between two openings shall not be less
If above criteria are not satisfied, the opening shall protected by 2-8mm diameter of bars.
`
ADDING A BAND
`
CASE STUDY
Inspection of Building
An Inspection is a qualitative assessment of damaged building, based on the experience and skill of
the engineer. A systematic inspection provides a fair idea about the irregularities in building configuration,
construction defects and most importantly, the signs of distress and deterioration of the structure. It is
helpful in deciding the extent of investigation and selection of material & technique to enhance the
structural performance of building.
In visual inspection we find that most of walls have several crackers – Flexural, diagonal, shear &
Tensile cracks approximately in the width of 0.5-1mm.
Beam are also having some hair cracks which are shear cracks.
Columns & walls are also settled some columns concrete cover is deteriorated;
therefore, reinforcement is visible & rusted.
In visual inspection we find that most of walls have several crackers – Flexural, diagonal, shear &
Tensile cracks approximately in the width of 0.5-1mm.
Beam are also having some hair cracks which are shear cracks.
Columns & walls are also settled some columns concrete cover is deteriorated; therefore,
reinforcement is visible & rusted.
Evaluation Of Building
To Clear all the situation there is a need to perform some taste on the different component of
building.
DETAILED INVASTEGATION: - After perform some non-destructive taste on this building to find
out actual strength & condition of the building
Field measurements are taken & Preparation for the as-found Plans.
By using Rebound hummer, we tasted compressive strength of the columns, beam and Roof
strength.
We found that column which is designed for a strength of M20 it just has 15.5N/mm2 and Beam
should have design strength of 20N/mm2 but it shows only 17 N/mm2 strength & most of main
reinforcement of roof is rusted approximately 30 %. Concrete of column & beam are honey
combed both type big honeycomb & small honeycomb.Core test of concrete – 3 cores are taken by
cutting in same sections. if the average equivalent cube strength of the cores is equal to 85% of
strength of core, then it is ok. Here, when we tasted compressive strength test of the core in
laboratory get an average strength of 15N/mm2 of columns and 18N/mm2 of beam. So that, some
beams are in acceptable condition but few columns & beams should be necessarily strengthen.
After studying all aspect of this case, we concluded to Retrofit the building. The Retrofit of this
building would be done step by step according to the sequence.
Repair of cracks
Repair of Floors
Repair of Plast
`
Firstly, we start with strengthen of column, beam & slab by using reinforced cement concrete
jacketing method. Which includes
cleansing of surface
Shotcreting
Curing
Repair
Finishing
Whole building columns and beam are not jacketed only few columns & beams are retrofitted,
which are in critical situation. Here is total 8 columns & mainly 4 beams which, are in critical
condition & we decided it to Retrofit. The size of existing columns is 230x300mm and strength of
these found near about 15.5N/mm sq. as the result of rebound hammer test To strengthen the
building, it is necessary re
`
CONCLUSIONS
Final Conclusions
In this study, first the seismic resistance of seven-story steel moment frame building was
evaluated. The three-dimensional “Equivalent Static Analysis-ESA”, “Response Spectrum
Analysis-RSA” and “Time History Analysis-THA” evaluations were carried out. The 3D ESA
and RSA was carried out in order to obtain the fundamental period, dominant mode
shapes and the base shear. In ESA, the fundamental period of the structure is 2.42sec. The
roof-displacement is 4.89in and the total base shear of the structure is 875.87k which is
obtained and distributed as story lateral loads throughout the building as described in
ASCE7- 05 Chapter 12.
In RSA the fundamental period of the structure is 2.47sec. and the roof- displacement is
4.05in where the first 20 mode shapes are combined with the CQC method. The
displacements were scaled by a scale factor of 1.517 due to obtained base shear 490.62k is
less than 85% of the equivalent lateral force method base shear. In the 3D THA with
recorded ground motion parameters of Northridge, CA Earthquake (1994) at discrete time-
steps, the fundamental period of the structure is 2.32sec. and the roof-displacement is
5.19in. As shown in the analysis above, the drift demands haven’t been met with allowable
limits in ASCE7.
The steel moment frame structure is retrofitted with concentrically steel braces in the
interior spans to decrease the deformations into acceptable limits. The retrofitted section
was analyzed by two-dimensional “Pushover Analysis”. The structure was pushed to a
target displacement (20in) where serious damage starts to occur. Plastic hinges as
expected initially started to occur on diagonal braces of the first three floors as a result of
each step of pushing the building. When the target displacement was reached, plastic
hinges started to occur in the first floor column which is an indication of significant
damage and relatively fewer damages were obtained after the third storey. When
evaluating the performance impact of retrofit implementation, it was quite obvious that
the addition of braces to the moment frame served to stiffen the building sufficiently and
help the structure resist lateral load
`
Generally, the structural retrofit improved the seismic resistance of the building and it can be
considered in the retrofit of moment frame structures to prevent the risk of structural collapse
under the design load with much more confidence. This study shows how the pushover analysis
may be used in order to estimate the seismic resistance of existing or retrofitted
structures as well as how the linear analysis may be followed by a detailed nonlinear
analysis of part of the structure. One of the most significant advantages of nonlinear
pushover analysis beyond the linear analyses is the opportunity to evaluate damage. The
pushover analysis can give valuable information about performance of building in expected
future seismic events
`
Recommendations
In this research of seismic retrofits, there were numerous points which were not covered by the
scope of this due to limitations in time and resources. However, they might be considered to
create a more detailed research for future work. These recommendations for further research
work are discussed below.
For this study, only one computer software was used to run all the analyses. Although, SAP 2000
is largely accepted in academia and engineering offices for structural analysis, it is advisable to
use different applications to compare the results rather than to rely on information from one
source. In further research, it is highly recommended to use different structural analysis software
to validate the results.
Due to the time constraints in developing this thesis, only the linear analyses were modeled in
three-dimensional model. Non-linear pushover analysis was modeled two- dimensional system
in retrofitted building. Additionally, the building was simplified in model with basic structural
framing which didn’t include many elements such as stairs, elevators, mechanical equipment,
etc. Furthermore, non-linear time-history analysis was not analyzed which would provide the
thesis with more accurate results. In further research, three-dimensional non-linear analyses
with both pushover and time-history including the weak zones are highly recommended to
capture more realistic behavior of the structure.
`