Lect 3
Lect 3
Lecture 3
Materials Management
Learning Outcomes of Lecture 3
1. Explain what material requirements planning (MRP) is
• Determine the number of subassemblies, components, and raw materials required and
their build dates to complete a given number of end products by a specific date
• How much of each part to obtain?
• When to order or produce the parts?
• What is Material Requirements Planning? - YouTube
• MRP does not work well in companies that produce a low number of units annually
• Better handled using project management
Industry Applications and Expected Benefits of MRP
Master Production Schedule
• Master production schedule (MPS) is the time-phased production plan that
specifies how many of each end item the firm plans to build, and when
• Major input to the MRP process
The next level down (not shown) would be the MRP program that develops detailed schedules
showing when cotton batting, springs, and hardwood are needed to make the mattresses.
Planning Sequence
• Specify product groups
• No specific items
Aggregate Plan
• Time fences: periods of time having some specified level of opportunity for
customer to make changes
• Frozen: make no or only insignificant changes to products
• Slushy: allow some changes in specific products within a family
• Liquid: allow almost any variation in products
Master Production Schedule Time Fences
Goals, Objectives, and Philosophy of MRP
• Goal
• Control inventory levels, assign operating priorities to items, and plan capacity to load the production system
• Inventory
• Order the right part at the right quantity at the right time
• Priorities
• Order with the right due date and keep the due date valid
• Capacity
• Plan for a complete work load for both machines and workers
• Plan an accurate load – make only what is needed
• Plan for an adequate time to view future loads
Benefits for MRP System
• Lower selling price due to increased scheduling efficiency
• Improved customer service because products are made and delivered as needed
• Secondary reports
• Planning reports
• Performance reports
• Exceptions reports
An Example Using MRP
• Ampere, Inc., produces a line of electric meters installed in residential buildings by
electric utility companies to measure power consumption
• Meters used on single-family homes are of two basic types for different voltage and
amperage ranges
• In addition to complete meters, some subassemblies are sold separately for repair or for
changeovers to a different voltage or power load
• The problem for the MRP system is to determine a production schedule to identify each
item, the period when it is needed, and the appropriate quantities
Forecasting demand
• Two sources of demand for the meters and components
• Regular customers that place firm orders in advance based on the needs of their projects
• Other customers that buy these items as needed, forecast requirements
Developing a Master Production Schedule
• Assume that the quantities to satisfy the known and random
demands must be available during the first week of the month
Bill-of-Materials (Product Structure)
• To keep things simple, we will focus on only one of the parts, part D, which is a transformer
Inventory Records
• Safety stock: minimum amount of inventory that we always want to keep on hand for an item
• On order: inventory scheduled to arrive
Week
Item 4 5 6 7 8 9
A
Projected available
Safety stock = 20 balance
• Lot-for-lot: Sets planned orders to exactly match the net requirements
Order qty = 5,000 Net requirements
Planned order receipts
Planned order releases
Week
Item 4 5 6 7 8 9
A
Performing MRP Calculations LT = 2 weeks
On hand = 50
Gross requirements
Scheduled receipts
1250
Projected available 50 50 50 50 50 0
Safety stock = 0 balance
Order qty = lot-for- 1250-50=1200
lot Net requirements
Planned order receipts 1200
Planned order releases 1200
B
LT = 2 weeks Gross requirements 470
On hand = 60 Scheduled receipts 10
Projected available 60 60+10=70 70 70 70 0
Safety stock = 0 balance
Order qty = lot-for- 470-70=400
lot Net requirements
Planned order receipts 400
Planned order releases 400
C
1200 +400
LT = 1 week Gross requirements
On hand = 40 Scheduled receipts
Projected available 2000-1565=435 435 435
40-5=35 35 35
Safety stock = 5 balance
1200+400-
Order qty = 2,000 Net requirements 35=1565
Planned order receipts 2000
Planned order releases 2000
D
4000 1200 270
LT = 1 week Gross requirements
On hand = 200 Scheduled receipts 100
• Produces exactly what is needed each week with no inventory carried over
into future periods
𝐷 𝑄
𝑇𝑜𝑡𝑎𝑙 𝑐𝑜𝑠𝑡 𝑄 = 𝑃𝐷 + 𝑆 + ℎ
𝑄 2
production setup holding
cost cost cost
𝐷 𝑄 ∗
2𝐷𝑆
𝑆 =ℎ 𝑄 =
𝑄 2 ℎ
Least Total Costs and Least Unit Cost
• Least total costs
• Dynamic lot-sizing technique that calculates the order quantity by comparing the
carrying cost and the setup (or ordering) costs for various lot sizes and then selects the
lot in which these are most nearly equal
𝑇𝑜𝑡𝑎𝑙 𝑐𝑜𝑠𝑡
𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑟𝑑𝑒𝑟𝑒𝑑
Choosing the Best Lot Size
• In the previous example for MRP Lot-Sizing problem
• Lot-for-lot: 376$
• EOQ: 171.05$
• Least total cost: 140.50$
• Least unit cost: 153.50$
• The advantage of Least Unit Cost is that it is a more complete analysis and would take into account
ordering or setup costs that might change as the order size increases
• If the ordering or setup costs remain constant, Least Total Cost method is more attractive because it is
simpler and easier to compute
MRP in Services
• Point-of-sale (POS) terminals Point of Sales Terminal - YouTube
• An inventory management system (one or more cash registers) connected to a central
computer located either on-site or at a remote location
• The POS terminals are designed for single-item pricing, where a single key represents
a specific item on the menu
• For each item sold, the system automatically posts the price of an item and subtracts
all of the items’ ingredients from the inventory records file