Blk.9 Lot 11 west plain subd. De Ocampo 4109 Trece Martires City (Capital) Cavite, Phil.
E-mail: [email protected]
BILL OF QUANTITIES
Quotation No. 23-011
ATTENTION: Mr. Alex Aguilar
TO : Clean Air Construction and Supply
PROJECT: HIGHBAY LAMP INSTALLATION
LOCATION : JTI, San Fernando , Malvar Batangas
ITEM DESCRIPTION UNIT QTY UNIT COST AMOUNT
SCOPE OF WORKS :
• Mobilization
• Layout / Marking
• Installation of Support System
• Roughing Ins
• Cable Pulling
• Installation of High Bay Light
• Termination Works
• Testing and Commissioning
• Tun over
• Demobilization
ELECTRICAL WORKS
Conduits and Pipes
EMT Conduit 1" le 4 502 2,007.04
EMT Conduit 3/4 " le 35 402 14,072.80
Connectors and Fiittings lot 1 2,867 2,867.20
Support System lot 1 5,040 5,040.00
Wires and Cables
THNN Wire 8.0mm2 , Red mtrs 10 118 1,176.00
2
THNN Wire 8.0mm , Black mtrs 10 118 1,176.00
THNN Wire 8.0mm2 , Blue mtrs 10 118 1,176.00
THNN Wire 5.5mm2 , Green mtrs 10 75 750.40
2
Royal Cord 5.5mm ,3c mtrs 95 398 37,800.50
Wire Accessories lot 1 5,807 5,806.89
Devices and Equipment
Power Panel assy 1 29,394 29,394.00
50AT/50AF Main
20AT/50AF Branches
High Bay LED 100W pcs 10 10,775 107,750.00
LABOR COST
Labor lot 1 200,000 200,000.00
GENERAL REQUIREMENTS
Mobilization / Demobilization lot 1 20,000 20,000.00
Accomodation lot 1 12,000 12,000.00
Transportation/Deliveries lot 1 15,000 15,000.00
OSH Management lot 1 20,000 20,000.00
Supply of Special Scaffolding lot 1 30,000 30,000.00
Erection of Scaffolding lot 1 20,000 20,000.00
Subtotal: 476,016.83
VAT 12 % 57,122.02
DISCOUNT: 3,138.85
Grand Total 530,000.00
Lead time for materials
Royal cord wire - 2-3 days -upon receive of P.O
Power Panel - 5-7 days upon received of P.O
Exclusion : Water and Power Supply Duration : 15 working days
Terms : 50% Downpayment Note : Additional materials will be billed separately
40% Progress Billing Additional scope will be billed separately
10% Upon Completion
Angelo P. Ampog Jay Ramirez Jesun Tingson
Prepared By: Noted By: Checked By :