This document is a bill of quantities for a highbay lamp installation project. It contains a scope of works, itemized list of materials, labor costs, general requirements, and notes. The total cost for the project is 530,000 pesos. The lead times for key materials like royal cord wire and the power panel are also noted.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views2 pages

Jti - Highbay Light Installation 23-011

This document is a bill of quantities for a highbay lamp installation project. It contains a scope of works, itemized list of materials, labor costs, general requirements, and notes. The total cost for the project is 530,000 pesos. The lead times for key materials like royal cord wire and the power panel are also noted.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Blk.9 Lot 11 west plain subd. De Ocampo 4109 Trece Martires City (Capital) Cavite, Phil.

E-mail: [email protected]

BILL OF QUANTITIES
Quotation No. 23-011
ATTENTION: Mr. Alex Aguilar
TO : Clean Air Construction and Supply
PROJECT: HIGHBAY LAMP INSTALLATION
LOCATION : JTI, San Fernando , Malvar Batangas
ITEM DESCRIPTION UNIT QTY UNIT COST AMOUNT
SCOPE OF WORKS :

• Mobilization
• Layout / Marking
• Installation of Support System
• Roughing Ins
• Cable Pulling
• Installation of High Bay Light
• Termination Works
• Testing and Commissioning
• Tun over
• Demobilization

ELECTRICAL WORKS

Conduits and Pipes


EMT Conduit 1" le 4 502 2,007.04
EMT Conduit 3/4 " le 35 402 14,072.80
Connectors and Fiittings lot 1 2,867 2,867.20
Support System lot 1 5,040 5,040.00

Wires and Cables


THNN Wire 8.0mm2 , Red mtrs 10 118 1,176.00
2
THNN Wire 8.0mm , Black mtrs 10 118 1,176.00
THNN Wire 8.0mm2 , Blue mtrs 10 118 1,176.00
THNN Wire 5.5mm2 , Green mtrs 10 75 750.40
2
Royal Cord 5.5mm ,3c mtrs 95 398 37,800.50
Wire Accessories lot 1 5,807 5,806.89

Devices and Equipment


Power Panel assy 1 29,394 29,394.00
50AT/50AF Main
20AT/50AF Branches
High Bay LED 100W pcs 10 10,775 107,750.00
LABOR COST
Labor lot 1 200,000 200,000.00

GENERAL REQUIREMENTS
Mobilization / Demobilization lot 1 20,000 20,000.00
Accomodation lot 1 12,000 12,000.00
Transportation/Deliveries lot 1 15,000 15,000.00
OSH Management lot 1 20,000 20,000.00
Supply of Special Scaffolding lot 1 30,000 30,000.00
Erection of Scaffolding lot 1 20,000 20,000.00

Subtotal: 476,016.83
VAT 12 % 57,122.02
DISCOUNT: 3,138.85
Grand Total 530,000.00

Lead time for materials


Royal cord wire - 2-3 days -upon receive of P.O
Power Panel - 5-7 days upon received of P.O

Exclusion : Water and Power Supply Duration : 15 working days

Terms : 50% Downpayment Note : Additional materials will be billed separately


40% Progress Billing Additional scope will be billed separately
10% Upon Completion

Angelo P. Ampog Jay Ramirez Jesun Tingson


Prepared By: Noted By: Checked By :