W7 - Project Planning (Part 3) Critical Path
W7 - Project Planning (Part 3) Critical Path
TIME CALCULATION
LOGO
LEARNING OUTCOME
Float/ Slack
It is additional time available to
complete an activity beyond the
activity’s work duration.
Activities on critical path have no
float.
Types of float:
• Total Float
• Free Float
Important Terms :
Total Float
Total time available to delay the start of an activity
without changing the project duration.
(LF-EF) or (LS-ES) of proceeding activity
Free Float
The time available to delay the start of the activity
without interfering the early start time of the activities
that follows.
Free float (n)=minimum early start of all successor
activities - early finish (n)
ES proceeding activity – EF current activity
Important Terms :
Critical Path
Represents the path which consist of all
activities that have no float time.
1 2 3 4 5
1-2 5 0 0+5=5 5
2-3 3 5 5+3=8 8
3-4 1 8 8+1=9 9
4-5 4 9 9+4=13 13
Backward Pass Computation
5-4 4 13 13-4=9 9
4-3 1 9 9-1=8 8
3-2 3 8 8-3=5 5
2-1 5 5 5-5=0 0
Backward Pass
0 5 8 9 13
1 2 3 4 5
Calculate the ES, EF, LS & LF.
ES=6 EF=10 23 DAYS
LS=14 LF=18
ES=0 EF=6 4
LS=8 LF=14
2 7 ES=18 EF=23
G LS=18 LF=23
6 5
A H I
ES=5 EF=12 6
LS=5 LF=12 ES=12 EF=18
1 7 LS12 LF=18 9
4 6
ES=3 EF=5 F ES=13 EF=15
LS=3 LF=5 ES=12 EF=13
3 LS=20 LF=21 LS=21 LF=23
C2 K 2
B J 1
ES=0 EF=3
LS=0 LF=3 7 1
3 D
5 8
E
ES=3 EF=10 ES=10 EF=11
LS=13 LF=20 LS=20 LF=21
Calculate the TF and FF