S4-05-PD Measurement On Power Cables
S4-05-PD Measurement On Power Cables
Mohan Watwe
Doble Engineering Company
ABSTRACT
Cable network systems in the power system are one of the most important part but also the
part most vulnerable to failure. More than half of cable failure stems from electrical reason
and the rest of them are due to external non-electrical inference. The main reasons for
failures on newly installed cables are-bad workmanship or damage caused during
manufacture, transportation or installation. Most defects observed in the cable accessories
results in partial discharges (PD) under the AC stress. Sensitive PD measurements can give
better understanding to assess the health of cable system
There are many diverse measurement methods which can be used to assess the condition of
high voltage cable at site. Each one of them has its own advantages and disadvantages and it
depends on the actual condition and defect which method is appropriate.
This paper describes the UHF and Acoustic PD measurement method to measure PD in the
cable accessories for EHV-XLPE cable systems in on line condition at site.
INTRODUCTION
Cable failure probability usually follows the so called bathtub curve where the failure
probability is high at the beginning and at the end of cable life. The rise of failure probability at
the end of cable’s life is mainly caused by cable aging. From statistics it is found that most of
the faults happen in cable joints and terminations. The addition of terminations and joints can,
if not properly installed, introduce PD into the cable system.
Most of the defects observed in the cable accessories results in partial discharges (PD) under
the AC stress. Sensitive PD measurements can give better understanding to assess the
health of cable system.
All power cables with polymer insulation are tested in the factory according to IEC60840 and
IEC62067 under ideal conditions (no environmental influences) and with calibrated PD
measuring systems in a shielded room. Similar conditions do not exist at site and
electromagnetic disturbances become a major issue to carry out measurements as per IEC
60270 at site.
Non-conventional partial discharge methods have since been established for condition
assessment of power cable insulation. This paper discusses applications that employ UHF
and Acoustic sensors, suitable for HV XLPE cable terminations like transformer sealing ends,
cable terminations for GIS /metal-clad substations and outdoor sealing ends based on field
experiences during investigations at site.
The test procedures recommended in the relevant standards IEC 60270 and IEC 60885-3
(conventional PD measurements) are not practical in an energized substation. The required
sensitivity is lost in the background noise due to the low signal-to-noise (S/N) ratio. This is
because the upper measuring frequency is limited to 500 kHz and below by IEC standards
and this is where substation noise is most prevalent.
From a physical point of view, the S/N ratio can be improved by increasing the measuring
frequency significantly higher than 500 kHz and by using either a frequency selective signal
processing or ultra wide band signal processing. Therefore the UHF PD measuring
technology is increasingly being used as an alternative
PDM SYSTEM
LDS-6 UHF
OR
PD SMART-UHF
The attachment of the UHF-PD-coupler to the cable termination is evident from figure 2.
This arrangement can be considered as a short circuit between the grounded parts of the
GIS enclosure and the cable termination, for the lower frequency range. In the UHF range,
however, the resulting impedance becomes about 50 Ω, which ensures an excellent S/N ratio
and thus a high PD detection sensitivity even under noisy on-site condition.
The output of the UHF-PD-coupler is connected via a coaxial cable to a preamplifier installed
close to the UHF sensor. Via a coaxial cable the signal is fed to the PD detector.
For PD pulse processing the PDM instrument is equipped with an UHF-Processing unit with
functionality similar to a spectrum analyzer. The measuring frequency in the zero span mode
of the UHF Processing unit is adjustable with a frequency bandwidth of 8 MHz in the
frequency range of 110 MHz to 900-1700 MHz
For the measurements in this mode various measuring frequencies having better S/N ratio
and signal strength are selected. The acquisition as well as the storage and the visualization
of the PD data are performed by means of the computer-based PD measuring system.
Voltage Synchronization
The decoupled PD signals from the PD coupler can be synchronized to the main power
supply of the measuring device (50 Hz line frequency).
In the recorded measuring files all necessary information is available. This permist all display
and diagnosis facilities from a rough overview about the PD magnitude up to the derivation
of expert system analysis. The PD Signal evaluation strategy is schematically shown
in figure 3.
In figure 4 the basic signals for the PD analysis resp. PD pattern evaluation is shown
Test Sequence
The above steps were carried out at 5 different measuring frequencies per measuring point.
All feeders were in online state, i.e. the test was carried out with normal operating voltage.
A measurement was done with the PD current sensor without connecting to the cable
termination was done to record the ambient noise at one location.
Finally the evaluation of measured data using analysis software (PRPD Pattern Recognition
and Replay-Mode) was carried out.
The measuring recordings are listed below as the PRPD Pattern (Phase Resolved Partial
Discharge Pattern) - diagrams. The recordings are quantified in mV.
For the cable sealing ends at transformer I, no typical PD patterns were observed despite of
many signals captured. There are no significant differences between the phases neither in
phase position nor in magnitude.
At transformer II, no typical PD patterns were detected. For different measuring frequencies
partly different patterns were observed, whereas magnitudes and patterns were comparable
between the phases.
At the sealing ends of transformer III the detected signals are with lower magnitude. The
behavior of all phases is also comparable. No dedicated PD patterns have been observed.
The overall signal activity in the GIS substation was found less than at the transformers
side.
For feeder 1 there was partly different behavior through all measuring frequencies.
The signal magnitudes of the three phases are comparable and no typical PD
patterns have been recorded.
Even fewer noise signals were detected at feeder 3. No PD patterns became apparent.
There was no indication for dangerous partial discharges found on the sealing ends in the
GIS substation.
The DFA100 instrument analyses the electric signals from an ultrasonic sensor. This sensor l
detects the acoustic signals emitted from partial discharges in cable terminations and joints.
The patterns of the acoustic signal indicate PD activity in the cable termination. Partial
discharges in the termination are discovered when there is distinct phase correlation of the
acoustic signal (phase correlation to 50Hz and 100Hz).
The instrument gives results that show the instants where the discharges appear relative
to the phase of the If a synchronizing signal from a 50 Hz power supply in the station is used,
the power frequency voltage. Thus, amplitude vs. phase plot is
obtained as illustrated in Figure 1.2. In the given example partial discharges appear
more or less concentrated in two parts of the power cycle, i.e. in both half cycles.
Below is a picture where piezoelectric (acoustic) sensor was placed in phase R. cable
termination on a 110 KV GIS and relevant acoustic patterns captured by DFA100 instrument.
The DFA100 instrument was synchronized to power grid by using the Synchronization Box
during the survey.
During on-site test, cable terminations in two left phases Y and B were also tested.
Neither of them show acoustic signal indicating PD. For phase R it was recommend to repeat
the acoustic test after some time (2, 3 months) in order to look for trends of magnitude of the
acoustic signal and to assess the risk of failure.
CONCLUSION
As can be seen from the different case studies as above, the unconventional PD monitoring
technology at power cable accessories has been successful as a valuable monitoring and
diagnostic tool for assessing the health of HV- and EHV power cable terminations.
It can be seen that undesirable failures can be prevented if suitable measuring methods are
applied for commissioning- and inspection tests at power cable systems.
REFERENCES
[1] Eberhard Lemke “Practical Experience in PD Sensing of Power Cable Accessories in the
VHF/UHF Frequency Range” ICC Fall 2010 Meeting Scottsdale / Fountain Hills, ( 2010)
[2] Instruction Manual, The Doble Type MEU 2500-Volt Portable Insulation Test Set,
Copyright, 1987, Doble Engineering Company
[3] Partial discharge measurements. IEC 60 270 (2001)
[4]Test methods for partial discharge measurements of extruded power cables. IEC 885-3
(1989)
[5] E. Lemke, H. Elze, W. Weissenberg: Experience in PD diagnosis tests of HV cable
terminations in service using the ultra-wide band PD probing. 14th ISH Deft (2003)
[6] E. Lemke, T. Strehl, W. Weissenberg, S. Markalous: Ultra-Wide-Band PD Diagnostics of
Cable Terminations in Service, IEEE Transactions on Dielectrics and Electrical Insulation
Magazine, 2008
[7] Matthias Boltze, Sacha. Michel Markalous, Alain Bolliger, Omar Ciprietti, Javis Chiu” On-
Line Partial Discharge MonitoringAnd Diagnosis at Power Cables; 76th Annual International
Doble Client Conference-2009