The document outlines a method statement for a construction site that includes: 1) Establishing temporary site boundaries and fences to maximize safety. 2) Using modern construction equipment that minimizes environmental impacts like noise and emissions. 3) Implementing a risk management plan to ensure safety from fires, chemical spills, and other hazards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views1 page

Project Work Methodology

The document outlines a method statement for a construction site that includes: 1) Establishing temporary site boundaries and fences to maximize safety. 2) Using modern construction equipment that minimizes environmental impacts like noise and emissions. 3) Implementing a risk management plan to ensure safety from fires, chemical spills, and other hazards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Method Statement

A. Build temporary site boundaries enclosure fencing to maximize site safety to the contractors,
employer personnel plant and equipment, visitor, bystander and the environmental.
B. Use of the latest model of construction equipment that inflict minimal disturbance to the
environment such as sound/noise deterrent, smoke/fume machinery equipment.
C. Setting up risk management plan to guarantee employer and employee personnel, pedestrian
and plant and equipment safety.

- Risk management plan for fire and explosion.

- Risk management plan for chemical and oil contaminants

- Risk management plan for an act of hostility such as war broke-up

D. Encourage and provide the construction worker and site personnel with the personal protective
equipment such as hard hat, safety cap boot, coverall protective clothing and earmuffs as part of
company duty of care practice.
E. Deploy the use of barricades, guards, fencing, shoring, temporary roadways, footpaths, signs,
lighting, watching and traffic flagging (lollipop personnel).
F. We will provide any rectification service if the need arise such as for access ways and property
damage.
G. Obstruction to the existing service such as utilities supply line will be minimized.
H. Encourage construction worker and site to comply with manual handling standard and workplace
ergonomic activity.
I. Posted site security and site entry reports point to ensure the safety of site plant, equipment,
environment and the personnel 24 hours a day, 7 days a week. Maintain site entry logging of any
visitors.
J. Build a temporary site compartment for daily administrational management.

Site office will be used to conduct daily meeting to oversee to plant and equipment safety
documents all well as general site induction prior to entering the construction site.

K. Allocate emergency muster point.


L. Setting up site pedestrian walkway access and emergency clearway access as well as vehicle
road access.
M. Set up temporary site ablution/toilet
N. Set up clear and conspicuous sign indictor.
O. Highly rigorous on workplace harassment and encourage gender equality.
P. Very strict and safety compliance is a must on the use rigging, dogging and scaffolding
equipment including safety harnesses.
Q. Workplace safety awareness enforcement is highly recommended.
R. Categorize bin allocation for each type of rubbish such as oil, recyclable material and non-
recyclable material.
S. Conduct compulsory site induction at the temporary site compartment prior to the construction
site entry for site visitor or inspector.