16 Construction
16 Construction
l
620 15 Route selection and detailed line design
15.49 Fleckenstein, K.; Rbiem, W.: Waldüberspannung und Walddurchquerung. Okologische 16 Construc tion
und landschaftspflegerische Aspekte beim Freileitungsbau ( Crossing above forests or
aisles through forests. Ecological and landscape aspects in case of overhead lines). Reports
of ANL, 1991
cases with hydraulically-operated cranes installed on the lorries. Conductor reels are
transported by means of self-loading transport trailers. The hydraulic pressure for the
lifting equipment is provided from a tractive engine to the trailer.
16.2.1 Means of transport All existing fences that have to be opened for work needs or future maintenance should
be recomposed or protected with gates, gateposts or cattle-guards, under an agreement
Due to the extended length of a line, transportatíon gains high importance when con- with the owner. Fences for crossing railways or highways are to be made with the
structing transmission lines. Concrete aggregates or ready-mixed concrete, considerable relevant criteria of the crossed ways.
quantities of reinforcement steel, soil excavation, material for planking and shuttering In order to interrupt the electric continuity of conducting material, barbed-wire or
and concrete formwork, driven piles, setting templates, tower parts, reels with earth flat-wire fences running para.lle! or crossing a power line have to be sectionalized and
wires and conductors, insulators, fittings as well as the construction equipment need to earthed before conductor stringing.
be transported to or from the individual support sites, sometimes in an undeveloped
terrain without access roads. An optimum organisation of the transport, therefore, is
decisive for an economically successful implementation of a project. 16.3 Construction of foundations
For construction of transmission lines, vehicles with four-wheel drive, cross-country
16.3.1 Introduction
gear and differential blocking are used in most cases: Lorries, unimog and tractors.
On surface with peat or sand, the wheel diameter should be as large as possible and The construction of foundations should be considered already when selecting and plan-
low pressure pneus with a large surface area should be used; for special cases, vehicles ning the type of foundation taking care of the soil and terrain conditions as well as of
equipped with tracks are used. the access to the individual tower sites. The construction of foundation types typically
In steep terrain not accessible for lorries, e. g. in high mountains, the material is trans- for transmission lines will be discussed in the following clauses.
ported either with ropeways or by helícopters to the individual tower sites. For rope-
ways, designs are used which consist oflow-weight components easily to be transported, 16.3.2 Concrete foundations black and slab foundations
quickly installed and remaining reusable after being dismantled (Figure 16.2). The ex-
pensive but versatile usable helicopter is as well qualified for transportation of trans- To start the excavation oí pits for stepped concrete foundations, slab foundations or pad
mission line materia.Is. However, the relatively high costs, the limited load capacity and and chimney foundations (see clause 13.4.4.2), the foundation pits are surveyed at the
the sensitivity on weather ask for a detailed planning of helicopter disposition. individual tower site and pegged out. Concerning excavation, the following types of soil
Loading and unloading activities are predominantly carried •out by cranes; in most can be distinguished:
Normal soíl, comprising clay, silt, sand and their combinations, including rocky
fragments which are easy to be removed.
- Decomposing rocks, presenting pebbles or grave! and requiring pick mattock or
even a big compressor for their removal.
Loose stones, comprising rocky terrain whose stones have such sizes and dimen-
sions that high gear force is required for excavation.
- Sound rocks which require very high gear force or explosives.
- Soíl 1.mder water and swamp terrain.
Hydraulic excavators are preferably utilized for the excavation in the first category.
In heavy soils of the second and third category, excavators with back-action shovels
having a high gear force are adopted. To loasen rock characterized by the fourth cate-
gory, pneurnatic hammers, heavy excavators with hydraulic hammers or explosives are
necessary. Here, anchor foundations are advantageous, requiring a minirnum of excava-
tion for the concrete muff only. In terrain of the fifth category, driven piles should be
preferred which do not require excavation.
The foundation pits should be secured against collapse and inadmissible entering ac-
cording to labour safety standards [16.1). The protection is carried out by a vertical
planking with horizontal shuttering using timber or steel. In case of steel reinforced
foundations, a 50 to 100 mm thick !ayer of lean concrete is placed to achieve a subface
keeping the reinforcement clean.
Figure 16.3: Earth drilling rig mounted Figure 16.4: Piling rig with a diesel-
After hardening of the lean concrete, the reinforcernent is installed so far as necessary on a crawler track chassis operated hammer
according to the design drawings, and the leg member stubs or tower bodies are installed
and adjusted. The concrete is placed !ayer by !ayer (see clause 16.3.7.5) and compacted.
The concrete Jormwork is installed in case of stepped or pad and chimney foundations diameter of 1,50 m mounted on crawlers excavate the soil at depths up to 8,00 m.
according to the progress of work. After ending the stipulated periods for concrete After the cylindrical borehole has reached the designed depth, an expansion in form
curing, the concrete forrnwork and pit shuttering can be removed and the open space of a truncated cone can be produced by means of an undercutting device. Augerbored
of the pit is filled in by excavated soil and other material. foundations are equipped with reinforcement steel to provide for tensile forces and
Before beginning the backfill, the water and mud eventually present in the pit should bending moments acting on the foundation when loaded by lattice towers or poles.
be removed. In general, the soil at sites where concrete foundations are installed in Prior to placing the concrete, the reinforcement is installed in the borehole.
excavated pits, can be used for backfill. However, the backfill should be free of roots, The borehole needs to be secured against collapsing. This can be achieved by a protec-
organic material and/or waste. The backfill should be carried out and compacted at tive casing or by installing the reinforcement and placing the concrete immediately after
layers approximately 0,20 rn thick, considering also the line owner criteria. If the exca- augering the hole. In this case, the borehole is filled up with concrete to such an extent
vated soil is not suitable for compaction, other material should be imported. The main that enough space is left for installing and adjusting the tower stubs. Since the foun-
target of backfill is to achieve soil characteristics close to those of the natural soil. dation pit is completely filled up with concrete, the excavated material is distributed
Compaction should preferably be made by motor-driven hammers. If they are not on the tower site or carried to a damp.
available, manual compaction equipment with a weight of about 20 kg is acceptable.
The backfill services, once begun, should be completed up to the surface leve! at the 16.3.4 Driven pile foundations
same day. If this is not feasible, it is necessary to scarify the superficial layer of the
existing backfill, before continuing to set new layers up to the completion of the work. 16.3.4.1 Common rules
Compaction of soil above concrete bases should begin not before 24 hours after placing Driven pile foundations (see clause 13.4.4.5) are often adopted in case of low bearing
the concrete. soils or a ground-water table close to the surface. The conditions of an overhead line
Compaction should be carried out thoroughly in arder to achieve characteristics of the project impose severa! special requirements on the pile dríving device (Figure 16.4).
backfill as close as possible to those of the undisturbed soil. The residual excavation Its weight should be as low as possible with respect to the mobility and cross-country
material is distributed on the tower site or carried to a damp. In case of an inclined suitability. On soft soil surfaces, the crawler tracks need to be equipped with wide and
terrain, special care needs to be taken that the required soil surcharge will be achieved. long tracks to attain a low soil pressure. To achieve a short period of time to move the
pile driving device from one site to the next, the piling rig with the hammer should
16.3.3 Augerbored foundations be easily erected and dismantled. The rig should permit rakes up to 250 mm/m. Its
height should be tall enough such that 14 to 20 m long piles can be driven. The action
Auger-bored foundations (see clause 13.4.4.3) require stable soils which can be augered. weight of the drop hammer should approximately be equal to the weight of the piles to
For the excavation of such foundations, earth-drilling rigs are used which are mounted be driven.
on cross-country vehicles with wheels or tracks (Figure 16.3). Earth-drilling rígs should During pile driving, the position of the pile, its deviation, distorsion and penetration
reach the tower sites without extreme effort. Augers or split buckets with a maximum as well as its rake have to be monitored and controlled. The driving process is recorded
628 16 Construction 16.3 Construction of foundations 629
,... ~
o
0,0 0,2
~
0,4 0,6
----
0,8 1,0 1,2
k
'> ,,,. ...
pile2
Cement
- Filling of ali voids in between grillage members with friable material, e. g. sand.
Cement is a hydra.ulic bínder for mortar and concrete. When mixed with water, cement
Alternatively, the grillage base profiles are cast in concrete, if specified.
hardens at the a.ir and is capable doing so under water. The hardened cement paste
- Then, backfillin.g needs to be carried out carefully without damaging the steel
formed such is water resistant. The standards ENV 197 [16.5] and DIN 1164 [16.6]
parts. Therefore, mechanical backfilling is not advisable. In.stead, the backfill is
apply for cement. ENV 197 distinguishes between three ma.in types:
placed in ma.nually.
Compaction of ba.ckfill is carried out with a pneumatic hammer or by a cornpa.ctor - CEM I: Ordinary Portland cement,
having a weight of a.t least 10 kg. lt is preferable to use the same soil for backfilling - CEM 11: Portland iron pulverízed fuel-cement, Portland ash cement, Portland
as removed during excavation, if suita.ble. The layer thickn.ess for ba.ckfill should limestone cement,
be aroun.d 0,20 rn. - CEM III: Blast furnace cement.
- It is recornmen.ded to carry out the ba.ckfill until a height of about 0,30 rn above Cement is offered with special features such as "LHPC" for low-heat Portland cement,
the ground leve], in arder to avoid water accumulation around the foundation. "SR" for high-sulphur-resisting cement and "LA" for low a.lcali cement a.nd wíth dif-
Grillage foundations ha.ve been successfully used for lines in less corrosive soil conditions fering strength classes.
and for towers with relatively low foundation loads. Ordinary Porlland cement with the strength classes 32,5 or 42,5 is used predomina.ntly
for overhead line foundations, whereby the nominal strength after 28 days will be at
least 32,5 N /mm2 or 42,5 N /mm 2 , respectively. The letter "R" (rapid) added to the
16.3.6 Anchor foundations strength cla.ss refers to an early strength. For ordinary Portland cement, the initial
setting time may not be less than 60 minutes (a.t 20ºC) according to [16.6] after adding
Tra.nsmission line towers at sites with rock subsoil can be erected on foundations using the water. The concrete has to be placed within this period of time. In case of cernen.t
tensile anchors, if the rock complies with the classifications WO and Wl accordin.g to a.ccordin.g to (16.5], the setting may start already after 45 minutes. The start of setting
Ta.ble 13.8 characterized as not to be loosened manually. Special anchors are a.dopted can be delayed by admíxtures, e. g. calcium sulpha.te.
for the stay wires of guyed towers.
Cement takes up humidity and carbon.ic acid from the air resulting in a strength re-
The drillings into the rock are carried out by rock drilling rigs which adopt rota.tional duction. Therefore, the cement needs to be protected aga.inst these impacts during
drillin.g, beat drilling or beat-rotational drilling methods. For transmission. !in.es, the transport a.nd storing (see [16. 7], da.use 2.1.3). Cement used for overhead line construc-
beat drillin.g rigs usin.g compressed a.ir for rinsing out the material are used. Drilling tion should not be older tha.n three months.
diameters up to 120 mm can be achieved.
To transfer the loa.ds from the anchor to the subsoil, the borehole together with the
installed anchor bar is cast with mortar. Mortar premixed by the producer or site-mixed Aggregates
mortar with admixtures can be used. The borehole diameter should be 40 mm larger For concrete aggregates, ENV 206 [16.4] refers to national standards or project spec-
than the nominal diameter of the anchor bar to achieve complete covering of the anchor ifications. Aggregates accordin.g to standard requirements as specified in DIN 4226-1
bars by mortar as well as the required resistan.ce and suflicient corrosion protection. [16.8] are sufficient for overhead lines. The compressive stren.gth is an essential property
Spacers are required to guarantee the necessary concrete coverin.g. of the concrete. It will be achieved if the compressive strength of hardened cement paste
The tensile strength can be tested after suflicient hardening of the mortar. When using and aggregates is higher than the concrete compressive strength envisaged. In practice,
premixed cast-in rnortar or site-mixed mortar with admixtures for an early strength, the compressive strength of the aggregates is higher tha.n that of the ha.rdened cement
testing can be carried out already a.fter a few days. According to common practice, one paste and, therefore, n.ot decisive for the concrete strength. The compressive strength
anchor is tested for each individual foundation. The anchors are connected to the tower of concrete is not much affected by the strength of the aggregates unless they were very
stubs by means of a steel-reinforced concrete muff. weak.
16.3 Construction of foundations 633
632 16 Construction
100~----------------------0 Any components of organic origin, sugar, sulphates and chlorides affect the concrete
quality negatively in different manners and should be avoided. Reliable limits and
Mass-%
verification methods are stipulated in [16.8] and [16.10], respectively.
According to ENV 206, Table 4, requirements on the composition of the concrete con- Table 16.3: Requirements on standard-mixed concrete C20/25 depending on exposure
ceming mínimum cement content and maximum water-cement ratio, on the type of conditions according to ENV 206 [16.4] and on concrete without suitability test according
cement, e. g. cement with sulphate resistance, and for coatings to protect the concrete to DIN 1045 [16.9]. Maximum particle size 32 mm, cement according to strength class 32,5
in direct contact with aggressive media (exposure condition 5 c) result for the individual E1'N 206 DIN 1045
exposure conditions. National standards may be used until ENV 206 will be mandatory Condition Water/ Cement Gradíng Water/ Cement content for consisten.ce class
of cement content curve cement Fl/Cl/Sl F2/C2/S2 F3/C3/S3
approved. According to [16.9], concrete complying with the requirements for exposure
exposure ratio kg/m3 ratio kg/m 3
condition 2 b (concrete for externa! application) should be used for overhead lines.
2a 0,60 280 No ínformation
2b 0,55 280 A/B 0,6 300 2 ) 3202 ) 3502 )
16.3.7.4 Ready-mixed concrete B/C 0,6 320 21 350 2 ) 380 2 )
5a 0,55 2803 ) n. p.'l n. p.'l n. p.'l
Ready-mixed concrete is prepared in a concrete plant, mixed in the plant or on a truck 5b 0,50 300 3 ) ll. p_1) n. p.'l n. p.'l
mixer and delivered to site in a condition ready for placing. Ready-mixed concrete 5c 0,45 300 3 ) n. p.') n. p.'l n. p.'l
presents the most economic solution for many overhead lines, complying reliably with ,¡ Not permissible without suitabilíty test
the quality and testing requirements. In [16.4], the responsibility between the construc- 2) Concrete for externa! applícations accordíng to DIN 1045, 6.5.5.1 - Table 4
tion company (user of concrete) and the producer of the concrete is controlled with 3)In case of a sulphate content above 500 mg per kg water or above 3000 mg per kg soil, sulphate
reference to the following types of order: resistance cement needs to be used
Prescribed mixture: The concrete composition and the aggregates are specified
by the construction company. However, it is a prerequisite that the specifications valid for a project permits the use
Design mixture: The concrete producer selects the aggregates and determines of standard mixtures.
the concrete composition. A mix desígn offers the most economic solution in case of larger concrete quantities
For overhead line purposes, mostly design mixtures are selected from the concrete type as required far overhead line construction sites. The mixture of the concrete should be
list of the producer, considering the following criteria: specified based on suítability tests or on experience with comparable conditions. The
Strength classes: C20/25 or C30/37 or others; special conditions concerning thc aggregates available on the construction site need to
- Maximum particle size of aggregates: 32 mm or others; be considered to ensure that the required characteristics of the concrete will be met.
- Purpose of use: Reinforced concrete, environmental conditions, exposure condi- For many over head lines, the exposure condition 2 b (humid environment with frost)
tions: see clause 16.3. 7.3; according to [16.4] is relevant. The concrete strength class C20/25 and a maximum
- Workability: Consistence, admixtures in case of long transport distance or placing particle size of 32 mm for the aggregates are provided far this application. For a superior
periods, ability for pumping, fresh concrete temperature; workability, plastic consistence, e. g. a consistence with a spreading index of 370 to
- Type of cement: Special climatic conditions, special requirements concerning pro- 390 mm, should be aimed at.
tection against chemical attack. According to Table 16.3, a cement content of 280 kg/m3 is necessary according to ENV
The construction company should check the delivering notes in view of conformity with 206 [16.4] without any special requirements on the strength class and type of cement.
the order and the transport period befare unloading on the construction site. During The water-cement ratio may reach 0,55 at maximum according to a water demand of
unloading, the consistence should be checked visually or by tests in case of doubts. 280·0,55 = 154 l. The grading curve may be between the lines A32 and C32 according to
Figure 16.7. According to Figure 16.8, a cube strength of 37 N/mm 2 can be expected
under these preconditions, using a cement with the strength class 32,5. However, to
16.3.7.5 Site-mixed concrete
achieve a consistence range F2 with a water demand of 154 l/m3, a finess index of
Mixing of concrete on site requires a mixing instruction which can be obtained from: approximately 5,0 is required according to Figure 16.9. Therefare, the grading curve
- Specifications stipulated by the line owner or by project specification. These stip- needs to be within the range A/B. This can be achieved with 600 kg/m3 aggregate of
ulations should be checked on compliance with the mínimum requirements of the the particle size 0/4, 800 kg/m3 of the particle size 4/16 and 600 kg/m3 of the particle
relevant standards. size 16/32.
Use of standard-mixed concrete, e. g. according to DIN 1045 (Table 16.3), if this The example demonstrates that with standard mixtures according to ENV 206 the re-
is permitted for the individual application. quired properties cannot be securely achieved. Therefore, a verification of the stipulated
Selection of aggregates and composition of concrete according to the mix design properties should be carried out.
and verification of the required properties of fresh and hardened concrete. According to DIN 1045 [16.9], a standard mixture without suitability tests for the
Mixtures stipulated by a line owner aim at achieving the desired quality without much consistence range F2 and far the exposure condition 2b is required as follows (Table
care on economics. They take into consideration any uncertainties possibly occurring 16.3): Mínimum cement content 320 kg/m3 with a cement strength class 32,5; water-
at overhead line construction sites and assume grading curves with high water demand cement ratio at maximum 0,6, that is 320 • 0,6 = 192 l water; grading curve within the
which may not care enough on the particle size distribution of actually used aggregates. range A/B.
Concrete may be produced followíng prescribed mixtures without suitability tests ac- Under these conditions, a strength of 35 N/mm2 tested at cube results from Figure 16.8.
cording to [16.9]. Standard-mixed concrete should comply with the mínimum require- In case of 192 1/m3 water, a finess index of 3,4 is required for the consistence range F2
ments accordíng to Table 16.3. The application of standard-míxed concrete is advan- according to Figure 16.9. For this water and cement content, ali types of aggregates
tageous if low concrete quantities are necessary or a tight schedule requires its use. having grading curves within the range A/C can be used. The specified properties can
be safely achieved with the standard mixtures according to [16.9]. Backfilling of the excavation with slightly humid material immediately after re-
If no other stipulated properties require the use of cement according to the strength moving of the formwork and planking;
class 32,5, cement according to the strength class 42,5 should be selected. The concrete Spraying of curing agents which form a protecting film.
strength will be increased and the mínimum cement demand can be reduced by 10 %. The required period for concrete curing amounts between two and ten days according to
Cement with both strength classes is offered at the same price on the market. (16.4] and depends on the development of concrete strength and on the environmental
conditions such as sun radiation, action of wind and air humidity. Curing the concrete
16.3.7.6 Handling and placing the concrete may also be necessary to protect the concrete against heavy rainfall, flowing water, a
too rapid cooling or freezing at low air temperatures. At temperatures of 10 to 20ºC,
Placing the concrete requires a clean and so far as possible dry excavation pit. Water the concrete reaches 80 % of its final strength after a period of 14 days; then the tower
should be pumped out or the concrete has to be placed as under-water concrete. erection can start.
The reinforcement may not be polluted by soft soil subfuces. Therefore, a subgrade
layer of lean concrete should be provided before installing the reinforcement. Mixing 16.3. 7.8 Methods for verification of concrete properties
of soft soil and concrete would affect the concrete quality and needs to be avoided.
The concrete formwork should withstand the expected load. It should be clean and Compressive strength
coated with release agents not contaminating the reinforcement. The position of the Standard [16.4] requires a test series of the concrete compressive strength according to
reinforcement may not be dislocated when placing the concrete. To avoid such a dislci- (16.17] and [16.11] to be carried out after 28 days at 300 mm tall cylinders with 150 mm
cation of reinforcement, thick timber planks should be used to walk on. diameter or at cubes with 150 mm length of edges. The test specimens are stored under
Ready-mixe,d concrete should be placed without interruption after delivery. In case of water at 18 to 22ºC before testing. Standard [16.9] requires a test series according to
concrete without retarding admixtures, the transport and placing period at 20ºC may [16.18]. The test specimens are stored seven days under water and 21 days at air with
not exceed 60 minutes in case of cement types according to German standards or 45 a humidity of 50 to 70 % and 15 to 22ºC temperature.
minutes in case of cement types according to EN standards. The differing dimensions of the test specimens affect the testing results. For compar-
The workability of concrete depends on its consistence. Plastic concrete, e. g. according isons, the compressive strengths obtained from differing test specimens can be con-
to consistence range F2, can be compacted by vibrators. During transportation and verted using factors gained from experience. Assuming the storing conditions accord-
placing, the concrete may not demix, especially honey combs may not be generated. ing to [16.9], the following relations for the strengths apply: /3cube200 = 0,95 /Jcubel50i
Elephant trunks, craning skips or chutes need to be used in case of falling heights above /3cube200 = 1,18 /3cyl and /3cubel50 = 1,24.Bcyl, where .Bcube200 is the compressive strength
2,0 m, column-type structural components with a cross section of 0,5 m times 0,5 m gained at a test cube with 200 mm length of edges, /3cubel50 that at a test cube with
excepted. 150 mm length of edges and /3cyl that gained at a standard cylinder.
The concrete should be placed such that after compaction no hollow spaces will be With increasing penetration of humidity, the friction forces within the texture decreases
left below anchoring sections or cleats. The concrete is placed in 0,5 m thick layers Therefore, it can be concluded that also the storing conditions affect the test results.
and compacted by intemal vibrators. The interna! vibrator should be dipped rapidly Test results gained from the procedures according to EN or DIN standards cannot be
into the concrete at distances of 0,4 to 0,8 m and pulled out slowly depending on compared directly. Test results gained from testing a cube with 200 mm length of edges
the working principie of the vibrator. The vibrator should penetrate approximately and processed according to specifications given in DIN 1048 have to be reduced by a
0,15 m into the bottom layer which was previously compacted, to achieve a sufficient factor of 0,92 according to [16.19], page 5.6 to gain data which can be compared with
bonding between the individual layers and avoid unscheduled construction joints. When compressive strengths obtained from tests on cylinders.
pulling out the vibrator, the hole within the concrete should close itself. The vibration
procedure should be stopped when no more air bubbles escape at the surface. A too Consistence
long vibration process should be avoided since otherwise a watery concrete mud would To assess the consistence, the spreading index test according to ISO 9812, the com-
be formed at the surface. paction test according to ISO 4110 or the Slump test according to ISO 4109 are fre-
Rain as experienced in Central Europe <loes not affect the concrete quality to a notice- quently used. Table 16.2 represents informationrelevant for overhead lines. The assess-
able extent. However, very heavy and enduring rainfalls may result in washing off the ment of consistence according to the specified approaches does not completely coincide.
cement at horizontal and inclined surfaces and in demixing of concrete layers close to That means, that the consistence range F2 is not completely equivalent to the class
the surface, thus increasing the water-cement ratio. Therefore, the concrete should be S2. In Central Europe, the spreading index or compaction test is given priority, while
adequately protected in this cases. outside of Europe the Slump test is most frequently adopted.
16.3.7. 7 Curing the concrete 16.3.7.9 Quality supervision and quality management
The concrete needs the water content for hardening, therefore a curing of freshly placed According to [16.4],quality supervision comprises all measures, decisions and tests which
concrete is always necessary, e. g. to avoid drying out. are carried out corresponding to stipulations for concrete with the aim of guaranteeing
Methods of curing the concrete are: the specified requirements.
- Continuous spraying with water; The quality supervision can be divided into:
- Application of humid covers; - Contractor su.pervisíon (production supervision): Contractor supervision com-
- Keeping the formwork up to the end of the curing period; prises checks and tests including the evaluation of the test results. The contractor
640 16 Construction 16.5 Setting of tower stubs or bases 641
supervisíon needs to be carríed out by the construction manager, the subcontrac- adjustment of leg member indination point of reterence p!anview A • A
1 tors and supplíers, whereby each of these entities is responsible for its range of
tasks. T
Quality verification: Quality verification comprises measures and decísíons A
based on stipulated criteria to assess conformity with stípulated requirements.
1 Vv'ithin this group are the quality verification by independent quality control
organisations and/or acceptance tests taking test specimens. For overhead lines connection
using concrete according to the strength class C20/25, the qualíty verification can ot struts.
iower centre
be carried out by the construction company, since in case of site-mixed concrete
only negligible reliability related risks are given.
leg member stub
A documentation according to the rules is an essential part of quality superv1S10n.
Retraceable records need to be made for which the construction manager is responsible.
The tests need to be recorded and approved with respect to the necessary number of
tests and the compliance of the results wíth the stipulations. The chronologícal progress adjustable struts
1/,
of the individual activitíes like installation of the reinforcement, placing the concrete to ground
and curing have to be documented. For this purpose, the weather conditions, unusual
events and special mea.sures, if any, to reach the stipulated concrete characteristics are
recorded, e. g. protection against frost.
Suitability tests belong to the responsibility of the contra.ctor's supervision. Prior to Figure 16.10: Example of an equipment for installation of individual stubs
usíng the concrete, the concrete composition is verified which is needed to reach reli-
ably the requirements on the concrete with the aggregates and the conditions at the on both sides. Low earthing resistance are achieved in cohesive soil. Stones or coarse
construction si te. gravel directly at the earth electrode increase the earthing resistanceto a large extent.
In case of ready-mixed concrete, the manufacturing plant verifies the suitability if con- Earthing rods are driven manuaily or by tools as deeply as possible into the soil. In
crete is delivered according to a design mixture. Delivery notes and consistence need case of shallow foundations, they can be driven into the soil from the excavation pit
to be checked visually when the ready-rnixed concrete is delivered to site. subface before starting of concrete placing.
For site-mixed concrete, a series of tests concerning the constituent materials of con- The earthing resistance are measured by means of an earth tes ter (see clause 5.11). If the
crete, tools and production of the concrete have to be carried out according to (16.4]. required earthing resistance is exceeded, the earthing properties need to be improved
Also for production, transportation, placing, compacting, curing and quality supervi- by additional earth electrodes. To achieve low transition resistance, metallic bright
sion of concrete quality management programs are increasingly established or required. connections between earth connectors and towers should be envisaged and supervised.
These contain requirements, mea.sures to comply with the requirements, tests and spec-
ifications for documentation. Within these categories are:
Requirements on constituent materials (cement and aggregates);
16.5 Setting of tower stubs or bases
Requirements on composition and properties of the concrete;
16.5.1 Methods and tools
Type, extent and documentation of tests for verification that the requirements
are complied with; The stubs or bases of lattice steel towers need to be set in place before establishing the
Description of methods for production, transportation, placing, compaction and connection with the foundation. There are two procedures adopted:
curing of the concrete; - The stubs are set by means of a setting template or with the tower base.
Methods for documentation. - The stubs are set individually and independently of each other.
Quality management programs have proven their adequacy for a qualitatively convinc- In case of shallow foundations, the stubs are arranged on concrete blocks in the ex-
ing and economic execution of concrete works (16.20]. cavation or on a layer of lean concrete. Differences in heights are balanced by placing
steel plates underneath the stubs or by adjustment of bolts arranged at the lowermost
cleats at the stubs.
16.4 Installation of earthing In case of augered foundations or piles, the setting templates are supported and adjusted
by jack stands. The stubs are connected to the setting templates hanging into the
Where necessary, transmission line supports are equipped with earthing installations borehole or a.hove the pile head. The tower axis should intersect the line axis at the
to conduct failure and induction currents as well as currents from lightning strokes into tower witness pillar. The tower base or setting template can be adjusted by means of
the earth (see Chapter 5). For this purpose, horizontally arranged electrodes, named a theodolite. Reference marks at the template or tower base can ease this activity.
counterpoises or earthing rods can be installed in the soil. Settíng of stubs individually has proved its qualification especially in case of wide-spread
Horizontal/y armnged electrodes can be installed radial oras rings in manually or tool- towers and towers with grea.t differences in the leve! of the individual leg member foun-
assisted excavated trenches in depths between 0,6 and 1,0 m. The earthing conductor datíons. Each índividua.l leg member stub is separately adjusted to the required position
or strap is conductive connected to the tower leg members. Earthing straps should be and fixed there. Thereby, the efforts for manufacturing, transport and expensive instal-
installed endup in the trench such that the back-filled soil touches the earthing strap lation and removing of wide and heavy setting templates can be waived. An equipment
a) where
rm is the horizontal displacernent at the top of the structure (Figure 16.11 a) and
hT the reference height above the base of the structure.
1,8
%
1,6
"' ~i
"'
1,4
i
1
1,2
1 ¡'\_
g 1,0 1
i
"' - -
.S --1--- -- -- ~
~ 0,8 ¡ 1\
i í [\
0,6 '
1 ¡~··
1 !!
0,4 1 !
0,2
1
' 1\
1 Figure 16.12: Inclination of an angle strain
1 \
90 100 110 120 130 140 150 160degreel80 tower given as a percentage of the tower width
Une angle - - - ( example)
Figure 16.13: Tower erection by elevation
tilting due to the bolt slippage within the joints should be considered. An assumption
of 4 mm slip per joint has been proved as correct. An additional inclination of 0,1 to 16.6 Erection of supports
0,2 % of the tower height takes care of visual amplification of tower inclination dueto
tension insulator sets and the deformatíon of the foundation. In Figure 16.12, the data 16.6.1 Introduction
for determination of inclination depending on the line angle are shown for a 110 kV line.
The inclination is expressed as the increase in level of the compr-ession loaded stubs The method used for erection of supports depends on design, weight and dimensions of
relatively to the tower width at the joint above ground surface. towers or poles, accessibility of tower sites, available tools and machines and qualifica-
The diagram in Figure i6.i2 appiies for a tower instaiied in the bisectrix of the angle. tion of the erection staff. The method has to be selected with respect to economics as
From this diagram, also the necessary inclination of towers can b,e determined which well. Assessing these aspects, lattice steel towers are erected piece by piece with pre-
are not arranged in the bisectrix or are loaded by differing conductor tensile forces. For assemhled walls, with preassembled sections or completely assembled on ground and
this purpose, the acting forces are divided into components in parallel to both tower
axes. For these components, the equivalent line angles can be determined which would lifted or tilted then.
lead to the same horizontal forces. For these fictitious line angles, the inclination as
a percentage of the tower width can be taken from the diagram in Figure 16.12. By
multiplication with the tower widths, the portions in increase of stubs of the individual 16.6.2 Assembly and erection by elevation
tower legs can be obtained.
Low-weight and short self-supporting lattice steel towers are frequently assembled by
elevation. The activities are started by erection of the legs, continuing with the first hor-
Example: For a line angle of 145º anda tmver wídth of 6,30 m, the increase of stub elevation
should be determined from Figure 16.12. izontal diaphragm as base for the erection of the supports. The erection then proceeds
For 145º an inclination of 0,86 % results from Figure 16.12, yielding a difference in height of by installing sets of preassembled or individual members. Hoisting of parts is carried
6,30 • 0,86 · 1000/100 = 54 mm. out manually assisted by winches and trucks. The hoisted members are rendered to the
In case of solid wall steel poles with slip joints, the publication [16.21] proposes to linemen at the mounting position to insert them in due place and tighten the bolts.
consider a tilting of 0,4° per joint at the maximum load. In [16.2 2], the deformation After completing a tower section, the assembly of the following section can start. In this
of solid wall steel poles equipped with slip joints is reported. The poles were erected phase, bolts are only partially tightened just enough to keep the structure in position.
with the predetermíned inclinations and then checked with respect to the position of The final bolt tightening is carried out when revising the assembling. In Figure 16.13,
the crossarms after finalizing conductor stringing. From this study, it can be concluded tower assembly by elevation method is shown. Guyed towers as well can be erected by
that independently of the loading and the pole type a tilting of 0,3 to 0,4° should be elevation making use of provisional guys. Here, winches are generally adopted.
considered for ea.ch joint. From these measurements, no conclusion on the inclination of
the foundations could be drawn. Since an inclination against the tower loading seems
16.6.3 Tower erection using a crane
always to be more expedient, the inclination of the foundation should be considered
by an angle of at least 0,1° unless locally more unfavourable subsoil conditions would Tower or pole erection by means of a mobile crane suitable for going cross-country is
advice to adopt higher values. advantageous if the support sites can be accessed without dif:!iculties at all weather
conditions. Single poles made of wood, concrete or steel tubes can be lifted by a crane
onto the foundation or into an excavation. By the help of a crane, lattice steel towers
having heights up to 30 m and widths up to 2,5 m can be erected in one piece. A suf-
ficiently wide space is necessary for a complete three-dimensional assembly on ground.
Taller and wider towers nave to be erected section by section after preassembling on
ground.
646 lo Uonstruct1on
be varied by means of come-alongs similarly as ín case of gin pole arranged outside the
tower. The hoisting rope is guided from the hoisting winch over a pulley installed close
to the ground surface in the centre of the tower and through the gin pole and a revolving anchor to ground
for keeping off
pulley at the gin pole head to the load. By this procedure, the tower components can
be assembled piece by piece or face by face.
With the work progress, the gin pole must be lifted to a higher section. For this purpose,
the head anchors equipped with the come-alongs are first fixed to brackets installed at
the tower section just assembled. Then, the lifting of the gin pole is carried out by
means of a hoisting rope fixed at the foot component of the gin pole. This hoistíng rope
is guided over a pulley arranged at a rope between two opposite leg members of the just strop with chain hoisl
assembled section. During lifting of the gin pole, the head anchors are released such to I
keep the gin pole in a vertical position as far as possible. When the foot anchors can
be arranged to the same brackets as the head anchors, the new position of the gin pole
is reached.
By means of a gin pole arranged in the centre, towers with large widths and tall
heights can be erected "ithout any anchors to the ground. Therefore, this method has
gained priority during the last years, especially for erection of self-supporting towers
consisting of a tower body and severa! crossarms. As an example the suspension towers
of the 380 kV crossing over the river Elbe with a height of 227 m and approximately
1000 t weight should be mentioned [16.23]. The 40 m long gin pole hada load capacity
of 100 kN.
Using the same procedure, the suspension towers of the 500 kV crossing over the Suez
canal [16.24] with a weight of 710 t cach aI1d a height of 220 mas ,ve!l as the suspension
towers of the 380 kV crossing III over the Bosphorus [16.25] (weight 450 t, height 160 m)
were erected. In Figure 16.16, the erection of a suspension tower of the crossing over
the Suez canal is shown .
\ I
\ I balance
\ I I \
I \
\ 1 / \
\ pre-assembred lower masts/ \
\ I \
I \ aUXmary mast
I \
I \
-{- I \
I \
I ting \ I \
I \ I \
I \ I \
I \ I \
I \ I \
I \ I \
I \ I \
I \ I \
I I \
I 'INinch \ I \
I truck , I \
I \ I
.I =
I \\
I.
-J,~~~;---winch
7, 777,
A 1, A
guyanchor auxiliary base
Figure 16.20: Arrangement of tower site with Figure 16.21: Lifting of preassembled guyed
preassembled guyed tower tower with auxiliary mast
~
~
guy-wires
Figure 16.18: Hoistíng of a crossarm Figure 16.19: Tower erection usíng a heli-
copter
la
from the storage area to the tower sites where they are installed continuously without Figure 16.22: Erection of guyed tower with Figure 16.23: Erection of guyed tower by
any interruption. Therefore, the linemen on the towers will be active for short periods an auxiliary crossbeam by cranes cranes without auxiliary crossarm
of time only. When adopting high-performance helicopters for heavier weights neces-
sary to erect taller towers, the wake of the rotor will become so strong that working laid down for supporting the mast a.nd tra.nsferring the compression loads to the soiL
of linemen on the towers would be risky. For this case, auxiliary erection remedies are Figures 16.20 and 16.21 outline this erection method.
required which provide guidance and temporarily fastening of the tower components
flown in until the linemen can bolt this parts after the departure of the helicopter and
the auxiliary erection remedies can be dismantled again. In Figure 16.19, tower erection 16.6.6.3 Erection by cranes
by means of a helicopter is shown.
The quicker and usually cheaper method of erecting guyed towers is by means of cra.nes
of adequa.te capa.city, which picks up the assembled tower on the ground either directly
16.6.6.1 Manual method at the crossarm or a.t an auxiliary crossbeam. In Figures 16.22 and 16.23, it is outlined
For manual erectíon o/ guyed towers, the tower is assembled by elevation simílarly how the crane method is applied for erecting towers up to 40 m high (crossarm to
to erection of self-supporting towers described in clause 16.6.2. Provisional guys are ground). The cra.nes adopted should have a ca.pacity of approximately 500 kN and a
adopted for stability of the assembled sections. lifting height of 45 m. Due to the reduction of lifting capacity with height, towers higher
than 32 m require the use of a.uxilia.ry crossbeams. The pick-up point of the crane, as
well the detailed design of the auxiliary crossbea.m are made by the tower ma.nufa.cturer.
16.6.6.2 Use of an auxiliary mast
After erection, while the crane still holds the tower, the guy wires are provisionally tied
A tubular mast composed of about 5 m long modules, sufficiently high according to the to the guy anchors. The guy wires are then cut to appropriate lengths as a function of
tower to be erected is used. On its upper part, an articulated support piece is fastened the terrain slopes, and with the help of two theodolites laid down at longitudinal a.nd
which lays horizontally during the erection. At the lower edge of the mast, a base is transverse directions, the tower is positioned at the plumb, as shown in Figure 16.24.
652 16 Construction 7 16.7 Installation of insulator sets and hardware 653
line axis
control equipment of
guy wire tension
totower
l Table 16.4: Torques for bolt tightening
Bolt type Ml2 Ml6 M20 M22 M24 M27
Bolt diameter (mm) 12 16 20 22 254 27
Torque (N-m) 40 to 60 80 to 120 130 to 180 190 to 230 300 to 340 475 to 610
tower axis Alternatively, bolts should be punched on three points spaced at 120°, and protected
with anti-corrosive dyes. Alternatively, other blocking systerns can be used, as the
employment of spring washers or special glues.
/ - -
- = - = _- ~~ - ~
---
-~~~--=---:~~~
- =-:e--""'-- .......,__
'-- pullíng rope
stringing block reel stand
for twin bundle
~ PULLER SITE
" stringing of a
pilo! rope by
means of a tractor
Figure 16.28: Braided pullíng ropes Figure 16.29: Jointing of conductor and pull-
ing rope
pilot rope
puller
stringing the conductors even over strain towers. For this stringing procedure, the same
TENSIONER SITE
lengths are chosen for the pulling ropes as for the phase conductors. However, it is
Figure 16.27: Stringing of a twin bundle conductor necessary to establish tensioner and puller sites regardless the terrain and the sites of
the strain towers. The ends of the conductors are anchored to ground after stringing at
the tensioner site as well as at the puller site. A line crew operating independently of the
To prevent dangerous overvoltages that rnay result from electrostatic induction by stringing procedure adjusts the conductors and terminates them at the strain towers.
parallel energized lines, safety measures should be adequately defined during conductor In densely populated areas like Central Europe, the terrain and the land use do rarely
stringing. permit to plan and constmct lines with long straight tensioning sections. There, it
Before stringing, dynamometers, earth meggers and other equipment should be checked is more appropriate to string the conductors tensioning section by tensioning section
and adjusted. from one strain tower to the next. Behind each strain tower at the end of a tensioning
Before conductor stringing, the contractor should present to the client, for approval, a section a tensioner or puller site is installed. The stringing operation is carried out
complete plan of distribution and unwinding of the conductor and earth wire reels along independently of the lengths of the conductors and the available pulling ropes. If the
the line, containing control spans, layout of stringing equipment, position of the joints, tensioning section Jengths are shorter than the conductor manufacturing lengths, the
provisional anchors to ground. Attention should be given to the reel lengths, aiming conductors are cut; if they are longer, they need to be extended by tension- and current-
at losing the least possible amount of cables. The ma.ximurn length of conductor to be resistant joints (see clause 10.2.4).
strung under tension should not exceed 8 to 10 km.
16.8.3 Conductor stringing equipment
16.8.2 Stringing methods 16.8.3.1 Requirements
There is no international or European standard on conductor stringing. IEC 61328 TS Conductor stringing requires special pulling rapes, stringing blocks, pullers, tensioners
[16.26) deals with installation of conductors in the vicinity of live circuits. The German and accessories. The conductor type and cross section to be installed are decisive for the
standard DIN 48 207-1 (16.27) is applicable for the stringing of overhead line conductors. design of conductor stringing equipment. The required stringing equipment depends
Phase conductors and earth wires should be installed under tension without touching on the conductor stríngíng force for which the everyday stress may be assumed as
the ground or any obstacles. Touching ground or obstacles could cause damage of the maximum. For standard conductors, the everyday stress is approximately 50 N/mm 2 .
conductors, that would infringe their mechanical and electric characteristics. Further-
more, the conductors could corrode because of chernical products potentially available 16.8.3.2 Pulling ropes
on the soil. Therefore, the conductors should run over stringing blocks suspended at
the supports, with sufficient tension to keep them clear of ground surface or obstacles. Pullíng rapes should be as far as possible twist-free. Their mínimum failing load should
For this purpose, the conductor to be unwinded is connected to a pulling rope at the be at least three times the expected stringing force. Ropes may not be used further if a
tensioner site and strung by a puller to the puller site, which can be installed sorne given number of visible strand failures has been reached. Two pulling rope types have
kilometres apart from the tensioner site (Figure 16.27). To guarantee enough clearance proved worthwhile and are mainly used:
to the ground during conductor stringing, an adequate tensile force has to be applied Bmíded rapes made of eight or twelve plaited steel strands have low twist and are,
by means of a controlled tensioner. therefore, well-suited (Figure 16.28). Loops formed during the stringing process open
In case of long line mutes with only a few angle points, it is expedient to utilize the again automatically under tension without forming a typical sharp bend within the
capacity of conductor reels to their ful! extent with respect to the production length, rope. This type of pulling rope has a relatively low filling coefficient compared with
656 16 Construction
conductor
stranded conductors. Therefore, braided pulling ropes are thicker than stranded ropes
of the same tensile strength and need a larger winding volume on reels or winch drums.
Due to their costlier production, braided ropes are more expensive than stranded ropes. conductor grip
balancing pul!ey steel wire
Compacted, mostly three-plaited-strand steel rapes are less twist-free and, therefore,
should be kept continuously under tension during the stringing procedure. The com- Figure 16.30: Running board for stringing of bundle conductors
paction of the ropes after stranding of the litzes increases their strength and the filling
coefficient, thus reducing the twisting strain. Pulling ropes compacted in this manner
need an essentially lower winding volume compared with braided pulling ropes, how- Inductive or capacitivé interference may occur on the conductors to be strung due to live
ever, are more susceptible against forming of loops and cannot be spliced because of parallel circuits which cannot be disconnected. The current to be expected, therefore,
the design made of three plaited strands. Therefore, joints and thimbles have to be should be known in advance to select suited swivels and woven wire grips. According
compressed in this cases. In Table 16.5 specífications for pulling ropes are shown. to DIN 48 207, Part 2 [16.28), woven wire grips made of steel can be used for currents
up to 160 A. In case of a higher current, damage cannot be excluded. For this case,
tempora.ry compressionjoints or speciaJ cla.mp::; for an increased current capacity should
16.8.3.3 Rope connections
be used. Application of swivels and pulling woven wire grips is standardized in [16.28]
During conductor stringing, rigid connectíons and swívelling joints are used. The first and [16.29), respectively.
type is used for jointing conductors of the same type due to the absence of any twist,
while the latter is used for jointing different conductor types to compensate the expected 16.8.3.4 Stringing blocks
twist. Rigid connectors may run over the bullwheel puller, however, swivels may not be
used such. The size of sheaves for stringing of overhead line conductors depends on the diameter
AH conductor connections applied during stringing operations should withstand three of the conductor to be strung; the diarneter of the pulleys at the groove basis should
times the maximum stringing force to be expected. They should be as slim as possible amount to at Jeast 20 times the conductor diameter. A sufficient width of the grooves
and designed with a diameter as low as possible to enable running over sheaves without should enable an unhindered passage of temporary joints Iike swivels and woven wire
being blocked there. Sharp edges must be avoided. grips. When selecting the stringing blocks, the maximum load expected due to the
Severa! types of connections can be distinguished in view of conductor stringing: conductor rollover angle should be considered as well. Therefore, it is recommended to
- Connection of two identical pulling ropes by a rigid joint; use reinforced stringing blocks at strain towers close to the tensioner and puller site.
- Connection of two pulling ropes with differing diameter by means of a swivelling Neoprene- or perlon-lined sheaves should be used to protect the aluminium layers of the
joint; conductors. The sheaves can be combined to stringing blocks for stringing of bundle
Connection of a conductor and a pulling rope by means of woven wíre grips with conductors, whereby the grooves of the central sheaves accommodating the pulling
a swivel (Figure 16.29); ropes need not to be lined.
Connection of two conductors by two woven wire grips with a rigid connector;
Connection of the subconductors of a bundle with one pulling rope by means of a 16.8.3.5 Puller for conductor stringing
running board, which equalizes the tensile forces in the strung subconductors and
stabilizes them in a horizontal position to guide the connection between pulling The pullers used nowadays for conductor stringing haul either pilot ropes or pulling
ropes and the subconductor over the multiple stringing block without a jerk. The ropes, whereby reel-type or twín bullwheel pullers are used. Reel-type pullers equipped
pulling rope and the conductors are connected to the running board by means of with a permanently integrated drum are used to string pilot or pulling ropes for con-
swivels for this purpose. Easy mobility of the hinges and pulleys of the running ductors with cross sections up to 300 mm 2 •
board and the swivels is of particular importance (see Figure 16.30). For pulling conductors with higher cross sections with adequate conductor tensile forces,
For ease, compression joints at the conductors can be installed on the ground surface predominantly hydraulically driven twin bullwheel pullers are preferred which haul pilot
directly behind the tensioner before continuing conductor stringing. The connector and pulling rope by means of two bullwheels (Figure 16.31), designed with six to ten
should be provided with a protector against bending when running over stringing blocks. grooves each for running of the ropes. The wheels having a diameter of at least 30 times
Passing of the protector, however, requires sheaves with accordingly designed groove the rope diameter are staggered by half of the groove width to each other.
dirnensions. The shape of the groove is designed such that rigid connectors to be hauled will be able
16;8.3.6 Tensioner
The conductors to be strung run over conductor tensioners which are used to hold
tension against the pulling rope and are designed preferably as twin bullwheel units.
Alternative designs adopt one wheel only which is equipped with an endlei;s shoe chain.
The conductor is guided over two bullwheels equipped with three to six grooves and
hold to tension. The diameter of the wheels should correspond at least to 30 times the
conductor diameter. The dímensions of the grooves lined with neoprene are selected
such that the thickest conductor for which the tensioner is provided can run with a
woven wire grip or a connector over the wheel.
The tensioner should hold the conductor from standstill to the maximum stringing
speed at different tensile forces continuously variable and without jerks and dissipate
Figure 16.31: Twin bullwheel puller Figure 16.32: Conductor tensíoner driven the braking heat generated thereby. This requirernents have lead to differing designs of
by an engine
tensioners which will be described hereafter.
to pass over the grooves. A brake working at the bullwheel anda clamping device, which Mechanical tensioners
doses automatically in case of a standstill or a pressure decrease within the hydraulic
system, exclude gliding of the ropes. The bullwheels of mechanical tensioners are equípped with mechanical braking units.
Behind the puller the rope is winded on a reel winder equipped with changeable reels. While in the past flexible band brakes or block brakes have been used, nowadays pre-
The hydraulic drive of the reel winder keeps the rope continuously under a tensile force dominantly disc brakes with sufficiently large discs are adopted which dissipate the
to exclude sliding of the rope over the bullwheels. The size of the reels is the same for braking energy without artificial cooling. The required braking pressure is applied
all diameters of pilot and pulling ropes. The reels, therefore, can store different rope pneumatically or hydraulically by means of a pump operated by feet or hand simi-
lengths depending on the rope diameter. E. g., in case of a rope with 24 mm diameter, lar to operation of disc brakes in automobiles.
800 m can be wound on one reel, while in case of a rope diameter of 11 mm 3 000 rn A sufficiently large rotating mass of the bull wheels equalizes the running of the me-
can be wound (see Table 16.5). chanical tensioners during starting due to overcome the higher friction coefficient at
The lineman operating the puller controls the machine by means of a portable remote standstill (adhesive friction) than during operation (gliding friction) and ensures steady
control unit. He can, therefore, chose a position where he is able to follow closely the stringing of the conductor. Mechanical tensioners are characterized by noiseless run-
running of the ropes over the bullwheels and onto the reel winder. He is located at ning, a relatively simple design and economic advantages resulting therefrom.
sufficient distance frorn the puller, such that the noise generated by the drive will not
impair too rnuch the corn.munication. Hydraulic tensioners
The running velocity depends on the load and may achieve up to 100 m/min in case of The bullwheels of hydraulic tensioners are coupled with a hydraulic pump which is
low loads and up to 50 m/mm in case of heavy bundle conductors. driven by the wheels during braking operations. The braking effect is achieved by
Bullwheel pullers offer the following considerable advantages compared with reel-type restraining the oil strearn generated by the pump, whereby the braking force can be
pullers: controlled continuously variable by means of a throttle valve. The oíl will be heated
- Due to the separation of the winder for the ropes the weight of the bullwheel by the dissipated braking energy. The heat is extracted from the oíl in a radiator unit
puller is lower. before being sent back to the hydraulic pump.
- A change of the rope type is possible just by changing the. rope reel without time-
and cost-consuming rewinding activities.
Engine-driven brakes
- The total length of the rope can be expanded as necessary just by coupling the
ropes stored on reels. The bullwheels of engine-driven tensioners as shown in Figure 16.32 are driven hy-
- When running over the bullwheels, constant stringing speed and stringing forces draulically as in case of a twín bullwheel pullers. A diesel engine drives a hydraulic
are achieved at the same driving intensity dueto the constant wheel diarneter. pump, by which the oil flow within the hydraulíc system is controlled. When pulling or
- Winding off the ropes frorn separate reels treats them with care since the ropes holding conductors, the hauling or holding force, respectively, as well as the conductor
are under a low pretension only and cannot cut into the rope layers on the reels stringing speed can be adjusted by means of the running speed of the oíl. To avoid
with the full tensile force. overspeeding during braking, the oil flow is guided through a throttle valve and decel-
Modern bullwheel pullers are equipped with an adjustable overload control, meter coun- erated, whereby the braking energy is dissipated within the oíl circuit. The oíl heated
ters, tachometers and instruments for recording the tensile force. Tensioners equipped up flows back to the hydraulic pump via a radiator unit.
with a dríving unit, also called puller tensioner, are used to hold tension against the Engíne-driven tensioners can be universally used for stringing and replacing of con-
pulling rope and are as well suited to string pilot or pulling ropes (see 16.8.3.6). ductors under everyday tensile stress. They are designated, therefore, as combined
puller/tensioner and are suited for conductor sagging as well. When combined with a
reel stand connected to the hydraulic system, the tensioner can also be used for dis-
mantling conductors, whereby the conductor is permanently kept under tensile stress
by the driven reel stand and wound up.
16.8 Conductor stringing 661
660 16 Constructio n
f = a 2 • mcg/(8H) , (16.9) where /h is the sag at a horizontal viewing line, f the target initial sag corresponding
to the temperature during sagging and h tbe vertical distance between the attachments
from which it is obtained using (16.8} oí the conductors. When checking the sag with a horizontal viewing line, the sag fh is
measured at a tower between the conductor attachment and the viewing line. At this
f = g/8 • t 2 (16.10) point, the theodolite for the horizontal sight is arranged. A check of the viewing line is
According to these formulae, the running periods of waves allow to check the sags. The possible by installing a sag batten at the opposite tower of the span (see Figure 16.35).
wave is initiated by an impact exerted by means of a rope guided across the conductor in
the vicinity of the attachment. The wave is reflected at the adjacent tower. To improve 16.8.4.4 Terminating the conductors
the accuracy, the wave is led to run three times between adjacent towers before the
After sagging, the conductor can be terminated to the strain tower close to the tensioner
running period t is measured in seconds. The subconductors of a bundle conductor
site. For this purpose, the position of the dead-end clamp has to be marked on the
have to be checked separately. Duríng this checking stage, no additional fittings, such
conductor taking account of the length of the dead-end insulator set. The dead-end
as spacers or vibration dampers, should be installed. From the period t5 measured in
clamps can be installed on a working platform arranged at the tower or on ground,
seconds for running six times the span length, the corresponding sag can be determined
whereby ~he conductor has to be lowered again.
by:
This method for conductor sag determination applies to span lengths and conductor After preparation of the dead-ends, the suspension clamps can be installed. Then the
tensile stresses as far as the approximation (16.9) is applicable. The method is inde- stringing blocks are removed. With respect of a vertical position of the insulator sets
pendent oí the conductor material. after clípping-in, the conductors are clipped-in with an offset compared to their position
In hilly terrain, checking the conductor sag by means of a viewing line inclined by the on the stringing blocks especia.lly in rough terrain. The procedure to determine the offset
angle is well suited (Figure 16.34). The angle <f; can be obtained from is described in clause 16.8.5.2. For clipping-in at the appropriate position, it is necessary
to mark the conductors at the position where they rest on the stringing blocks and
<f; = arctan ( h- 4/ + 4J(f • D)/a) (16.12) measure from that position the offset of suspension points as calcula.ted before (Figure
16.36). Clipping-in to suspension clamps can only be started when offsets have been
There, <f, is the inclination angle of the tangent at the initial sagging line (+</; above marked at all suspension sets of the tensioning section or at least the positions of the
the horizon, -</; below the horizon), a the horizontal distance between the towers T1 conductors on the stringing blocks.
664 16 Construction 16.8 Conductor stringing 665
anchoring ropes
reels, inserted to a reel winder equipped with brake, wind on the replaced conductors.
Afterwards, the winded conductor coils can be removed from the separable reels and
recycled. If the replaced conductors need to be dismantled in a reusable condition, a
Figure 16.36: Offset of the in- Figure 16.37: Line car driven stand for standardized conductor reels is used.
stallation position of a suspension
clamp
16.8.4.9 Stringing conductors with optical fibres
16.8.4.6 Installation of jumper loops Conductors with optical fibres or ali dielectric self-supporting (ADSS) cables are fre-
quently installed in overhead power lines. Stranded conductors with integrated fibres
At each strain tower, the corresponding ends of the conductors terminated at the in- are adopted as earth wires {OPGW ~ optical ground wire) and less frequently as phase
sulator sets need to be connected such that they can conduct the current. In case of conductors~ In general, the same tools and procedures are used for stringing conductors
wedge-type tension clamps, the conductor ends extend through the clamps such that with optical fibres as in case of conventional conductors. For sorne conductors with opti-
the jumper loop can be produced by overlapping the ends to be connected. The con- cal fibres, the manufacturers stipulate specific lirnits for the stringing tensile stress. To
ductor ends overlapping on approximately one third of the jumper loop length are verify the compliance with these limits, the tensile force of puller or tensioner needs to
connected by two or three parallel groove clamps. In case of conductor terminations be recorded continuously, for example by means of monitoring the hydraulic pressure.
using compression dead-end clamps, preassembled jumper loops made of conductors of In addition, the bending radii stipulated by the manufacturer and the mininmm dia-
the same type are connected to the lugs at the compression clamps. meters of stringing blocks as given for example in DIN 48 207, Part 1 (16.27] may not
Ali clamping positions at the jumper loop connections should be metallically clean to be disregarded.
ensure low electric transition resistance. For any type of jumper loops, the designed During the stringing procedures, the conductors with optical libres may not be handled
distances between adjacent loops and to the tower structure need to be obeyed also in with conventional working grips but only with adjusted tension-proof armor rods (see
swung conditions. clause 10.2.2).
16.8.5.2 Position of the conductor on stringing blocks and in clamps Figure 16.41: Data to
-..._..,_=-~H,-_- - + - - - - - - - - - - + - - ~
determine the conductor
The mechanical behaviour of conductors suspended on stringing blocks (Figure 16.39) state in spans between sus-
within a tensioning section differs essentially from the behaviour when the conductors a; pension towers
are fixed to suspension clamps (Figure 16.40), if either large differences in the attach-
ment heights of the conductors at the towers exist or if the span lengths differ to a of conductor tensile forces result thereof. The differences affect a displacement of the
larger extent within a tensioning section. These aspects have to be considered when
ínsulator set in direction of the span with the lower conductor downstrain angle. The
determining the conductor sagging data.
difference of horizontal tensile forces of two adjacent spans results from Figure 16.41
It is the goal of the procedure described in [16.31] to determine the sags of conductors
and [16.31] to be
and the installation positions of the suspension clamps at the conductors resting on
stringing blocks such that the sags of the conductors and the position of the insulator (16.14)
sets after clipping-in comply with the data established during line planning.
where hsi is the difference of the height of the sagging line vertices of two adjacent spans.
Since the conductors are fixed in line direction at the suspension supports, the insulator
This relation describes the state of equilibrium of the conductor, when the conductors
sets will assume a vertical position only if the horizontal components of the conduc-
tor tensile forces in the adjacent spans are equal. However, if the conductors rest on rest on stringing blocks at ali suspension sets of the tensioning section. If the horizontal
stringing blocks, a condition of equilibrium exists if the conductor tensile forces on tensile force in the first span is given, then the value in the span i results from
both sides of the stringing blocks are equal. Then, no resulting moment acts around i-1
the block axle (Figure 16.39). The horizontal components of the tensile forces of the H; = H 1 + mcg ¿ hsj (16.15)
conductors in the adjacent spans will be equal, if there are neither differences in height j=l
between the conductor attachments nor in the span lengths. Only under this condition, If the conductors are fixed to a suspension clamp, the equilibrium of moments is com-
the downstrain angles of the conductors on both sides of the stringing block are equaL plied with around the suspension pivot of the insulator set (Figure 16.40). The be-
In case of differing attachment heights of conductors or differing span lengths, differing haviour of conductors suspended by clamps within a tensioning section of an overhead
conductor downstrain angles a exist (Figure 16.39) and differing horizontal components line is dealt with in clause 14.8 in detail.
668 16 Construction 16.8 Conductor stringing 669
i-1 i+1
For an exact installation of the conductors, the position of the suspension clamps at
each suspension tower of the tensioning section needs to be determined. The exact
initial sags have to be calculated as well for the conductors suspended by stringing
blocks such that the insulator strings assume a plumb position after clipping-in the
suspension clamps.
The swing angle /3i+1 at the insulator set i + 1 can be determined from
The signification of the variables as; and así+1 can be taken from Figure 16.41. The
offset of the conductor suspension point is obtained from
(16.18)
Due to the offset of the insulator set, the theoretical lengths of the individual spans are
modified according to Figure 16.43: Sags and
conductor tensile forces in
(16.19) a tensioning section after
clipping-in of conductors
The conductor length can be obtained from (14.14) for conductors on stringing blocks
section. However, in this case the conductor needs to be readjusted at the strain tower
(16.20) at the end of the tensioning section with n spans by the value
n n
The length of the clipped-in conductor in the span i is obtained from Vn+l = L !:,.Lj = ¿(Lj - Lj) (16.24)
j=l j=l
L;= (16.21) An optimum could be achieved if the conductor tensile stringing forces for the conductor
resting in stringing blocks (Figure 16.42) were determined such that the offsets within
the tensioning section are mutually compensated after the clipping-in. Then, the offset
assurning a constant horizontal tensile force H 0 in ali spans. The variation of the con- Vn+I at the strain tower will be zero and any readjustment would not be necessary
ductor length in the span i between a suspension of conductors in stringing blocks or anymore (Figure 16.43). This requirement is complied with, if the sum of conductor
clipped-in results from catenary lengths is equal for the conductors on stringing blocks and for conductors
(16.22) clipped-in at the suspension clamps.
With the abbreviation
From (16.22), the offsets can be determined by which the suspension clamps at each
insulator set need to be displaced such that the insulator sets will be suspended verti-
Lo;= Jh¡ + ar (16.25)
cally after installation of the suspension clamps and the horizontal forces and sags in an approximation for the conductor catenary length can be obtained from
all spans correspond to the required data. The offset measured approximately along a¡. (mcg)2
the conductor at the insulator set of the tower i of a tensioning section with n spans is (16.26)
L; ~Lo;+ 24Lo; · H¡
obtained from
The sum of the conductor catenary lengths in the tensioning section is obtained from
i-1 i~l
the horizontal tensile forces H; for conductors suspended on stringing blocks from
Vi = I: /:,.Lj = I:=(Lj - L5) (16.23)
j=l j=l
L' =~ (L'. + a~4.(mcg)2) (16.27)
D o, 24L' --H?
The offsets in a tensioning section are shown in Figure 16.42. In case of a positive sign i=l Oi 1
of the offset v;, the suspension clamp at tower i has to be installed in a distance v; After clipping-in of conductors with the horizontal tensile forces Ho in all spans from
measured in direction to tower i + l. the sum of the catenary lengths will be
The relations (16.20) to (16.23) enable to determine the offset v; for any given horizontal
tensile forces H; such that the insulator sets will be suspended vertically after clipping-in
and the horizontal tensile force is constant and equal to Ho within the whole tensioning
L = t
i=l
(LOi +a¡. (mcg):)
24 Lo; • H 0
(16.28)
L'--'•V' .__,.....,..._ ... ....._...._.._,.,s..;.1. uv.1..1.LL5.1..1.-<-5 ...;, .L
As assumed, the lengths L and L' should be equal. The horizontal tensile forces H; to There, e is the creep strain, measured in thousandth; e1h and n are parameters de-
be selected in the stringing condition can be obtained from (16.27) and (16.28): pending on the conductor design, conductor material and conductor cross section, the
n 4 1 n 4
operation history, the tensile stress and the temperatures; t is the period of time elapsed
¿~=-2 -¿~ ' (16.29) after the first loading of the conductors in hours. The parameter e 1h represents the creep
i=l LOi H; H 0 i=l Lo; strain one hour after loading the conductor.
where Ló; ~ Lo; and a~ ~ a; was assumed. To determine the parameters n and e1h, tests need to be carried out for each conductor
Equation (16.29} cannot be solved directly to one of the n horizontal tensile forces H;. under sagging conditions and an expected mean temperature. Such tests, however,
An iteration procedure is recommended where at first a value H1 o for the horizontal need a long period of time and are costly because of the long duration and the required
tensile force in the first span of a tensioning section is assumed and then the data H· 0 accuracy of the measurements. A procedure for testíng the creep behaviour of conductors
within the other spans are calculated by equation (16.15). The equivalent horizonW is standardized in IEC 61395 [16.35]. In [16.34], a method and data are given which
tensile force HE,k can be computed from (16.29): can be used to forecast the creep strain for practica! application. The creep strain to
be expected after an operation period of 30 years can be obtained from
tªt¡t-1
Lo;
i=l
(-55._)2
Lo; H;,k
i=l
(16.30) (16.33)
There, the index k refers to the iteration step. Using the value HE,k, the tensile forces The parameter e30 is the non-elastic strain at everyday stress according to 20 % of
Hi,k+l used in the following step can be determined according to the rated tensile strength (RTS) of the conductor. As an approximation, the creep
elongation can be assumed as depending linearly on the steel content of the conductor
(16.31) weight
The iteration process is continued until HE,k corresponds with sufficient accuracy to
the target value Ho. A few steps are sufficient to achieve this goal.
e30 = 1,12 - 0,97 • w/100 , (16.34)
The practica! calculation needs sorne effort because of the necessary iterations and the where w is the steel content of the conductor weight, expressed in percent. As an
large number of possible adjustment conditions which should take care of the ambi- appropriate approximation, the parameter ku is assumed to depend linearly on the
ent temperature during adjustment and the time schedule of conductor installation
re!ative everyday stress a'.
activities. Therefore, the calculation is carried out using computer programs.
ku = a'/20 (16.35)
16.8.5.3 Impact of conductor creep
Conductors for overhead lines, being single-material conductors made of aluminium or The relative everyday stress is expressed as a percentage of the rated tensile stress.
aluminium alloy or composite conductors ~ e of aluminium and steel or aluminium The relations (16.34) and (16.35) apply for ACSR conductors with a' :S 30 %, however,
alloy and steel, expand non-elastically under a permanent tensile load. This creep pro- they can be used for AACSR conductors as an approximation, too.
cess results in a non-reversible elongation of the conductors and steadily increasing sags The creep process of the conductors starts immediately after stringing. Since the creep
during overhead line operation. Planning and installation should provide for conductor strain is relatively high immediately after stringing, the period between the stringing
creep. and the sagging of the conductor reaching up to severa! weeks should be considered
A non-reversible elongation of a conductor is caused by consolidation of the conductor when determining the sagging data. For this purpose, equation (16.32) can be used. The
structure after the first loading of the stranded conductor. This phenomenon occurs exponent nis gained from tests [16.35]; for sorne conductor types, information is given in
already during stringing of the conductor and continues during operation especially [16.34]. Where other data are not available, n = 0,25 can be used asan approximation.
under increased mechanical loads. Then, additional irreversible elongations are caused The parameter e 1 h can be obtained from (16.32) with t = 24 • 365 • 30 = 2,628 • 105 h
by metallurgical procedures within the conductor material, which is called conductor and e30 according to (16.34). From (16.32), the creep strain at a given time can be
creep. The conductor tensíle stress and the conductor temperature affect essentially calculated then using the mentioned data for e1h and n.
the conductor creep. With rising tensile stress and temperature, the speed of creep is The elongation of conductors due to creep produces the same change of the conductor
increased as well. To provide for the additional sag due to creep, it is necessary to state as an equivalent temperature variation ll.T¡d, which can be obtained from
estímate the non-elastic elongation to be expected during the life-cycle of the conduc-
tors. A forecast is difficult also in case where measured data for the creep behaviour (16.36)
of a certain conductor are available, since such a forecast would need the variations of
tensile forces and temperatures durin·g operation. However, these data are not known where e is the creep strain according to (16.32) and ET the coefficient of thermal expan-
in advance. sion given in l/K. To provide for creep, the conductor may not be adjusted with data
for the ambient temperature during sagging, but with data for a conductor tempera-
Numerous measurements were carried out at overhead line conductors to determine
ture which is lower by the equivalent tempemture difference llT¡ct, Taking into account
their creep behaviour [16.32, 16.33]. An evaluation of these tests with proposals for
a constant creep strain and an equivalent temperature difference for all span lengths
considering the creep is given in [16.34]. The expected irreversible creep strain can be
described by means, that the reduction of sag is relatively higher, the lower the span length is. The
initial stress is, therefore, increased to a higher extent than in long spans, and the
(16.32) resistance of the structures may limit the reduction of sags.
672 16 Construction
7! 16.9 References 673
Tower No. 2 3 4 5 6 7
2
Ta,ver type A+ 18 T+20 T+20 T+20 T+20 A+18 Table 16,7: Sagging table: Sags in m and conductor tensile stresses in N/mm for
Span length m 412,0 293,0 239,0 250,0 438,0 sagging, conductors in strínging blocks, 14 days after stringíng
Dítference in 15,06 96,00 96,65 73,56 1,09
Altítude m Temperature during sagging ºC
o 5 10 15 20 25 30 35
Span l Sag 16,36 16,64 16,92 17,19 17,47 17,74 18,01 18,27
412,0 rn Tensile stress 50,3 49,5 48,6 47,9 47,1 46,4 45}7 45,0
Span 2 Sag 8,74 8,88 9,02 9,16 9,29 9,43 9,56 9,70
293,0 m Tensile stress 50,0 49,2 48,4 47,7 47,1 46,4 45,7 45,1
Span 3 Sag 5,70 5,79 5,87 5,96 6,04 6,12 6,20 6,28
Figure 16.44: Longitudi- 239,0 m Tensile stress 52,3 51,4 50,7 50,0 49,3 48,7 48,l 47,4
nal profile of a tensioning Span 4 Sag 5,49 5,57 5,64 5,72 5,79 5,86 5,94 6,01
section in a ínountainous 250,0 m Tensile stress 57,4 56,6 55,8 55,1 54,4 53,7 53,1 52,4
o 705,0 944,0 1194,0 m 1632,0 a.rea Span 5 Sag 15,23 15,44 15,65 15,86 16,07 16,27 16,47 16,66
438,0 m Tensile stress 61,0 60,1 59,4 58,6 57,8 57,l 56,4 55,7
Offset in cm at Tensile stress 54,6 53,7 52,9 52,2 ,51,4 50,7 50,0 49,3
Tower No. 2 o o o o o at N/mm 2
Tower No. 3 -6 -7 -10 -12 -13 Sag in m
Tower No. 4 Span 1 15,07 15,31 15,5'4 15,77 16,00 16,22 16,45 16,67
-86 -87 -87 -88 -88
Tower No. 5 -96 -96 -97 -98 -98 412,0 m
Tower No. 6 Span 2 8,01 8,13 8,25 8~38 8!50 8,62 8,74 8,85
-56 -57 -57 -58 -58
Tower No. 7 2 2 2 2 2 293,0 m
Span 3 5,46 5,54 5,63 5,71 5,79 5,87 5,95 6,03
239,0 ID
Span 4 5,77 5,86 5,95 6,04 6,12 6,21 6,30 6,38
250,0 m
Example: For the conductor 564-ALI/72-STlA (ACSR 564/72), which is used as a twín Span 5 17,03 17,29 17,55 17,81 18,07 18,33 18,58 18,83
bundle for 400 kV lines (see [16.36]), an equivalent temperature difference of 30 K is assumed 438,0 m
corresponding to a creep strain of approxímately 0,06 % for 30 years. The final everyday stress
2
at lOºC should be 57 N/mm • For aspan length of 600 m, the reduction of the sag is 1,45 m
equal to 5,5 % of the sag, and for 400 m span length it will be 1,30 mor 11,4 % of the sag and, e30 applicable for an operation period of 30 years. For the conductor 128-ALl/30-STlA, the
finally, for 200 m span length 0,80 mor 27,5 %, respectívely. coefficient of thermal expansion is 18,9 • 10-5 1 /K.
The results of the calculatíon explaíned above are shown in Tables 16.6, 16. 7 and 16.8 together
16.8.5.4 Example: Sagging data for an overhead line in a mountainous area with the data necessary for sagging. Table 16. 7 is designated also as sagging table. The offset at
the tower No. 5 rea.ches approximately one meter in thís case. For other examples, especially in
The longitudinal profile of an overhead line in a mountainous area is shown in Figure case of long tensioning sections, offsets reaching severa! meters are possible. As verified by many
16.44. Phase conductors 128-ALl/30-STlA are used and installed with an everyday stress of practical exarnples, conductor sagging using the described procedure leads to the designed final
2
50 N/mm , reaching 13,7 % ofthe rated tensile stress of 365 N/mm 2 . The conductor mass per sags also in extreme cases. Comparison of Tables 16.7 and 16.8 allows to recognize the essentíal
unit length is 0,59 kg/m, having a steel content of 0,23 kg/m, reaching 39 % of the conductor difference between the sags and conductor tensile stresses for conductors suspended in stringing
mass. blocks compared with conductors clipped-in in suspension clamps.
From equation (16.34), the creep strain e30 is obtained for this condition to be 0,074 % and
the para.meter ku is calculated from (16.35) to be 0,685. The creep strain to be considered is,
therefore, 16.9 References
e3 0 = 0,74 • 0,68 = 0,051 % 16.1 VBG 37: Bauarbeiten, Unfallverhütungsvorschríf t (Construction works, safety regula-
tions). Cologne, Berufsgenossenschaft der Feinmechanik und Elektrotechnik, 1977
The exponent n used in equation (16.32) is assumed to be 0,2 [16.33]. The para.meter e 1 h results
from
16.2 IEC 61 773: Overhead lines: Testing of foundations for structures. Geneva, IEC, 1996
e1h = 0,51/(2,628 • 105 )°~ 0,2 = 0,00420 %
16.3 EN 50 341-3-4: Overhead electrical lines exceeding 45 kV. Part 3-4: National Normative
It is assumed, that the conductors are sagged either 12 h, 24 h, 7 d, 14 d or 30 d after strínging. Aspects (NNA) for Germany. Brussels, CENELEC, 2002
The equívalent temperature differences for which the sag is determined fol!ow from (16.36).
For this case, the creep strain expected at the time of adjustment is to be determined from 16.4 ENV 206: Concrete; attributes, productíon, implementation and quality evidence. Brus-
(16.32) 11vith the mentioned parameters n and e1 h and then to be substracted from the strain sels, CEN, 1990
674 16 Constructi on
and equip-
Brussels, 16.28 DIN 48207-2: Overhead lines with nominal voltage exceeding 1 kV: Methods
16.5 ENV 197: Concrete; composition, requiremen ts and parameter of confonnity. ment for the installation of conductors. Part 2: Pulling grips, steel made. Frankurt, DKE,
CEN, 1992 Draft 2000
16.6 DIN 1164-1: Cement; Part 1: Compositio n, requiremen ts. Berlín, DIN, 1994 16.29 DL'J\l 48207-3: Overhead lines with nominal voltage above 1 kV: Methods and
equipment
for the installation of conductors . Part 3: Swivel joints. Frankfurt, DKE, Draft 2000
16.7 Betonkalen der (Annual concrete report 1996), Part l. Berlin, Emst & Sohn
Power
16.8 DIN 4226-1: Aggregates for concrete, aggregates with dense structures, definitions,
char- 16.30 Raymond, W.: Replacing conductors of high-voltage transmissio n lines. Síemens
Technology 2 (1980), pp. 35 to 42
acteristics and requiremen ts. Berlín, Drn, 1983
n of
16.9 DIN 1045: Reinforced concrete structures; design and constructio ns. Berlín, DIN,
1988 16.31 Kieflling, F.: Die Verlegung der Leiter einer Hochspann ungs-Freile itung (Installatio
for a hígh-voltag e transmissio n line). Elektrizita. tswirtschaft 78 (1979), pp.
conductors
Berlín,
16.10 DIN 4226-3: Aggregates for concrete, aggregates with dense.and porous structures. 712 to 719
DIN, 1983 mit unter-
16.32 He!ms, R.; Ziebs, J.: Stand der Untersuchu ngen an AI/St-Freile itungsseilen
16. 11 ISO 2736: Test of concrete; preparation of test cubes, specimens taken from fresh
concrete. schiedlichen Querschnitt sverhiiltnis sen (Status of actual investigatio n for ACSR conduc-
Geneva, ISO, 1986 tors vvith different cross-sectional portions). Berlín, Bundesans talt fiir Materíalprü fung,
Report 1967
16.12 ISO 4013: Concrete; classification of consistence. Geneva, ISO, 1979 ver-
16.33 Brandt, E.; Thomas, R.: Der Eínfluss der bleibenden Seildehnun g auf das Durchhangs
ISO 1979
16.13 ISO 9812: Fresh concrete: Determinin g of consistence, spreading index. Geneva, halten von Freileitunge n (The ínfluence of permanent creep on sags of overhead lines).
ISO Elektrizitii.tswirtschaft 78 (1979), pp. 262 to 268
16.14 ISO 1411: Fresh concrete: Determinin g of consistence, compressio n test. Geneva,
Electra 24
1979 16.34 Cigré SC22 WG22-05: A practical method of conductor creep determinati on.
1991 (1974), pp. 105 to 137
16.15 ISO 4109: Fresh concrete: Determinin g of consistence, slump test. Geneva, ISO,
conduc-
ISO, 1991 16.35 IEC 61395: Overhead electrical conductors. Creep test procedure for stranded
16.16 ISO 4110: Fresh concrete: Determinin g of consistence; "Vebe" test. Geneva, tors. Geneva, IEC, 1998
ISO,
16.17 ISO 4012: Concrete; determinin g of compressio n strength at test cubes. Geneva, 16.36 Flug, R.; Schnakenbe rg, D.: Überlegung en bei der Projektieru ng einer neuen
380-
1978 kV-Freileitung (Considerat ions on designing a new 380 kV transmissio n line). Elek-
16.18 DIN 1048-1: Testing concrete; testing of fresh concrete. Berlín, DIN, 1991 trízita.tswir tschaft 70 (1971), pp. 606 to 610
engineers).
16.19 Schneider, K.-J.: Bautabellen für Ingenieure (Constructi on tables for
th
Düsseldorf, Werner-Verlag, 13 edition 1998
ns for the
16.20 Gardes, J.-L. et al.: EDF's approach to the design and constrution offoundatio
transmissio n network overhead lines. Cigré Report 22-104, 1994
(Solid wall
16.21 Studiengesellschaft Stahlanwen dung e.V. Stahlmaste in Vollwandbauweise
Civil
steel towers): Project No. 152. Universita.t-Gesamthochschule Essen, Departmen t
Engineering , 1992
16.22 Gohm, H.; Kiefüing, F.; Mahr, V.: Verformung von Stahlvollwa ndrnasten mit Steckstéiflen
with
beim Einsatz in Hochspann ungsfreileit ungen (Deformati on of solid-wall steel poles
31
slip joint used for transmissio n lines). Elektrizita. tswirtschaf t 97 (1998)23, pp. 27 to
für eine
16.23 Raymond, W.; Schnakenbe rg, D.: Errichtung 227 m hoher Stahlgitterm aste
n
Freileitung s-Flusskreu zung (Erection of 227 m high steel towers for a 380 kV transmissio
line river crossing). Elektrizitat swirtschaft 78 (1979), pp. 255 to 261
Erlangen,
16.24 Fuchs, A.; Schramm, H.: 500 kV overhead transmissio n line across Suez Canal.
Siemens AG PTD H2, 1999
/800-
16.25 Schramm, H. et al.: Freileitung der Superlative verbindet Europa und Asien. 420-kV
420
kV-Bospor uskreuzung III (Superlativ e transmissio n line connects Europe with Asia,
kV /800 kV Bosphorus Crossing III). Elektrizitat swirtschaft 99 (2000}, pp. 13 to 19
devices
16.26 IEC TS 61328: Live working - Mínimum requiremen ts for the utilization of tools,
and equipment. Geneva, IEC, 2000
and equip-
16.27 DIN 48207-1: Overhead lines with nominal voltage exceeding 1 kV: Methods
ment for the installatíon of conductors. Part 1: Installation of conductors. Frankfurt,
DKE, Draft 1999