Rough Estimates
Rough Estimates
BLACK=INPUTS
EARTHWORKS NOTE:
PARTITION WALL
DESIGNATION HEIGHT(m) TOTAL LENGTH(m)
Below Ground 0 100
Ground 4 61
Second floor 3.1 55.75
TOTAL AREA=
CATCH BASIN
DESIGNATION WIDTH(m) QUANTITY(m) LENGTH
CB1 0.5 18 0.5
CB2 0 0
TOTAL AREA=
SEPTIC TANK
DESIGNATION PERIMETER(m) TOTAL HEIGHT(m)
SP1 12 2
SP2 0 0
TOTAL AREA=
FOOTING
DESIGNATION QUANTITY WIDTH (m) LENGTH (m)
F1 20 1.5 1.5
F2 2 1.2 1.6
F3 0 0 0
F4 0 0 0
F5 0 0 0
F6 0 0 0
HORIZONTAL
BEAM
DESIGNATION WIDTH (m) DEPTH (m)
B1 0.2 0.3
B2 0.2 0.4
B3 0.2 0.4
B4 0.2 0.7
CB 0.2 0.3
RB1 0.2 0.3
RB2 0.2 0.3
0 0 0
SLAB
DESIGNATION QUANTITY WIDTH (m) LENGTH (m)
S1 1 13.1 22.14
S2 1 11.05 19
S3 0 10.98 11
S4 0 8.7 9.6
RD1 0 4 5
RD2 0 3 3
CONCRETE GUTTER
DESIGNATION QUANTITY LENGTH (m) WIDTH (m)
CG1 0 36 1
CG2 0 24 1
RETAINING WALL
DESIGNATION HEIGHT(m) LENGTH (m) WIDTH (m)
RW1 0 0 1.9
RW2 0 0 1.7
SCAFFOLDINGS
BASEMENT AREA= 0 sq.m TOTAL AREA=
1ST FLOOR AREA= 288.927 sq.m BOARD FEET=
2ND FLOOR AREA= 228.375 sq.m BOARD FEET=
ATTIC AREA= 0 sq.m TOTAL BD.FT=
GRADE BEAM
DESIGNATION WIDTH (m) DEPTH (m) LENGTH(m)
TB1 0 0 1
TB2 0 0 1
COLUMN
DESIGNATION QUANTITY # OF REBAR NEEDED HEIGHT(m)
C1 20 6 6.4
C2 19 6 5.1
C3 2 6 7.4
C1 20 2 6.4
C5 0 0 2
C6 0 0 2
STAIR
DESIGNATION QUANTITY WIDTH (m) LENGTH(m)
S1 1 1.25 4.35
S2 1 1.25 4.35
SEPTIC TANK
DESIGNATION LENGTH (m) WIDTH (m)
SP1 3 1.5
SP2
CATCH BASIN
DESIGNATION LENGTH (m) WIDTH (m)
CB1 20 0.5
CB2 0 0.6
WALL FOOTING
DESIGNATION QUANTITY WIDTH (m) LENGTH(m)
WF1 1 0.4 63.5
WF2 1 0.4 61.1
WF3 0 0 0
RETAINING WALL
DESIGNATION HEIGHT(m) LENGTH(m) WIDTH (m) HEIGHT(m)
RW1 0 0 1.9 0.3
RW2 0 0 1.7 0.2
TOTAL LENGTH=
ROOF FRAMING
ROOFING
1.1 UNDERSHEATING
CARPENTRY
TILE WORKS
GLASS WORKS
PLUMBING WORKS NOTE: ESTIMATE BY DIRECT CO
AREA OF CEILING
QUANTITY
Doors=
Shelves=
Kitchen Cabinets=
Automotive Finish=
SOIL POISONING AND
WOOD PRESERVATIVES
TOTAL VOLUME(cu.m)
13.5
1.1136
0
0
0
0
14.6136
TOTAL VOLUME(cu.m)
5.08
4.888
0
9.968
TOTAL VOLUME(cu.m)
5.28
3.534
1.944
0
0
0
10.758
TOTAL VOLUME(cu.m)
1.038
5.644
6.528
1.4266
0.6564
7.335 190.58
0.45 66.17361111
0
23.078
TOTAL VOLUME(cu.m)
0
0
0
TOTAL VOLUME(cu.m)
1.0875
1.0875
2.175
TOTAL VOLUME(cu.m)
34.80408
25.194
0
0
0
0
59.99808
TOTAL VOLUME(cu.m)
0
0
0
TOTAL VOLUME(cu.m)
0.9
0
0.9
TOTAL VOLUME(cu.m)
0.54
0
0.54
TOTAL VOLUME(cu.m)
0
0
0
TOTAL CONCRETE VOL.= 122.03068 cu.m
TOTAL AREA(sq.m)
0 (CHB)4"x8"x16"=
260 (setting + filler)Portland Cement=
186 (plastering)Portland Cement=
0 (setting + filler)screened sand=
446 (plastering)screened sand=
6m,reinforcing steel(10mm)=
tie wires (#16)=
TOTAL AREA(sq.m)
0
244
172.825
416.825
16 sq.m.
12 bags
2.40 cu.m
12.00 kls
6 kgs
517.302 sq.m
7223.175
5709.375 Lumber:
12932.55
CWN:
LENGTH NEEDED
LENGTH (m) TOTAL LENGTH (m) rebar dia.(m) BASIS
1.5 600 0.016 CONCRETE
2.6 88.5333333333333 0.016 CONCRETE
1 0 0.016 CONCRETE
1 0 0.016 CONCRETE
1 0 0.016 CONCRETE
1 0 0.016 CONCRETE
TOTAL LENGTH= 688.533333333333
LENGTH NEEDED
LENGTH (m) TOTAL LENGTH (m) rebar dia.(m) BASIS
593.168 1195.376 0.01 CONCRETE
1701.7 3419.30 0.01 CONCRETE
0 0.012 CONCRETE
0.00 0.012 CONCRETE
0 0.012 CONCRETE
0.00 0.012 CONCRETE
TOTAL LENGTH= 4614.68
consider
all bar continuous TOTAL LENGTH (m) rebar dia.(m) BASIS
103.8 0.012 CONCRETE
564.4 0.016 CONCRETE
652.8 0.016 CONCRETE
81.52 0.016 CONCRETE
87.52 0.016 CONCRETE
733.5 0.016 CONCRETE
45 0.012 CONCRETE
0 0.02 CONCRETE
TOTAL LENGTH= 148.8
2119.74
1.5 DOWNSPOUTCOVER
287.45 sq.m
0.60x0.60 Awning Window
Doors,Shelves,Kitchen Cabinets,Automoti
Automotive Laquer Primer White
sq.m
class A
Portland Cement 1221 bags
Wash Sand 62 cu.m
3/4 " crushed gravel 123 cu.m
WEBC class A class B class C
(CHB)4"x8"x16"= 10619 10619 10619 10619 pcs
(setting + filler)Portland Cement= 673 N/A 860.549 644.7743 bags
(plastering)Portland Cement= 184 244.6574 163.105 122.3287 bags
(setting + filler)screened sand= 38 for 4"x8"x16" CHB cu.m
(plastering)screened sand= 14 14 14 14 cu.m
6m,reinforcing steel(10mm)= 627 627 627 627 pcs
tie wires (#16)= 84 84 84 84 kgs
#4" 82 kgs
#3" 82 kgs
#2" 163 kgs
T COUNTING
725.085
4350.51
0 pcs. 12mm
6m,bar needed= 0 kgs
BASIS ties=
CONCRETE 0 pcs. 10mm
CONCRETE 6m,bar needed= 0 kgs
ties=
ES/FASCIA BOARD
Roughing-in
Emerald PVC pipe 4" S-1000 35 le
Emerald PVC pipe 3" S-900 41 le
Emerald PVC pipe,2" S-1000 19 le
PVC Fittings&Accessories 1 lot
Marine Epoxy A&B 2 gal
Solvent Cement 400cc 6 cans
ulti-layer Cold Water Line Pipe,3/4" 50 mtrs
ulti-layer Cold Water Line Pipe,1/2" 55 mtrs
Multi-layer HOt Water Line Pipe,1/2" 45 mtrs
Fittings&Accessories 1 lot
Fixtures
Master Bedroom T&B
Wash Basin-HCG Peony L101
ssel Type White (with Counter Top) 1 set
Shower Enclosure-BRL OLS A06-3 1 set
Shower Panel 1 set
Water Closets 1 set
Common T&B/Powder Room
HCG l4001 Basin Type Lavatory 2 sets
Water Closets 2 sets
Shower Panel 2 sets
Kitchen & Service Area
Kitchen Sink 1 sets
Kitchen Sink Faucet 1 sets
Service Faucets 5 sets
Floor Drain 20 pcs
A. Roughing-In
2.0 mm^2 THHN Stranded Wire 12 roll
3.5 mm^2 THHN Stranded Wire 10 roll
5.5 mm^2 THHN Stranded Wire 5 rolls
38 mm^2 THHN Stranded Wire 80 mtrs
Telephone Wire 22/4c 2 roll
Cable Wire RG-6 2 roll
Entrance cap 2 2 set
EMT Pipe 2" 2 length
Secondary rock 3 pole 4 pc
Emt connector 2" 10 pcs
Neltex PVC POlylinePipe, 11/2 17 lengths
Neltex PVC Elbow, 11/2 8 pcs
Neltex PVC Polyline Pipe 1/2 50 lengths
Neltex PVC PolylinePipe 3/4 55 lengths
PVC Clamp 5 bags
Flexible Hose 1/2 8 rolls
PVC Accessories 1 lot
4 x 4 x 2 Junction Box 1 lot
2 x 2 x 4 Utility Box 1 lot
4 x 4 x 11/16 Pull Box 2 set
3/8 in. dia. Mica Tube 4 roll
Electrical Tape 20 pcs
Panel Board w/ Circuit Breakers 1 set
Fixtures
Ceiling Lamp 10 sets
7 watts Pin Lights (casing & Bulb) 50 sets
Outdoor wall lamps 10 sets
Single gang switch 10 sets
Two Gang Switch 12 sets
Two Way Switch 6 sets
Three Gang Switch 7 sets
Two gang C.O 22 sets
Cable Outlet 4 sets
Telephone Outlet 4 sets
Eagle Weather Proof Outlet 5 sets
Rangehood Outlet 2 set
Range Outlet 10 set
ACU Outlet 10 set
3RD FLOOR
FAMILY ROOM 0 sq.m BALCONY
STUDY ROOM 26.25 sq.m TERRACE
STOCK ROOM 0 sq.m
HALLWAY 0 sq.m
STAIR 0 sq.m
T&B 2.4 sq.m
BEDROOM 1 0 sq.m
BEDROOM 2 0 sq.m
BEDROOM 3 0 sq.m
BEDROOM 4 0 sq.m
2ND FLOOR
CLOSED AREA
MASTER'S BEDROOM 20 sq.m
STUDY ROOM 0 sq.m
STOCK ROOM 0 sq.m
HALLWAY 9.5 sq.m
STAIR 20.4 sq.m
T&B 17.63 sq.m
BEDROOM 1 9.9 sq.m
BEDROOM 2 18.2 sq.m
BEDROOM 3 0 sq.m
BEDROOM 4 0 sq.m
OPEN AREA
BALCONY 0 sq.m
TERRACE 0 sq.m
ATTIC FLOOR
CLOSED AREA
FAMILY ROOM 0 sq.m
STUDY ROOM 26.25 sq.m
DECK AREA 20.9 sq.m
HALLWAY 0 sq.m
STAIR 20.4 sq.m
T&B 2.4 sq.m
BEDROOM 1 0 sq.m
BEDROOM 2 0 sq.m
BEDROOM 3 0 sq.m
BEDROOM 4 0 sq.m
OPEN AREA
BALCONY 0 sq.m
TERRACE 0 sq.m
OPEN AREA
62 sq.m
0 sq.m
0 sq.m
0 sq.m
0 sq.m
19.25 sq.m
19.25 sq.m
Concrete 84.53 cu.m 84.53 Excavation 93.14
A. Roughing-in
Wires & Cables 74,004.00
2.0 mm^2 THHN Copper Wire 5 rolls 2,255.00 11,275.00
3.5 mm^2 THHN Copper Wire 6 rolls 3,300.00 19,800.00
5.5 mm^2 THHN Copper Wire 2 rolls 5,058.00 10,116.00
38 mm^2 THHN Copper Wire 120 m 252.00 30,240.00
3 C Jacketed Tel. Wire 1 rolls 755.00 755.00
1/4 in. dia. Mica Tube 1 rolls 415.00 415.00
1/2 in. dia. Mica tube 1 rolls 810.00 810.00
Electrical Tape 16 pc 33.00 528.00
Rubber tape 1 65.00 65.00
Pipes & Fittings 11,265.00
15mm dia. PVC Pipe 65 L 65.00 4,225.00
20mm dia. PVC Pipe 25 L 78.00 1,950.00
25mm dia. PVC Pipe 20 L 33.00 660.00
65mm dia. PVC Pipe 10 L 163.00 1,630.00
Elbow & Connector 1 lot 2,500.00 2,500.00
65mm dia. Entrance Cap 1 set 125.00 125.00
3 Pole Secondary Rack 1 pc 175.00 175.00
Panel Board & Boxes 17,650.00
Panel Board & Circuit Breakers 1 lot 15,000.00 15,000.00
4 x 4 x 2 Junction box 1 lot 1,200.00 1,200.00
2 x 2 x 4 Utiliry Box 1 lot 1,200.00 1,200.00
4 x 4 x 11/16 square box 1 set 250.00 250.00
Switches & Outlets 1 lot 8,500.00 8,500.00
Electrical Fixtures 1 lot 25,000.00 25,000.00
Cost of Material 136,419.00
Cost of Labor 54,567.60
Sub-total XIV - B 190,986.60 ###
Comfort room
Floor tiles #REF! 10
b. Second Floor
Ceramic Tiles
Bedrooms 73.7
Family Room/Hallway 28.6
Balcony 74.8
Stair - going garage
Comfort room
Floor tiles #REF! 117.80 15.5
265.35 ###
191 ###
456.35 ###
Granite Tiles
Living/Dining/Foyer/Family Room 95.9
Ceramic Tiles
Lanai/Service/Porch/Storage 46.50
Aux. Kitchen/MaidsRoom/Pantry 17.30
Carport 28.50
Comfort room
Floor tiles #REF! 4.9
Second Floor
Ceramic Tiles
Bedrooms/theater Room/Hallway 99.61
Balcony 19.53
Comfort room
Floor tiles #REF! 114.31 14.7
232.41 ###
48.03 408,212.50
46.50 302,250.00 ###
326.94 ###
35
123 75 233
125 55 180 413
248 4464000
130 1235000 5699000
378 5670000
Masonry 571.13 sq.m
BGL 132.3 0.6 79.38 0
gf 87.9 2.8 246.12
2f 109 2.8 305.2
level 1 3 0
attic 1.5 0
septic 18
cb 20.48
rd 1.5 0
669.18
less door n window 98.05
area 571.13 0
chb 7139.125 7140 0
cement 609.2053 610 0 610
bv 41.88287 42 0 42
10mm 452.6734 453 0 453
0
76.95 1120
16654
82.44
31.71
114.15 131.2725
18 0 64 293.3333
0 0 0 0
20mm
PROJECT : PROPOSED TWO-STOREY RESIDENTIAL BUILDING
LOCATION : LOT17 BLK10 VISTA VERDE VILLAGE,CDOC
OWNER : GINA KO
V. Concrete Works
Portland Cement 1,221.00 bags
Wash Sand 62.00 cu.m
3/4 " crushed gravel 123.00 cu.m
cost of material
cost of labor
Sub-total V
VIII. Roofing
A. Undersheeting
Marine Plywood 1/2" 94 shts
Self Drilling Screws 3290 pcs
Screwbits 6 pc
Harvi Foil insulation 6 rolls
Cost of Materials
Cost of Labor
Sub Total VIII - A
B. Shingles & Bended Accessories
Shingles Roofing 268.00 sq.m
Bended Accessories & Gutter 66.00 l.m
Tools and other consumables 1.00 ls
Cost of Materials
Cost of Labor
Delivery Cost
SubTotal VIII - B
Door accessories
Entrance Door Knob, Hafelle 1.00 set
Door Knob, locksets 8.00 sets
Door Knob, Sliding Glass Door 4.00 sets
Door Knob, T&B 6.00 sets
Door Hinges, Stanley 1.00 pairs
Cost of Materials
Cost of Labor
SubTotal IX-B
D. Mouldings
Cornice Moulding 4" 200.00 l.f
Baseboard Moulding 4" 160.00 l.f
Finishing Nail 8.00 kgs
Wood Glue 6.00 li
Cost of Materials
Cost of Labor
SubTotal IX-D
E.Downspout Cover
Marine Plywood, 1/2" 12 shts
Finishing Nail 1 1/2 4 kgs
Wood Glue 5 li
Airvent/Screen 1 lot
Cost of Materials
Cost of Labor
SubTotal IX-E
X.TILE WORKS
Ground Floor Plan Scq.m/bd.ft
Granite Tiles
Living Room/Dinning Area/kitchen/Foyer 110
Ceramic Tiles
Maids Room 11.53
Carport 47.214
Lanai 12.42
Service Area 12.3
Driveway 9.76
Stair_Tugas Wood
Stair ground floor to second floor 300
Comport Room
Maids Room 16.1
Powder Room 16.25
Guest T&B 17.2
Counter Top
Aux.Kitchen Counter -granite slab 10
Kitchen counter-granite slab 10
Lavatory counter -granite slab 7.2
Second Floor Plan
T&G Flooring Matwood Product
Bedsroom/Hallway/Family Room 204.535
Comport Room
Master's C.R 51.68
Children's C.R 64.12
Cement Mortars
Portland Cement 200 bags
Washed Sand 10 cu.m
Tile Grout 30 bags
Granite Polisher 5.00 sets
Cost of Materials
Cost of Labor
Sub total X
Prepared by:
NEVARD P.MAHINAY
CIVIL ENGINEER/ESTIMATOR
15,000.00 15,000.00
8,000.00 8,000.00
8,000.00 8,000.00
25,000.00 25,000.00
56,000.00 56,000.00
300.00 27,613.20
180.00 4,141.98
800.00 4,602.20
150.00 3,451.65
39,809.03 39,809.03
15.00 332,678.25
47.00 8,930.00
49.00 9,310.00
52.00 8,944.00
290.00 53,650.00
413,512.25
144,729.29
558,241.54 558,241.54
136.00 158,984.00
196.00 22,540.00
356.00 275,544.00
70.00 12,670.00
4,500.00 4,500.00
474,238.00
189,695.20
663,933.20 663,933.20
209.00 255,189.00
400.00 24,800.00
700.00 86,100.00
366,089.00
146,435.60
512,524.60 512,524.60
7.00 74,333.00
200.00 171,400.00
480.00 24,960.00
131.00 82,137.00
70.00 5,880.00
358,710.00
143,484.00
502,194.00 502,194.00
1,450.00 23,200.00
200.00 2,400.00
480.00 1,152.00
70.00 840.00
100.00 600.00
28,192.00
11,276.80
39,468.80 39,468.80
735.00 27930.00
425.00 46750.00
132.00 1980.00
145.00 3190.00
2,450.00 9800.00
370.00 5550.00
280.00 1400.00
18.00 108.00
96708.00
29012.40
125720.40 125,720.40
570.00 53580.00
2.00 6580.00
55.00 330.00
1,650.00 9900.00
70390.00
17597.50
87987.50 87987.50
800.00 214400.00
400.00 26400.00
10720.00 10720.00
251520.00
50304.00
5,000.00
306,824.00 306,824.00
395.00 69,520.00
398.00 9,552.00
105.00 29,715.00
118.00 10,030.00
36.75 6,247.50
5.50 2,557.50
0.50 4,780.00
0.50 4,495.00
95.00 1,520.00
138,417.00
62,287.65
200,704.65 200,704.65
2,000.00 2,000.00
1,800.00 1,800.00
1,700.00 5,100.00
1,600.00 12,800.00
1,500.00 9,000.00
2,400.00 0.00
5,500.00 5,500.00
6,800.00 108,800.00
2,850.00 8,550.00
5,500.00 5,500.00
400.00 3,200.00
1,000.00 4,000.00
300.00 1,800.00
120.00 120.00
168,170.00
67,268.00
235,438.00 235,438.00
700.00 11,200.00
900.00 54,000.00
105.00 1,050.00
385.00 385.00
8,000.00 8,000.00
74,635.00
33,585.75
108,220.75 108,220.75
85.00 17,000.00
85.00 13,600.00
105.00 840.00
125.00 750.00
32,190.00
12,876.00
45,066.00 45,066.00
570.00 6,840.00
54.00 216.00
125.00 625.00
2,500.00 2,500.00
7,681.00
6,000.00
13,681.00 13,681.00
Price
700.00 77,000.00
400.00 4,612.00
800.00 37,771.20
800.00 9,936.00
400.00 4,920.00
800.00 7,808.00
120.00 36,000.00
450.00 7,245.00
750.00 12,187.50
750.00 12,900.00
7,500.00 75,000.00
5,500.00 55,000.00
2,364.06 17,021.26
2,500.00 511,337.50
750.00 38,760.00
750.00 48,090.00
209.00 41,800.00
400.00 4,000.00
65.00 1,950.00
1050 5250
st of Materials 1,003,338.46
st of Labor 451,502.31
1,454,840.77 1,454,840.77
204,782.00
152,568.00
357,350.00 357,350.00
62,500.00
st of Materials 62,500.00
st of Labor 30,000.00
92,500.00 92,500.00
16,500.00
st of Materials 16,500.00
st of Labor 5,445.00
21,945.00 21,945.00
680.00 27,200.00
510.00 17,850.00
240.00 7,200.00
2,000.00 2,000.00
1,700.00 3,400.00
180.00 1,080.00
110.00 5,500.00
88.00 4,840.00
102.00 4,590.00
5,000.00 5,000.00
7,695.00 7,695.00
17,000.00 17,000.00
2,800.00 2,800.00
4,500.00 4,500.00
5,420.00 21,680.00
4,500.00 22,500.00
2,100.00 10,500.00
3,500.00 3,500.00
5,500.00 5,500.00
3,200.00 3,200.00
256.50 1,282.50
220.00 5,500.00
184,317.50
55,295.25
239,612.75 239,612.75
2,365.00 28,380.00
3,465.00 34,650.00
4,950.00 24,750.00
56.00 5,600.00
1,950.00 3,900.00
1,950.00 3,900.00
125.00 250.00
157.00 314.00
200.00 800.00
95.00 950.00
153.00 2,601.00
35.00 280.00
78.00 3,900.00
98.00 5,390.00
150.00 750.00
550.00 4,400.00
2,500.00 2,500.00
1,500.00 1,500.00
1,500.00 1,500.00
160.00 320.00
900.00 3,600.00
25.00 500.00
18,000.00 18,000.00
895.00 8,950.00
325.00 16,250.00
595.00 5,950.00
150.00 1,500.00
190.00 2,280.00
240.00 1,440.00
270.00 1,890.00
190.00 4,180.00
380.00 1,520.00
240.00 960.00
320.00 1,600.00
310.00 620.00
310.00 3,100.00
350.00 3,500.00
202,475.00
70,866.25
273,341.25 273,341.25
342.00 2,052.00
624.00 28,080.00
450.00 36,000.00
725.00 26,100.00
365.00 12,410.00
5,500.00 5,500.00
2,500.00 2,500.00
112,642.00
95,745.70
208,387.70 208,387.70
342.00 2,052.00
624.00 24,960.00
436.00 32,700.00
980.00 39,200.00
1,050.00 15,750.00
315.00 11,025.00
4,500.00 4,500.00
130,187.00
110,658.95
240,845.95 240,845.95
436.00 21,800.00
624.00 16,224.00
416.00 8,320.00
315.00 6,300.00
1,450.00 2,900.00
4,500.00 4,500.00
475.00 3,800.00
485.00 3,880.00
985.00 1,970.00
905.00 1,810.00
423.00 846.00
417.00 6,255.00
510.00 3,060.00
215.00 1,290.00
3,500.00 3,500.00
2,500.00 2,500.00
88,955.00
53,373.00
142,328.00 142,328.00
555.00 5,550.00
475.00 5,700.00
485.00 5,820.00
985.00 5,910.00
905.00 5,430.00
605.00 3,630.00
805.00 4,830.00
423.00 2,538.00
417.00 8,340.00
510.00 5,100.00
525.00 4,725.00
607.00 7,284.00
215.00 1,935.00
514.00 4,626.00
3,500.00 3,500.00
5,500.00 5,500.00
80,418.00
48,250.80
128,668.80 128,668.80
180.00 36,816.30
36,816.30
22,089.78
58,906.08 58,906.08
P 8,088,651.84
Conformed By:
PROJECT : PROPOSED TWO-STOREY RESIDENTIAL BUILDING
LOCATION : LOT 18, BLK 22, PHASE 1, XAVIER ESTATE, CDO
OWNER : MS. GINA CO
VIII. Roofing
A. Undersheeting
Marine Plywood 1/2" 342.00 sq.m 220.00 75,240.00
Self Drilling Screws 10,260.00 pcs 1.25 12,825.00
Screwbits 6.00 pc 55.00 330.00
Cost of Materials 88,395.00
Cost of Labor 27,360.00
Sub Total VIII - A 115,755.00 115,755.00
XII.Plumbing Works
Roughing-in
Emerald PVC pipe 4" S-1000 40.00 le 680.00 27,200.00
Emerald PVC pipe 3" S-900 35.00 le 510.00 17,850.00
Emerald PVC pipe,2" S-1000 30.00 le 240.00 7,200.00
PVC Fittings&Accessories 1.00 lot 10,500.0 10,500.00
Marine Epoxy A&B 1.00 gal 1,700.00 1,700.00
Multi-layer Cold Water Line Pipe,3/4" 64.00 mtrs 110.00 7,040.00
Multi-layer Cold Water Line Pipe,1/2" 55.00 mtrs 88.00 4,840.00
Multi-layer HOt Water Line Pipe,1/2" 45.00 mtrs 102.00 4,590.00
Fittings&Accessories 1.00 lot 15,750.00 15,750.00
Cost of Materials 96,670.00
Cost of Labor 38,500.00
Sub total XII 135,170.00 135,170.00
XIV.SOIL POISONING & WOOD PRESERVATIVES 358.50 sq.m. 80.00 28,680.00 28,680.00
Conforme:
MS. GINA CO
OWNER
175.00 GROUND
183.50 SECOND
34.45 GARAGE /PORCH
44.38 LANAA/SERVICE AREA
437.33 TOTAL FLOOR AREA
10,712.50
358.00
107,400.00
10,619.00
906.15466666667
62.298133333333
672.91111111111
196,020.00
2.88
64.00
253.50
342.23 7.16
118.83 11.93
572.00
105.93
21 1/3
175.00 GROUND
183.50 SECOND
34.45 GARAGE /PORCH
44.38 LANAA/SERVICE AREA
437.33 TOTAL FLOOR AREA
PROJECT : PROPOSED TWO-STOREY RESIDENTIAL BUILDING
LOCATION : LOT18, BLK22, PHASE 1, XAVIER ESTATE, CDO
OWNER : MS. GINA CO
SUBJECT: COST ESTIMATE (LABOR QUOTATION STRUCTURAL WORKS)
Item Description Item Total
I. Mobilization and General Requirements
Bunkhouse & Perimeter Inclusure 6,750.00
Building Processing 5,500.00
II. Earthworks
Excavation 27,613.20
Compaction/Grading 38,500.00
III. Forms and Scaffolding 107,400.00
IV. Reinforcing Bars 184,020.45
V. Concrete Works 147,600.00
VI. Masonry Works 196,020.00
VII. Roof Framing 42,750.00
VIII. Roofing
A. Undersheeting 27,360.00
B. Shingles & Bended Accessories by others
XII.Plumbing Works
Roughing-in 38,500.00
XIII. Electrical works
A. Roughing-In 57,902.25
XIV.SOIL POISONING & WOOD PRESERVATIVES by others
Conforme:
PROJECT : PROPOSED TWO-STOREY RESIDENTIAL BUILDING
LOCATION : LOT 18, BLK 22, PHASE 1, XAVIER ESTATE, CDO
OWNER : MS. GINA CO
FIRST DAY
Laminated sack 1 roll
Nylon (tangsi) 1 kilo
Garden hose 1/2" diam. 30 meters
G.I Coupling 1/2" diam. 1 pc
Ordinary Faucet 1/2" diam. 1 pc
Ordinary Bowl 1 pc
Corrugated G.I sheets gauge 26 x 10 ft. 12 pcs
Umbrella nails # 3 1 kilo
Pvc pipe 2" diam. 1 Le
Pvc pipe 3" diam. 1 Le
Ordinary Plywood 1/4" 20 pcs
Coco Lumber, 2x3x10' 500 Le
coco Lumber, 2x2x10' 300 Le
CWN # 4 5 boxes
CWN # 3 4 boxes
CWN # 2 1/2 3 boxes
CWN # 1 15 boxes
SECOND DAY
Def. Bars 10mm x 6.0m 300 le
Def. Bars 12mm x 6.0m 100 le
Def. Bars 16mm x 6.0m 300 le
G.I. Tie wire , ga.16 4 rolls
Hacksaw Blade 6 pcs
THIRD DAY
Portland Cement 300 bags
Wash Sand 6 cu.m
3/4 " crushed gravel 12 cu.m
VI. Masonry Works
A. Laying & Plastering
CHB 4" x 8" x 16", 10619 pcs
Portland Cement 906 bags
Washed sand 63 cu.m
Def. Bars 10mm 672 pcs
G.I. Tie wire , ga.16 84 kls
cost of materials
cost of labor
Sub-total VI - A
VIII. Roofing
A. Undersheeting
Marine Plywood 1/2" 342 sq.m
Self Drilling Screws 10260 pcs
Screwbits 6 pc
Cost of Materials
Cost of Labor
Sub Total VIII - A
XII.Plumbing Works
Roughing-in
Emerald PVC pipe 4" S-1000 40 le
Emerald PVC pipe 3" S-900 35 le
Emerald PVC pipe,2" S-1000 30 le
PVC Fittings&Accessories 1 lot
Marine Epoxy A&B 1 gal
Multi-layer Cold Water Line Pipe,3/4" 64 mtrs
Multi-layer Cold Water Line Pipe,1/2" 55 mtrs
Multi-layer HOt Water Line Pipe,1/2" 45 mtrs
Fittings&Accessories 1 lot
Cost of Materials
Cost of Labor
Sub total XII
196,020.00
2.88
64.00
253.50
342.23 7.16
118.83 11.93
572.00
105.93
21 1/3
PROJECT : PROPOSED TWO-STOREY RESIDENTIAL BUILDING
LOCATION : LOT 18, BLK 22, PHASE 1, XAVIER ESTATE, CDO
OWNER : MS. GINA CO
VIII. Roofing
A. Undersheeting
Marine Plywood 1/2" 342.00 sq.m 220.00 75,240.00
Self Drilling Screws 10,260.00 pcs 1.25 12,825.00
Screwbits 6.00 pc 55.00 330.00
Cost of Materials 88,395.00
Cost of Labor 27,360.00
Sub Total VIII - A 115,755.00
XII.Plumbing Works
Roughing-in
Emerald PVC pipe 4" S-1000 40.00 le 680.00 27,200.00
Emerald PVC pipe 3" S-900 35.00 le 510.00 17,850.00
Emerald PVC pipe,2" S-1000 30.00 le 240.00 7,200.00
PVC Fittings&Accessories 1.00 lot 10,500.0 10,500.00
Marine Epoxy A&B 1.00 gal 1,700.00 1,700.00
Multi-layer Cold Water Line Pipe,3/4" 64.00 mtrs 110.00 7,040.00
Multi-layer Cold Water Line Pipe,1/2" 55.00 mtrs 88.00 4,840.00
Multi-layer HOt Water Line Pipe,1/2" 45.00 mtrs 102.00 4,590.00
Fittings&Accessories 1.00 lot 15,750.00 15,750.00
Cost of Materials 96,670.00
Cost of Labor 38,500.00
Sub total XII 135,170.00
Conforme:
MS. GINA CO
OWNER
175.00 GROUND
183.50 SECOND
34.45 GARAGE /PORCH
44.38 LANAA/SERVICE AREA
437.33 TOTAL FLOOR AREA
Item Total
52,000.00
110,738.20
10,712.50
358.00
324,584.20 107,400.00
654,448.45
513,689.00
10,619.00
906.15466666667
62.298133333333
672.91111111111
196,020.00
581,339.00
139,458.00
2.88
115,755.00 64.00
253.50
342.23 7.16
118.83 11.93
572.00
105.93
497,056.56
21 1/3
135,170.00
223,337.25
28,680.00
3,376,255.66
168,812.78
253,219.17