DBT123 Chapter 5 - Setting Out
DBT123 Chapter 5 - Setting Out
CHAPTER 4:
SETTING OUT
Fieldwork Map/Plan
Map/Plan Fieldwork
2. Engineer :
Investigate the feasibility of the proposed project, to undertake
site investigation and prepare various solutions for the
employer’s consideration.
Act as independent arbiter and ensure that the works are
carried out in accordance with the drawings, specification, and
other conditions as laid out in the contract.
3. Contractor :
Chosen from the tenders submitted and a contract is formed
between the Employer and the Contractor.
AIMS OF SETTING OUT
AIMS
Horizontal Control
Points of known plan position (HORIZONTALLY) must be established
within or near the site from which the design points can be set out
in their correct plan positions.
Vertical control
Points of known elevation (VERTICALLY) relative to an agreed datum
are required within or near site from which the design points can be
set out at their correct reduced levels.
Positioning Techniques
Accurate methods must be adopted to establish design points from
this horizontal and vertical control.
PLANS AND DRAWINGS INVOLVE WITH
SETTING OUT
Site Plan
As-built Plan
PLANS AND DRAWINGS INVOLVE WITH SETTING
OUT
Site Plan
• Provide a series of horizontal and vertical control points which
may be used to help with any subsequent setting out.
• General arrangement of the new work in relation to the present
detail and form of site.
As-built Plan
• The drawing which shows all the alterations that have taken place
during the course of the works when the scheme completed.
GOOD WORKING PRACTICES
• These are horizontal control points and once they have been
located, they can be used with a positioning techniques to set
out E,N coordinates of the design points.
• On some schemes, the same control points that were used in the
production of the site plan prior to design work are used for
setting out. (they must be resurveyed!)
Baselines
Reference Grids
Offset pegs
BASELINES
1. Survey
Grid
Several
4. Secondary different grids
can be used in 2. Site Grid
Grid setting out.
3. Structural Grid
1. Survey Grid
Site Grid
points
3. Structural Grid
2ND STAGE
• CONTROL VERTICALITY OF ERECTED STRUCTURE(S)
METHOD:
PLUMBOP / THEODOLITE / OPTICAL PLUMBING / LASER
INSTRUMENTS:
PLUMBOP / THEODOLITE / OPTICAL PLUMB / LASER
SETTING OUT BUILDING
Control Points
Baseline
2nd stage :
a. Plumb-bob methods
b. Theodolite methods
c. Optical plumbing methods
d. Laser methods
SETTING OUT BUILDING