Overcurrent Study
Overcurrent Study
Commissioning of Substations
A Study of Power System Protection by Overcurrent Method
Power System protection: situation where overload current causes overheating of the
protected equipment.
is a branch of electrical power engineering that deals with the protection of
electrical power systems from faults through the isolation of faulted parts from The overcurrent protection is a bigger concept so that the overload
the rest of the electrical network. The objective of a protection scheme is to protection can be considered as a subset of overcurrent protection.
keep the power system stable by isolating only the components that are under The overcurrent relay can be used as overload (thermal) protection when
fault, while leaving as much of the network as possible still in operation. protecting the resistive loads, etc., however, for motor loads, the overcurrent
relay cannot serve as overload protection. Overload relays usually have a
1. Types of protection Schemes Protection schemes can be divided into two longer time setting than the overcurrent relays.
major groupings.
3. Types / Characteristics of Overcurrent Relays
1.1 Unit Type Protection:
2.3 Sensitive Earth Fault Protection: 1. Instantaneous Overcurrent Relay
Unit type schemes protect a specific area of the system, i.e., a transformer, 2. Definite Time Overcurrent Relay
transmission line, generator or bus bar. The unit protection scheme is The sensitive earth fault relay is a protective device that works by measuring the 3. Inverse Time Overcurrent Relay (IDMT Relay)
based on Kirchhoff's Current Law, sum of all the currents entering and residual current across the three phases and neutral (if available) in a system.
leaving a junction must be equal to zero. Any deviation from this must This is done using a Core Balance Current Transformer (CBCT). In the ideal
indicate a fault current. In these schemes, the effects of any disturbance or condition, the residual current will be zero as all the currents flowing through
operating condition outside the area of interest are totally ignored and the the three wires and neutral (if available) and their magnetic fields cancel each
protection is stable above the maximum possible fault current that could other out.
flow through the protected area.
In the event of a fault, the residual current over the three phases will not be
1.2 Non-Unit type protection: equal to zero as the current from the faulted phase flows through the earth.
Normally used on systems where the earth fault current is limited to a very low
The non-unit schemes, while also intended to protect specific areas but value (low or high impedance earthed systems) or if sensitive protection is
have no fixed boundaries. As well as protecting their own designated areas, required.
the protective zones can overlap into other areas. While this can be very
beneficial for backup purposes i.e an area to be isolated if a fault is
detected by non-unit schemes. 4. Instantaneous Overcurrent relay
The most simple of these schemes measures current and incorporates an Definite time relay operates instantaneously when the current reaches a
inverse time characteristic into the protection operation to allow predetermined value. Operates in a definite time when current exceeds its Pick-
protection nearer to the fault to operate first. up value. Its operation criterion is only current magnitude (without time delay).
adjusting the 'time dial setting / time multiplier'. The lowest time dial setting (fastest
operating time) is generally 0.05 and the slowest is 10.
4.2 Inverse Time Overcurrent Relays (IDMT Relay) IEC Normal inverse curve with different time multipliers (k) or (TD)
In this type / characteristic of relays, operating time is inversely changed with
current. So, high current will operate overcurrent relay faster than lower
ones. There are mainly standard inverse, very inverse and extremely inverse
types and several other manufacturers customized.
Inverse Time relays are also referred to as Inverse Definite Minimum Time
(IDMT) relay.
4. Time Graded Over Current Protection 4.2 Advantages of Definite Time Line Protection 5. Practical Exercise:
This may also be referred simply as over-current protection of electrical The main advantage of this scheme is simplicity. The second major Each participant to test Over current / Earth fault protection to measure,
power transmission line. Let' discuss different schemes of time graded advantage is, during fault, only nearest CB towards the source from fault
over current protection. point will operate to isolate the specific position of the line. • Pickup level
• Definite operate time
4.1 Protection by Definite Time Relay 4.3 Disadvantage of Definite Time Line Protection • Inverse operate time
• Draw definite & Inverse characteristics (at least two different time
The relay nearest to the end of the line has minimum time setting while If the number of sections in the line is quite large, the time setting of multipliers) by applying different fault currents via secondary
time setting of other relays successively increased, towards the source. relay nearest to the source, would be very long. So, during any fault injection instrument.
For example, suppose there is a source at point A nearer to the source will take much time to be isolated. This may cause
severe destructive effect on the system. An excel calculator is provided to each participant to verify tipping times at
different inverse time curves
4.4 Over Current Line Protection by Inverse Relay
At point D the circuit breaker CB-3 relay is installed with definite time of
relay operation 0.5 sec. Successively, at point “C” another circuit breaker
CB-2 relays is installed with definite time of relay operation 1 sec and
similarly relays at CB-1 & CB with increased times
Now, assume a fault occurs at point F. Due to this fault, the faulty current
flow through all the current transformers or CTs connected in the line.
But as the time of operation of relay at point D is minimum the CB-3
associated with this relay will trip first to isolate the faulty zone from rest
part of the line. In case due to any reason, CB-3 fails to trip, then next In the above figure, overall time setting of relay at point D is minimum
higher timed relay will operate the associated CB to trip. In this case, CB-2 and successively this time setting is increased for the relays associated
will trip. If CB-2 also fails to trip, then next circuit breaker i.e. CB-1 will trip with the points towards the point A. In case of any fault at point F will
to isolate major portion of the line. obviously trip CB-3 at point D. In failure of opening CB-3, CB-2 will be
operated as overall time setting is higher in relay at point C.
Although, the time setting of relay nearest to the source is maximum but
still it will trip in shorter period, if major fault occurs near the source, as
the time of operation of relay is inversely proportional to faulty current.
End of Training;
Hope after going through all above, each participant has a greater level of
understanding regarding overcurrent protection.