OT April 2022
OT April 2022
:
P6987 [5865] - 205
[Total No. of Pages :8
ii) The order in which machines are required for completing job is called as
a) Machine order b) Job order
c) Processing order d) Working order
iv) Problems based on the phenomenon of decision making under risk are
referred to as______.
a) Numerical problem b) Complex problem
c) Probabilistic problem d) None of above
[5865] - 205 1
P.T.O.
vi) As simulation is not an analytical model, therefore the result of simulation
must be viewed as
a) Unrealistic b) Exact
c) Approximation d) Simplified
vii) If in a LPP, the solution of a variable can be made infinity large without
violating the constraints, the solution is _______.
a) Infeasible b) Unbounded
c) Alternative d) None of the above
viii) In sequencing if smallest time for a job belongs to machine A then that
job has to placed towards ______ in the sequence.
a) right b) left
c) centre d) none of the Above
xvi) The minimin criterion is used when consequences are given in the form
of ______
a) Probabilities b) Table
c) Opportunity loss d) Payoff
xvii) Each player should follow the same strategy regardless of the other
player’s strategy in which of the following games?
a) Constant strategy b) Mixed strategy
c) Pure strategy d) Dominance strategy
xix) ________ are the entities whose values are to be determined from the
solution of the LPP.
a) Objective function b) Decision variables
c) Constraints d) Opportunity costs
[5865] - 205 3
Q2) a) Solve the following LPP [6]
Maximize Z 2 x1 x3
Subject to
x1 x2 x3 5
x1 2 x2 4 x3 8
x1 , x2 , x3 0
OR
Maximize Z 3x1 2 x2
Subject to constraints:
x1 x2 4
x1 x2 2
x1 , x2 0
[5865] - 205 4
Q3) a) The following information regarding a project is given [6]
Time in days
Activity Immediate Most Most Most
Predecessor optimistic likely pessimistic
A - 4 6 8
B A 5 7 15
C A 4 8 12
D B 15 20 25
E B 10 18 26
F C 8 9 16
G E 4 8 12
H D,F 1 2 3
I G,H 6 7 8
b) Consider the following profit table along with given probabilities of each
state. [6]
States
N1 N2 N3
Probabilities
Strategies 0.3 0.6 0.1
S1 20 18 9
S2 25 15 10
S3 40 10 12
Calculate
i) EMV
ii) EVPI
iii) VPI
OR
[5865] - 205 5
a) For the data given in the table below, draw the network, crash
systematically the activities and determine the optimal project duration
and cost. [6]
Time(week) Cost in Rs. (000)
Activity Normal Crash Crash
1-2 2 1 10 15
1-3 8 5 15 21
2-4 4 3 20 24
3-4 1 1 7 7
3-5 2 1 8 15
4-6 5 3 10 16
5-6 6 2 12 36
Each cycle costs his Rs. 7,000 and he sells them Rs. 10,000 each. Any
cycle that are left unsold at the end of the season must be disposed off
for Rs. 6,000 each. How many cycles should be in the stock so as to
maximize his expected profit?
[5865] - 205 6
b) The number of units of an item that are withdrawn from the inventory on
a day to day basis is a Markov chain process in which the requirements
for tomorrow depend on today’s requirements. A one-day transition matrix
is given below. [4]
Tomorrow
5 10 12
5 0.6 0.4 0.0
Today 10 0.3 0.3 0.4
12 0.1 0.3 0.6
OR
Find the elapsed time and idle times for machnies A and B.
b) The present market shares of three brands of soft drinks are 60%, 30%
and 10% respectively. The transition probability matrix is as follows:
[4]
[5865] - 205 7
Q5) a) Rainfall distribution in monsoon season as follows: [4]
Rain in cm 0 1 2 3 4 5
Probability 0.50 0.25 0.15 0.05 0.03 0.02
Simulate the rainfall for 10 days using following random numbers
67, 63, 39, 55, 29, 78, 70, 6, 78, 76. Find the average rainfall.
OR
a) A bakery keeps stock of a popular brand of cake. Previous experience
shows the daily demand pattern for the item with associated probabilities,
as given below: [4]
Daily demand 0 10 20 30 40 50
(number)
Probability 0.01 0.20 0.15 0.50 0.12 0.02
[5865] - 205 8