Lecture 5
Lecture 5
Physical Constraints
Resource Constraints
Productivity Constraints
Safety Constraints
Financial Constraints
Environmental Constraints
Management Constraints
Contractual Constraints
Regulatory Constraints
Activity Box
The format for activity box is not standardized, so one need only to adopt a format
that is comfortable for a particular application.
Critical Activity and Critical Path
Critical activity is quickly identified as one whose two start times at the left of
the activity box are equal. Also equal are the two finish times at the right of the
activity box.
The critical activities must form a continuous path from project beginning to
project end, this chain of critical activities is called the Critical Path.
The critical path is the longest path in the network.
The critical path is normally indicated on the diagram in some distinctive way
such as with colors, heavy lines, or double lines.
Any delay in the finish date of a critical activity, for whatever reason,
automatically prolongs project completion by the same amount.
Subcritical paths
Subcritical paths have varying degree of path float and hence
depart from criticality by varying amounts
Subcritical paths can be found in the following way:
Example 1: The activity list shown below represents the activities, the job logic and
the activities’ durations of a small project. Draw an activity on node network to
represent the project.
Solution
Example 2:
The activity list shown below represents the activities, the job logic and the
activities’ durations of a small project. Draw an activity on node network to represent
the project.
Solution
Step-1: Draw Activity diagram
When you have to draw an activity diagram. Pick the first activity and then see on
which it depends and then see on which these (i.e., predecessors) depend. For
example, to draw activity A, see activity D then see on which activity D depends and
so on.
ES t EF
Activity
LS TF LF
EF = ES + D
In forward pass you may encounter merge activities (e.g., S and R are merging to E)
whereas in backward pass you can encounter burst activities (e.g., A and C are
bursting from D)
LS = LF - D