TARIFF SCHEDULE TARIFF FOR SUPPLY OF ELECTRICITY AT LOW TENSION, HIGH TENSION, AND EXTRA HIGH TENSION Effective from 1st September, 2011 GENERAL 1. The tariff figures indicated in this tariff schedule are the tariff rates payable by the consumers of unbundled Distribution Licensees of the erstwhile GEB viz. UGVCL, DGVCL, MGVCL and PGVCL. 2. These tariffs are exclusive of Electricity Duty, tax on sale of electricity, taxes and other charges levied by the Government or other competent authorities from time to time which are payable by the consumers, in addition to the charges levied as per the tariff. 3. All these tariffs for power supply are applicable to only one point of supply. 4. The charges specified are on monthly basis. Distribution Licensee may decide the period of billing and adjust the tariff rate accordingly. 5. The energy supplied under these tariffs can be utilized only within the compact area of the premises not intervened by any area/road belonging to any person or authority other than the consumer. 6. Except in cases where the supply is used for the purpose for which the Distribution Licensee has permitted lower tariff, the power supplied to any consumer shall be utilized only for the purpose for which supply is taken and as provided for in the tariff. 7. Meter charges shall be applicable as prescribed under GERC (Licensees Power to Recover Expenditure incurred in providing supply and other Miscellaneous Charges) Regulations, 2005 as in force from time to time.
8. The various provisions of the GERC (licensees power to recover expenditure incurred in providing supply and other miscellaneous charges) Regulations will continue to apply. 9. Conversion of Ratings of electrical appliances and equipments from kilowatt to B.H.P. or vice versa will be done, when necessary, at the rate of 0.746 kilowatt equal to 1 B.H.P. 10. The Connected Load for the purpose of billing will be taken as the maximum load connected during the billing period. 11. The Fixed charges, minimum charges, demand charges, meter rent and the slabs of consumption of energy for energy charges mentioned shall not be subject to any adjustment on account of existence of any broken period within billing period arising from consumer supply being connected or disconnected any time within the duration of billing period for any reason. 12. Contract Demand shall mean the maximum kW for the supply of which licensee undertakes to provide facilities to the consumer from time to time. 13. Fuel Cost and Power Purchase Adjustment Charges shall be applicable in accordance with the Formula approved by the Gujarat Electricity Regulatory Commission from time to time. 14. Payment of penal charges for usage in excess of contract demand / load for any billing period does not entitle the consumer to draw in excess of contract demand / load as a matter of right. 15. The payment of power factor penalty does not exempt the consumer from taking steps to improve the power factor to the levels specified in the Regulations notified under the Electricity Act, 2003 and licensee shall be entitled to take any other action deemed necessary and authorized under the Act. 16. Delayed payment charges for all consumers: No delayed payment charges shall be levied if the bill is paid within ten days from the date
of billing (excluding date of billing). Delayed payment charges will be levied at the rate of 15% per annum in case of all consumers except Agricultural category for the period from the due date till the date of payment if the bill is paid after due date. Delayed payment charges will be levied at the rate of 12% per annum for the consumer governed under Rate AG from the due date till the date of payment if the bill is paid after due date. For Government dues, the delayed payment charges will be levied at the rate provided under the relevant Electricity Duty Act.
PART - I
1.0
Rate: RGP
This tariff is applicable to all services in the residential premises which are not covered under Rate: RGP (Rural) Category. Single-phase supply- Aggregate load upto 6kW Three-phase supply- Aggregate load above 6kW
1.1
Fixed Charges/Month:
Range of Connected Load: (Other than BPL Consumers) (a) (b) (c) (d) Upto and including 2 kW Above 2 to 4 kW Above 4 to 6 kW Above 6 kW For BPL Household Consumers: Fixed charges Rs. 5/- per month Rs. 5/- per month Rs. 15/- per month Rs. 30/- per month Rs. 45/- per month
PLUS 1.2 Energy Charges: For the total monthly consumption: (Other than BPL consumers)
First 50 units Next 50 units Next 150 units Above 250 units
295 Paise per Unit 325 Paise per Unit 390 Paise per Unit 480 Paise per Unit
1.3
Energy charges: For the total monthly consumption For the consumer below poverty line (BPL)**
(a) (c )
**The consumer who wants to avail the benefit of the above tariff has to produce a copy of the Card issued by the authority concerned at the sub-division office of the Distribution Licensee. The concessional tariff is only for 30 units per month.
1.4
Minimum bill (excluding meter charges) Payment of fixed charges as specified in 1.1 above.
2.0
This tariff is applicable to all services for residential premises located in areas within Gram Panchayat as defined in the Gujarat Panchayats Act. However, this is not applicable to villages which are located within the geographical jurisdiction of Urban Development Authority. Single-phase supply- Aggregate load upto 6kW Three-phase supply- Aggregate load above 6kW
2.1
Fixed Charges/Month:
Rs. 5/- per month Rs. 15/- per month Rs. 30/- per month Rs. 45/- per month
For BPL Household Consumers: Fixed charges Rs. 5/- per month
PLUS 2.2 Energy Charges: For the total monthly consumption: (Other than BPL consumers)
First 50 units Next 50 units Next 150 units Above 250 units
255 Paise per Unit 285 Paise per Unit 350 Paise per Unit 450 Paise per Unit
2.3 Energy charges: For the total monthly consumption For the consumer below poverty line (BPL) ** (a) (c) First 30 units For remaining units 150 Paise per Unit Rate as per RGP (Rural)
**The consumer who wants to avail the benefit of the above tariff has to produce a copy of the Card issued by the authority concerned at the sub-division office of the Distribution Licensee. The concessional tariff is only for 30 units per month.
2.4
Note: If the part of the residential premises is used for non-residential (commercial) purposes by the consumers located within Gram Panchayat as defined in Gujarat Panchayat Act, entire consumption will be charged under this tariff.
3.0
Rate: GLP
This tariff is applicable to the educational institutes and other institutions registered with the Charity Commissioner and research and development laboratories. (a) (b) Fixed charges Energy charges Rs. 45/- per month 345 Paise per Unit
4.0
Rate: Non-RGP
This tariff is applicable to the services for the premises those are not covered in any other tariff categories and having aggregate load upto and including 40kW.
4.1
Fixed charges per month: Rs. 30/- per kW Rs. 55/- per kW PLUS
4.2
Energy charges:
(a)
For installation having contracted load upto and including 10kW: for entire consumption during the month
(b)
For installation having contracted load exceeding 10kW: for entire consumption during the month
4.3
Minimum Bill Minimum bill per installation per month for consumers other than Seasonal Consumers: Rs. 140 per kW
4.4
Minimum Bill Per Installation for Seasonal Consumers (a) Seasonal Consumer, shall mean a consumer who takes and uses power supply for ice factory, ice candy machines, ginning and pressing factory, oil mill, rice
mill, huller, salt industry, sugar factory, khandsari, cold storage plants (including such plants in fisheries industry), tapioca industries manufacturing starch, etc. (b) Any consumer, who desires to be billed for the minimum charges on annual basis shall intimate to that effect in writing in advance about the off-season period during which energy consumption, if any, shall be mainly for overhauling of the plant and machinery. The total period of the off-season so declared and
observed shall be not less than three calendar months in a calendar year. (c) The total minimum amount under the head Fixed and Energy Charges payable by the seasonal consumer satisfying the eligibility criteria under sub-clause (a) above and complying with the provision stipulated under sub-clause (b) above shall be Rs. 1600/- per annum per kW of the contracted load. (d) The units consumed during the off-season period shall be charged for at a flat rate of 435 Paise per unit. (e) The electricity bills related to the off-season period shall not be taken into account towards the amount payable against the annual minimum bill. The amount paid by the consumer towards the electricity bills related to the seasonal period only under the heads Fixed Charges and Energy Charges, shall be taken into account while determining the amount of short-fall payable towards the annual minimum bill as specified under sub-clause (c) above.
5.0 Rate: LTMD This tariff is applicable to the services for the premises those are not covered in any other tariff categories and having aggregate load above 40kW and upto 100kW. This tariff shall also be applicable to consumer covered in category- Rate: Non-RGP so opts to be charged in place of Rate: Non-RGP tariff.
5.1
Fixed charges: For billing demand upto the contract demand (i) For first 40 kW of billing demand (ii) Next 20 kW of billing demand (iii) Above 60 kW of billing demand Rs. 65/- per kW per month Rs. 100/- per kW per month Rs. 165/- per kW per month Rs. 210/- per kW
(a)
(b)
PLUS
5.3 Reactive Energy Charges: For all the reactive units (KVARH) drawn during the month 10 paise per KVARH
5.4
Billing Demand
The billing demand shall be highest of the following, rounded to the next full kW: (a) (b) (c) Eighty-five percent of the contract demand Actual maximum demand registered during the month 15 kW
5.5 Minimum Bill Payment of demand charges every month based on the billing demand.
5.6 Seasonal Consumers taking LTMD Supply: 5.6.1 The expression, Seasonal Consumer, shall mean a consumer who takes and uses power supply for ice factory, ice-candy machines, ginning and pressing factory, oil mill, rice mill, salt industry, sugar factory, khandsari, cold storage plants (including such plants in fishery industry), tapioca industries manufacturing starch, pumping load or irrigation, white coal manufacturers etc.
5.6.2
A consumer, who desires to be billed for minimum charges on annual basis, shall intimate in writing in advance about the off-season during which energy consumption, if any, shall be mainly for overhauling of the plant and machinery. The off-season period at any time shall be a full calendar month/months. The total period of offseason so declared and observed shall be not less than three calendar months in a calendar year.
5.6.3 The total minimum amount under the head Demand and Energy Charges payable by a seasonal consumer satisfying the eligibility criteria under sub clause 5.6.1 above and complying with provisions stipulated under sub clause 5.6.2 above shall be Rs. 2700/per annum per kW of the billing demand.
The billing demand shall be the highest of the following: The highest of the actual maximum demand registered during the calendar year. Eighty-five percent of the arithmetic average of contract demand during the year. (c) 15 kW.
5.6.5 Units consumed during the off-season period shall be charged for at the flat rate of 435 Paise per unit.
6.0 Rate: Non-RGP Night This tariff is applicable for aggregate load upto 40kW and using electricity exclusively during night hours from 10.00 PM to 06.00 AM next day. (The supply hours shall be regulated through time switch to be provided by the consumer at his cost.) 6.1 Fixed Charges per month: Fixed charges specified in Rate Non-RGP above. PLUS 6.2 Energy Charges: For entire consumption during the month 220 Paise per Unit
NOTE: 1. 10% of total units consumed and 15% of the contract load can be availed beyond the prescribed hours. 2. This tariff shall be applicable if the consumer so opts to be charged in place of Non-RGP tariff by using electricity exclusively during night hours as above. 3. The option can be exercised to switch over from Non-RGP tariff to Non-RGP Night tariff and vice versa twice in a calendar year by giving not less than one months notice in writing. 4. In case the consumer is not fulfilling the conditions of this tariff category, then such consumer for the relevant billing period will be billed under tariff category Non-RGP. 7.0 Rate: LTMD- Night This tariff is applicable for aggregate load above 40kW and using electricity exclusively during night hours from 10.00 PM to 06.00 AM next day. (The supply hours shall be regulated through time switch to be provided by the consumer at his cost.)
7.1 Fixed Charges per month: Fixed charges specified in Rate LTMD above. PLUS 7.2 Energy Charges: For entire consumption during the month 220 Paise per Unit
7.3 Reactive Energy Charges: For all reactive units (KVARH) drawn during the month 10 Paise per KVARH
NOTE: 5. 10% of total units consumed and 15% of the contract load can be availed beyond the prescribed hours. 6. This tariff shall be applicable if the consumer so opts to be charged in place of LTMD tariff by using electricity exclusively during night hours as above. 7. The option can be exercised to switch over from LTMD tariff to LTMD- Night tariff and vice versa twice in a calendar year by giving not less than one months notice in writing. 8. In case the consumer is not fulfilling the conditions of this tariff category, then such consumer for the relevant billing period will be billed under tariff category LTMD. 8.0 Rate: LTP- Lift Irrigation
Applicable for supply of electricity to Low Tension Agricultural consumers contracting load up to 125 HP requiring continuous (twenty-four hours) power supply for lifting water from surface water sources such as cannel, river, & dam and supplying water directly to the fields of farmers for agricultural irrigation only.
(a)
(b)
9.0
Rate: WWSP
This tariff shall be applicable to services used for water works and sewerage pumping purposes.
9.1
Type I Water works and sewerage pumps operated by other than local authority:
(a)
Rs.15/- per HP
(b)
Energy charges per month: For entire consumption during the month
9.2
Type II Water works and sewerage pumps operated by local authority such as Municipal Corporation. Gujarat Water Supply & Sewerage Board located outside Gram Panchayat Area will also attract this tariff:
(a)
Rs.9 per HP
(b)
Energy charges per month: For entire consumption during the month
9.3
Type III Water works and sewerage pumps operated by Municipalities/Nagarpalikas and Gram Panchayat or Gujarat Water Supply & Sewerage Board for its installations located in Gram Panchayats:
Energy charges per month: For entire consumption during the month
275 Paise/Unit
9.4
Applicable to all the water works consumers having connected load of 50 HP and above for the Energy consumption during the Off-Peak Load Hours of the Day.
For energy consumption during the off-peak period, viz., 1100 Hrs to 1800 Hrs. For energy consumption during night hours, viz., 2200 Hrs to 0600 Hrs. next day
10.0
Rate: AG
This tariff is applicable to services used for irrigation purposes only excluding installations covered under LTP- Lift Irrigation category.
10.1
Rs.175/HP/month
NOTE: The consumers under Tatkal Scheme shall be eligible for normal metered tariff as above, on completion of five years period from the date of commencement of supply.
10.2
No machinery other than pump water for irrigation (and a single bulb or CFL upto 40 watts) will be permitted under this tariff. Any other machinery connected in the installation governed under this tariff shall be charged separately at appropriate tariff for which consumers shall have to take separate connection.
10.3
Agricultural consumers who desire to supply water to brick manufacturing units shall have to pay Rs. 100/HP per annum subject to minimum of Rs. 2000/- per year for each brick Mfg. Unit to which water is supplied in addition to existing rate of HP based / metered agricultural tariff.
10.4
Such Agricultural consumers shall have to pay the above charges for a full financial year irrespective of whether they supply water to the brick manufacturing unit for full or part of the Financial Year. Agricultural consumers shall have to declare their intension for supply of the water to such brick manufacturing units in advance and pay charges accordingly before commencement of the financial year (i.e. in March every year).
11.0
Rate: SL
11.1
Tariff for Street Light for Local Authorities and Industrial Estates:
This tariff includes the provision of maintenance, operation and control of the street lighting system.
11.1.2 Optional kVAh Charges: For all the kVAh units consumed during the month: 270 Paise per Unit
11.1.3 Renewal and Replacements of Lamps: The consumer shall arrange for renewal and replacement of lamp at his cost by person authorised by him in this behalf under Rule-3 of the Indian Electricity Rules, 1956 / Rules issued by CEA under the Electricity Act, 2003.
11.2
Tariff for power supply for street lighting purposes to consumers other than the local authorities and industrial estates:
11.2.2 Energy charges: For all units consumed during the month 360 Paise per kWh
The consumer shall arrange for renewal and replacement of lamp at his cost by person authorised by him in this behalf under Rule-3 of the Indian Electricity Rules, 1956 / Rules issued by CEA under the Electricity Act, 2003.
11.2.4 Maintenance other than Replacement of Lamps: Maintenance of the street lighting system shall be carried out by Distribution Licensee.
12.0
Rate: TMP
This tariff is applicable to services of electricity supply for temporary period at the low voltage.
12.1
Note: Payment of bills is to be made within seven days from the date of issue of
the bill. Supply would be disconnected for non-payment of dues on 24 hours notice.
PART-II TARIFFS FOR SUPPLY OF ELECTRICITY AT HIGH TENSION (3.3 KV AND ABOVE, 3-PHASE 50 C/S), AND EXTRA HIGH TENSION
The following tariffs are available for supply at high tension for large power services for contract demand not less than 100 kVA
13.0
Rate: HTP-I
This tariff will be applicable for supply of electricity to HT consumers contracted for 100 kVA and above for regular power supply and requiring the power supply for the purposes not specified in any other HT Categories.
13.1
Demand Charges;
13.1.1 For billing demand upto contract demand (a) (b) (d) For first 500 kVA of billing demand For next 500 kVA of billing demand For billing demand in excess of 1000 kVA Rs. 100/- per kVA per month Rs. 200/- per kVA per month Rs. 270/- per kVA per month
13.1.2 For Billing Demand in Excess of Contract Demand For billing demand in excess over the contract demand Rs. 370 per kVA per month
For entire consumption during the month (b) (c) (d) upto 500 kVA of billing demand For next 2000 kVA of billing demand For billing demand in excess of 2500 kVA 390 Paise per Unit 410 paise per Unit 420 Paise per Unit
PLUS 13.3 Time of Use Charges: For energy consumption during the two peak periods, viz., 0700 Hrs to 1100 Hrs and 1800 Hrs to 2200 Hrs (a) For Billing Demand upto 500kVA (b) For Billing Demand above 500kVA 35 Paise per Unit 75 Paise per Unit
13.4
Billing Demand:
The billing demand shall be the highest of the following: (a) Actual maximum demand established during the month (b) Eighty-five percent of the contract demand (c) One hundred kVA
13.5
Minimum Bills:
13.6
13.6.1 Penalty for poor Power Factor: (a) The power factor adjustment charges shall be levied at the rate of 1% on the total amount of electricity bills for the month under the head Energy Charges for every 1% drop or part thereof in the average power factor during the month below 90% upto 85%. (b) In addition to the above clause, for every 1% drop or part thereof in average power factor during the month below 85% at the rate of 2% on the total amount of electricity bill for that month under the head Energy Charges, will be charged. 13.6.2 Power Factor Rebate: If the power factor of the consumers installation in any month is above 95%, the
consumer will be entitled to a rebate at the rate of 0.5% (half percent) in excess of 95% power factor on the total amount of electricity bill for that month under the head Energy Charges for every 1% rise or part thereof in the average power factor during the month above 95%.
13.7
The maximum demand in kW or kVA, as the case may be, shall mean an average KW/KVA supplied during consecutive 30/15 minutes or if consumer is having parallel operation with the grid and has opted for 3 minutes, period of maximum use where such meter with the features of reading the maximum demand in KW/KVA directly, have been provided.
13.8
Contract Demand:
The contract demand shall mean the maximum KW/KVA for the supply, of which the supplier undertakes to provide facilities from time to time.
13.9
On Energy charges: (a) (b) If supply is availed at 33/66 kV If supply is availed at 132 kV and above
13.10 Concession for Use of Electricity during Night Hours: For the consumer eligible for using supply at any time during 24 hours, entire consumption shall be billed at the energy charges specified above. However, the energy consumed during night hours of 10.00 PM to 06.00 AM next morning (recorded by a polyphase meter operated through time-switch) as is in excess of one third of the total energy consumed during the month, shall be eligible for concession at the rate of 75 Paise per unit. The polyphase meter and time switch shall be procured and installed by the consumer at his cost and sealed by the Distribution Licensee.
5.7 Seasonal Consumers taking HT Supply: 13.11.1 The expression, Seasonal Consumer, shall mean a consumer who takes and uses power supply for ice factory, ice-candy machines, ginning and pressing factory, oil mill, rice mill, salt industry, sugar factory, khandsari, cold storage plants (including such plants in fishery industry), tapioca industries manufacturing starch, pumping load or irrigation, white coal manufacturers etc.
13.11.2 A consumer, who desires to be billed for minimum charges on annual basis, shall intimate in writing in advance about the off-season during which energy consumption, if any, shall be mainly for overhauling of the plant and machinery. The off-season period at any time shall be a full calendar month/months. The total period of offseason so declared and observed shall be not less than three calendar months in a calendar year.
13.11.3 The total minimum amount under the head Demand and Energy Charges payable by a seasonal consumer satisfying the eligibility criteria under sub clause 13.12.1 above and complying with provisions stipulated under sub clauses 13.12.2 above shall be Rs.4000/per annum per kVA of the billing demand.
The billing demand shall be the highest of the following: The highest of the actual maximum demand registered during the calendar year. Eighty-five percent of the arithmetic average of contract demand during the year.
(f) 13.11.5
One hundred kVA. Units consumed during the off-season period shall be charged for at the flat rate
13.11.6
Electricity bills paid during off-season period shall not be taken into account
towards the amount payable against the annual minimum bill. The amount paid by the consumer towards the electricity bills for seasonal period only under the heads Demand Charges and Energy Charges shall be taken into account while determining the amount payable towards the annual minimum bill.
14.0
Rate HTP-II
Applicability: This tariff shall be applicable for supply of energy to HT consumers contracting for 100 KVA and above, requiring power supply for Water Works and Sewerage pumping stations run by Local Authorities and GW & SB. GIDC Water Works.
14.1
Demand Charges:
14.1.1 For billing demand upto contract demand (a) (b) (c) For first 500 kVA of billing demand For next 500 kVA of billing demand For billing demand in excess of 1000 kVA Rs.90/- per kVA per month Rs.190/- per kVA per month Rs.250/- per kVA per month
14.1.2 For billing demand in excess of contract demand For billing demand in excess of contract demand Rs.335 per kVA per month
For entire consumption during the month (b) (c) (d) upto 500 kVA of billing demand For next 2000 kVA of billing demand For billing demand in excess of 2500 kVA 390 Paise per Unit 410 Paise per Unit 420 Paise per Unit
PLUS
14.3
For energy consumption during the two peak periods, viz., 0700 Hrs to 1100 Hrs and 1800 Hrs to 2200 Hrs (a) For Billing Demand upto 500kVA (b) For Billing Demand above 500kVA 35 Paise per Unit 75 Paise per Unit
Billing demand Minimum bill Power Factor Adjustment Charges Maximum demand and its measurement Contract Demand Rebate for supply at EHV Same as per HTP-I Tariff
15.0
Rate: HTP-III
This tariff shall be applicable to a consumer taking supply of electricity at high voltage, contracting for not less than 100 kVA for temporary period. A consumer not taking supply on regular basis under a proper agreement shall be deemed to be taking supply for temporary period.
15.1
Demand Charges: Rs.462/- per kVA per month Rs. 550/- per kVA per month
For billing demand upto contract demand For billing demand in excess of contract demand
PLUS
15.3
Additional charge for energy consumption during two peak periods, viz., 0700 Hrs to 1100 Hrs and 1800 Hrs to 2200 75 Paise per Unit Hrs
Billing demand Minimum bill Power Factor Adjustment Charges Maximum demand and its measurement Contract Demand Rebate for supply at EHV Same as per HTP-I Tariff
16.0
Rate: HTP-IV
This tariff shall be applicable for supply of electricity to HT consumers opting to use electricity exclusively during night hours from 10.00 PM to 06.00 AM next day and contracted for regular power supply of 100 kVA and above.
16.1
Demand Charges:
PLUS
16.2
Billing demand Minimum bill Power Factor Adjustment Charges Maximum demand and its measurement Same as per HTP-I Tariff
16.7 16.8
NOTE: 1. 10% of total units consumed and 15% of the contract demand can be availed beyond the prescribed hours for the purpose of maintenance. 2. For the purpose of office lighting, fans etc. the consumer may apply for a separate connection. 3. This tariff shall be applicable if the consumer so opts to be charged in place of HTP-I tariff by using electricity exclusively during night hours as above. 4. The option can be exercised to switch over from HTP-I tariff to HTP-IV tariff and vice versa twice in a calendar year by giving not less than one months notice in writing. 5. In case the consumer is not fulfilling the conditions of this tariff category, then such consumer for the relevant billing period will be billed under tariff category HTP-I. 17.0 Rate: HTP- V HT - Agricultural (for HT Lift Irrigation scheme only) This tariff shall be applicable for supply of electricity to High Tension Agricultural consumers contracting for 100 kVA and above, requiring power supply for lifting water from surface water sources such as canal, river and dam, and supplying water directly to the fields of farmers for agricultural irrigation only.
17.1
Demand Charges:
Demand Charges Rs. 25 per kVA per Month PLUS 17.2 Energy Charges: 160 Paise per Unit
Billing demand Minimum bill Power Factor Adjustment Charges Maximum demand and its measurement Contract Demand Rebate for supply at EHV Same as per HTP-I Tariff
18.0
This tariff is applicable for power supply to Railway Traction at 132 kV/66 kV.
18.1
Demand Charges:
(a) For billing demand upto the contract demand (b) For billing demand in excess of contract demand
Rs. 160 per kVA per month Rs. 400 per kVA per month
NOTE: In case of the load transfer for traction supply due to non-availability of power supply at preceding or succeeding point of supply or maintenance at Discoms level, excess demand over the contract demand shall be charged at normal rate at appropriate point of supply.
Normal Demand Charges will also apply in case of bunching of trains. However, Discoms shall charge excess demand charges while raising the bills and Railways have to give convincing details and documentary proof of bunching of trains if they want to be charged at the normal demand charges. If satisfactory proof of bunching of trains is provided, Discom shall consider that occasion for normal demand charges, otherwise excess demand charges will be applicable specified as above at 18.1(b). PLUS 18.2 Energy Charges:
Billing demand Minimum bill Power Factor Adjustment Charges Maximum demand and its measurement Contract Demand Rebate for supply at EHV Same as per HTP-I Tariff