MS For The Drainage Pipes Installation & Testing
MS For The Drainage Pipes Installation & Testing
PROJECT DETAILS
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 2
Rev. No. Date By Chkd. Approvals Description and Page Numbers of Revisions
0
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 3
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENTS
7.0 PROCEDURE
8.0 ATTACHMENTS
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 4
1.0 PURPOSE
This method statement is applicable for Installation & testing of all types drainage piping system in all
areas for the project.
2.0 SCOPE
Supply , installation & testing of drainage piping system for all applications in line with project requirments .
3.0 REFERENCE
3.1 Latest Approved shop drawings for the required and applicable areas for Drainage.
3.2 Specification:
3.3 ISO 9001:2008.
3.4 Project Quality Plan
3.5 Material Approval Requist references:
4.0 DEFINITIONS
5.0RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant
steps in the procedure:
Project Manager
Construction manager
QA/QC Engineer
Site Engineer
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 5
HSE officer
SK
The work progress shall be carried out as per planned program and all the equipment’s required to
execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer
and QA/QC Engineer and in line with PSP and PQP.
The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
Provision of all necessary information and distribution of responsibilities to his Construction team.
The work progress shall be monitored in accordance with the planned work program and he will provide
reports to his superiors.
The constant coordination with the Safety Engineer to ensure that the works are carried out in safe
working atmosphere.
The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the
Inspection for the finished works.
He will ensure the implementation of any request that might be raised by the Consultant.
Efficient daily progress shall be obtained for all the equipment and manpower.
He will engage in the work and check the same against the daily report received from the Foremen.
The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.
The monitoring of executions of works at site and should be as per the approved shop drawings and
project specifications.
Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
He will follow and carried out all the relevant tests as per project specifications.
The carrying-out of work and the proper distribution of all the available resources in coordination with
the Site Engineer on a daily basis.
Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer
immediately.
The implementation of all safety measures in accordance with the HSE plan and that the whole work
force is aware of its proper implementation.
The implementation of safety measures is adequate to maintain a safe working environment on the work
activity.
Inspection of all the site activities and training personnel in accident prevention and its proper reporting
to the Construction Manager and the Project Manager.
Ensure all concerned personals shall use PPE and all other items as required.
Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.
Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in
suitable area that will keep the material in safe from rusty and damage.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 7
6.0 EQUIPMENTS
7.0 PROCEDURE
7.2 Handling
During transportation pipes must be handled with care. Do not drop or drag pipes especially on
hard surfaces. This is particularly important where the pipe ends have been pre-prepared in the
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 8
7.3 Storage
Drainage Pipes should be stored on a flat dry level surface free from sharp projections, stones or other
objects likely to cause point loading or pipe deformation. Timber supports spaced 1.5m apart along the
pipe can be used to support the pipes. The width of the stack should not exceed 3m.
Pipes of different sizes should be stacked separately or where this is not possible, hose with larger
diameters and/or thicker walls should be placed at the bottom of the stack. The height of the stack
should never exceed 7 layers or maximum 2m high.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 9
All pipes and fittings should be properly covered with tarpaulins to protect them from UV rays. The
tarpaulins are to be fixed to the wooden supports, which allow a free passage of air around the pipes.
Fittings will be stored in sheltered conditions in the boxes as supplied to protect them from weathering
and accidental damage.
The vichele should have flat bed freefrom sharp projections of any kinds. Also the pipes must be
supported strongly inside the vichel and should not overhand pipe lengh more than 1 meter.
The larger size and thicker pipes shold be loaded first. And for more information you can check the
below photo.
where applicable .
Proceed with pipe Installation with the appropriate Slope and Route as per the approved Shop
Drawing using suspended supporting system as per the project specification & leakage test to be
applied to insure no leakage from joints & pipes.
Pipes joint shall not place in the passage of pipes through the concrete wall.
Check all the joints and pipe slope before closed the false ceiling or shafts.
Using a brush apply an even layer solvent cement to the spigot and socket mating surfaces.
The cement should be applied in a lengthwise direction and not with a circular motion.
The cement should be applied simultaneously to the spigot and socket by two people.
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 11
Immediately following cement application ensure that the pipe is suitably anchored, and push the
spigot home in the socket without turning the pipe. The spigot should be inserted with a steady,
continuous motion and held in place for 20 seconds. Remove the surplus cement from around the
mouth of the socket.
Leave the joint undisturbed for five minutes, and then handle with reasonable care.
Plug all open ends of the pipe work.
Compaction for the full width of the pipe shall be to at least 95% Modified Proctor Density, and
then same shall be tested and approved by site Civil engineer.
Mark routing and install the pipes as per approved shop drawings
All horizontal drainage piping for sizes Ø100mm and above shall be installed with 1 % minimum slope
and 2% for sizes less than Ø100mm unless otherwise indicated.
Sanitary tees and short sweep ¼ bends may be used if change in direction of flow is from
horizontal to vertical.
Use long turn double Y-branch and 1/8 bend fittings if two fixtures are installed back to back or
side by side with common drain pipe.
Do not change the direction of flow more than 90 degrees.
Use the proper size of standard increasers and reducers if pipes different sizes are connected.
Reducing the size of drainage piping in direction of flow is prohibited.
Check all the joints and pipe slope before proceed with 150 mm Thick concrete encasement.
The spigot and the socket to be joined must be carefully examined for any damages.
The pipe should be chamfered to a depth of half the wall thickness and at an inclination of 15 O to
the pipe axis.
Check chambered spigot should be clean and free from burrs as well the sealing ring should be
correctly seated in the socket groove complete with the inserted ring.
The spigot insertion depth should be measured and marked -as per below photos-.
The mating areas of the spigot and socket should be thoroughly cleaned (All grease, dirt and
other foreign matter should be removed from the sealing area -as per the below photo-.
Push – fit joint shall be used for manhole (Inlet – outlet) as per approved details drawing.
Concrete encasement shall be not used above push fit joint (special method should be used) detail
for the same shall be approved by consultant.
The spigot end and triple sealing portion of the sealing ring should be lubricated with the
recommended lubricant as per below photo-. The spigot should be lubricant to the full insertion
depth and around its complete circumference.
Immediately after lubrication, the spigot should be brought into contact with the socket and the
PROJECT NAME
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
INSTALLATION & TESTING OF DRAINAGE PIPING SYSTEM AND ACCESSORIES Date :
Page 13
parent joint should be accurately aligned so those axes of pipes are precisely in line.
The spigot should be hand fed into the socket until resistance from the inner sealing selection is
felt.
Correct alignment at this stage is essential to ensure that the rubber sealing ring is not pinched or
torn.
Joints shall be carried out using electro weld sleeve couplings – as shown in below photo- :
in the outpouring of HDPE or wire movement. The movement of the pipe can cause melted HDPE
to flow out of the joint. This can result in wire movement and possibly a short circuit and thus a
bad weld or fire hazard.
7.5Leak Testing
The piping system to be tested shall be closed by plugging and blanking all openings in the system
in an approved manner.
Suitable plugs are inserted at the lower end of the drain or sewer and at the head of any
connections.
A suitable bend together with a vertical length of pipe is fitted at the head of the sewer or drain to
provide the necessary test head. The system then filled with water.
Close openings in piping system and fill with water to point of overflow but less than 10-foot head
of water (30 KPa) from before 15 minutes before starts to completion of inspection. Water level
must not drop and inspect joints for leak & this test is applicable for gravity system.
The sewer or drain under test should be left filled with water for min 2hours.
For pressurized piping system the recommended pressure test to be applied is 1.5 Times the
operating pressure. (Using manual pressure pump & recommended rating Plugs).
So ensure that all piping and joints are no leak.
During the water test, precautions should be taken to prevent any movement of the drain or sewer.
All ends shall be plugged after completion of test to protect from debris.
After successful testing & Inspection of pipe work, covering of pipe work can proceed as per
approved drawing details.
7.6 Backfilling
I. Embedded in concrete
All piping (HDPE, UPVC) cross with roads shall be encased in concrete with 150 mm cover on all
sides as required by local authorities. Provide thrust blocks at every change in direction. Thrust
blocks shall be of 20 MPa concrete poured against undisturbed soil.
Provide warning tapes or detectable warning tapes based on the type of pipe material, contractor
has to specify the right one before final back filling.
Provide polyethylene bond breaker between concrete and pipe. Unless indicated otherwise, all
piping with less than 1 meter cover shall be encased in concrete with 150mm cover on all sides, as
described above. ( Refer to Specs. 230500 page #.1)
8.0 ATTACHMENTS
Check Sheet
Check Sheet
Risk Assessment