Seal Design and Construction (Additional Notes)
Seal Design and Construction (Additional Notes)
COURSE
ON
(A DDITIONAL N OTES }
June 2007
LIST OF CONTENTS
1 INTRODUCTION............................................................................................... 3
3 SEAL SELECTION............................................................................................4
4 SURFACING EQUIPMENT...............................................................................5
6 TRAFFIC CONTROL.......................................................................................18
APPENDICES
This document titled “ Additional Notes ”, provides information not necessarily covered in TRH3.
During presentation of each course, additional but relevant information is either discussed during the course
or requested by participants. The purpose of this document is, therefore, to provide such information to
participants and to keep record of information required for future upgrading of the TRH3 and other relevant
documents.
Cape seal consists of a bituminous binder followed by a layer of 19,0mm or 13,2 mm stone followed
by one or two applications of slurry.
Sand seal is an application of binder covered with sand. It is used to improve the texture of an existing
surface and to waterproof it. It is also used in new construction as a single surface treatment (using
sand instead of stone) for lightly trafficked roads.
Dust palliative is a spray of emulsion or cutback bitumen to lay dust. Polymers are sometimes added
to these products. It is also used as a binder for surface dressings on temporary deviations or lightly
trafficked roads.
Rejuvenators are used as a temporary measure to restore some life to weathered and oxidised road
surfaces, applied in the same way as a fog spray.
Fog seal is a light application of emulsion, usually diluted 50 percent with water. It is sprayed after the
final stone application and ensures the adhesion of the top layer of chips by coating them completely
with binder. It is also used to renew old asphalt surfaces and seal hairline cracks.
Slurry seal and micro surfacing are mixtures of emulsion, fine aggregate, (usually crusher dust)
mineral filler and water. It is used to fill the voids between chips as in the popular Cape Seal, or to
restore old surfaces to a uniform surface texture. It also prevents water entering the pavement. It is
normally not used without a chip and spray treatment in new construction. Micro surfacing has
superior setting and adhesion properties compared against normal slurry seal.
A choked seal can be described as an open single seal, choked with a smaller aggregate, without the
application of a binder penetration coat
The Otta seal was developed by the Norwegian Roads Research Laboratory during the early 1960’s
and refers to the Otta valley where it was first used The seal consists of graded aggregates (natural
gravel or crushed rock) in combination with soft (low viscosity) binders.
3 SEAL SELECTION
Notes:
Skid resistance is dependent on both micro texture and macro texture.
4.1 GENERAL
All plant and equipment must be of adequate capacity for the project at hand, and be in good working order,
operated only by properly qualified operators.
The Binder distributor is one of the most important pieces of equipment on a paving project, prime coat, and
tack coat or surface treatment operation. It is made specifically to apply liquid bitumen material uniformly and
in proper quantities to a roadway surface.
The person in charge must ensure that the distributor has a valid calibration certificate before spraying
commences. The sprayer and equipment shall only be driven and operated by suitably qualified people.
Chip spreaders are normally self-propelled and can be adjusted to various widths. Truck mounted chip
spreaders are used at times, Chip spreaders must be capable of:
o Spreading the stone chips uniformly over any width in the range of 1,5 m to a full lane width.
o Be able to control the rate of application.
Design and Construction of Surfacing seals (Additional notes)
Asphalt Academy, Pretoria, South Africa Version 1-1, June 2007 5
o Stopping and starting without forming a joint line, and
o Keeping pace with the binder distributor.
o Producing a flat even layer of stone - free of ripples corrugations and unevenness
4.4 ROLLERS
4.4.1 General
Sufficient rollers of each type must be available on site to maintain the required tempo of work and be so
ballasted as not to cause crushing of the aggregate.
Pneumatic-type rollers must be self-propelled with smooth pneumatic tyres of uniform size and diameter.
The wheels must be so positioned that the tracks of the back wheels overlap the tracks of the front wheels.
4.5 BROOMS
Drag brooms must be of the size, type and capable of distributing the stone chips evenly over the surface
without dislodging the stone chips from the binder.
These must be made available on site at all times during surfacing work. They are used for cleaning the road
prior to the seal application. A mechanical broom can be used to clean the road at any time providing that no
aggregate is dislodged from the binder.
The basic equipment required for mixing and laying slurry seal consists of a special mixer mounted on a
truck and a spreader box towed behind the truck. This equipment is known as a slurry machine.
The mixer must be capable of mixing the slurry seal to a uniform blended consistency. The spreader box for
slurry must be capable of spreading a slurry seal mix in a uniform application.
Or slurry can be mixed in a small concrete (hand) mixer; this is usually limited to small surface area tasks.
More sophisticated controls are required on the machine when mixing and spreading micro surfacing.
Design and Construction of Surfacing seals (Additional notes)
Asphalt Academy, Pretoria, South Africa Version 1-1, June 2007 7
4.6.1 Miscellaneous equipment
Sufficient equipment for loading, handling, and hauling aggregate and binder to ensure prompt delivery must
be available. The contractor must also have available on site all the necessary auxiliary equipment, including
facilities for pre-coating of aggregate (when required), hand spraying equipment and hand tools to carry out
the work efficiently.
Poor performance of seals can often be traced back to inadequate planning for sealing and poor preparation
of existing surfaces prior to resealing.
Visual inspections, using TMH 9 as a guide must be carried out to determine the type and extent of failure,
the type of resealing required and the pre-seal repairs necessary.
Roads to be resealed must be repaired well in advance, including the correction of faulty drainage. One of
the most common mistakes made in repair work is that the repair is not dense enough to stop the passage of
water. In practice it is quite easy to determine the density by pouring a bucket of water over the freshly
prepared base. The water will be absorbed by the surface if it is not dense and waterproof.
Because planning and communication are so essential for successful paving operations, a pre-paving
construction conference should be held before work begins. Such a conference allows the Resident
Engineer, the Contractor’s personnel, Traffic Control personnel, Trucking personnel, and others directly
involved with the operation the opportunity to discuss topics such as the following and to plan the surfacing
operation accordingly:
Safety
Continuity and sequence of operations,
Number and types of rollers needed,
Number of trucks required,
The chain of command for giving and receiving instructions
Weather and temperature requirements, restrictions,
Intermingling of aggregate from different sources,
Construction of control strips,
Traffic control
Once the pre-seal repairs have been completed the actual sealing operation must be planned in detail. This
applies to new seals and resealing contracts. The work of construction starts with the planning back in the
office with scheduling, site inspection, organizing materials, and
plant. Then on site, before the work can begin, there is the site
organisation itself. Only then can the actual work process take
place.
All site activities need to be scheduled in accordance with
.
5.3 PLANNING OF MATERIALS TESTING
The consulting engineer or road authority may have specified their own test schedule. In the absence of this,
the following materials tests are suggested.
Note: Please also refer to TRH3 (2007) Chapter 9 and the latest TG1 document.
Flakiness Flakiness
Test
Size ALD
Gradation Sieve
Analysis
Fines content
< 0,425mm
Dust content
< 0,075mm
Water (if used in a Compatibility for Dilution test 1 litre from each source 1 per
fogspray) dilution sour
ce
Note:
Aspect to be Sampling
Component Type of control Sample size
Controlled Frequency
The stockpile area must be big enough to store the binders (static tanks and haulers) and aggregate for the
area it services:
Note:
Assume that 1 m3 of loose stockpiled aggregate will cover 40m2 on the road (for a single seal). Assume a pile
of 20m3 will take up an area in the stockpile of approximately 3 metres x 4 metres. Thus for enough
aggregate for a 5 kilometre single seal surfacing:
Road width = 8m
Length = 5,000m
Road surface area = 8 x 5,000 = 40,000m2
Aggregate needed = 40,000/40 = 1,000 m3
Number of 20m3 heaps = 1,000/20 = 50
Area needed = 50 x (3x4) = 600 m2
All of the above have different responsibilities during the surfacing operation. Although it is not possible to
discuss all the decisions to be taken during seal construction, the following should serve as a guideline.
5.5.2 PRIMING
5.5.2.1 Before priming
Decision Departmental Operation Contractor Operation
Has the base course dried out Technician RE/Site Agent
sufficiently
Has the base course been Technician/Foreman RE/Site Agent
swept to a satisfactory standard
Is the weather conducive to Technician/Foreman RE/Site Agent
priming
Is the correct prime available Technician/ Distr. Operator Site Agent /Distr. Operator
Is the prime the correct Technician/ Distr. Operator RE/Site Agent /Distr. Operator
temperature
5.5.3.3 Rolling
Decision Departmental Operation Contractor Operation
Is the correct type of roller Technician RE/Site Agent/Roller Operator
available
If a pneumatic roller is used are Technician/Foreman/ RE/Site Agent/Roller Operator
the tyre pressures correct Roller Operator
Has the surface been rolled Technician/Foreman RE/Site Agent
sufficiently
If a steel tyre roller is used, is Technician RE/Site Agent
the aggregate not crushing
excessively
5.5.4 SLURRY
6.1 GENERAL
The provision of the necessary road signs is an important aspect of any reseal work, not only for the effective
execution of the work, but also for the safety of the traveling public.
Traffic signs for reseal work must be erected according to legislation. The person in charge of resealing units
must ensure that he is familiar with these requirements. Detailed instructions must be issued to teams
regarding the provision and placing of road signs.
The specified signs, including cones, must be available on site and in good condition before work is
commenced. On heavily trafficked roads it is of particular advantage to use portable traffic lights controlled
by two-way radio or telephone.
It is important to ensure that traffic is not allowed on a new seal until such time as an affective adhesion has
taken place between the stone and the binder, to ensure a minimum loss of aggregate. For this reason work
should be done in half-widths unless detours can be constructed.
If early opening of the road is required, after using emulsion as a spray, the surface should be covered lightly
with sand or crusher dust and distributed evenly with a hessian drag. The surface must then be back rolled
with wet wheels before opening to traffic.
Where possible arrangements must be made with the local traffic police to be on duty on site to control the
traffic. Speed of traffic over the completed seal must be controlled during the first 24 hours.
The prescribed road signs must be erected before any completed section of road is opened to travel. The
temporary road signs must be removed from the constructed section as soon as there is no longer danger of
loose stones being whipped up by traffic. Care should be taken not to leave signs up where there is no
longer danger of loose chips, since the public is then inclined to disregard all such signs.
Rural 600
7.1 GENERAL
The entire Chapter 6 of TRH3 (2007) forms part of the course content
Services, such as culverts, water mains, telephones, Installation well ahead of any
rehabilitation work, or trench
etc.
reinstatement 6 weeks
Notes
Times will increase in cool or humid climates.
If time is critical, do periodic ball penetration tests on the pretreatment and adjacent old surface.
When the differential is less than 1mm, or the corrected ball penetration is less than 2 mm, then
resurfacing can be done.
Note: The complete and latest COLTO updates to road related contract are either bound into this document
as Appendix B or provided as part of the course documentation in electronic format
The most appropriate remedial measure is dependent on the cause of distress, the degree to which
aggregate loss has already occurred, the type of seal and the risk and consequences of further damage and
windscreen losses.
Typical situations and potential remedial measures are further discussed:
Application of additional binder in the form of a cationic spray grade emulsion or diluted cationic spray grade
emulsion cover spray should stabilise the situation. The amount of residual additional binder required is
dependent on the macro texture (voids available), expected traffic volumes and the prevailing and expected
climatic conditions. The minimum application would typically be a 50% diluted 65% cationic spray grade
emulsion at 0,8 l/m2.
A slight application of coarse sand (Grit) after the emulsion has broken will further reduce the risk of
aggregate loss.
Excellent results have been obtained by converting single seals to double seals through:
Application of binder and pre-coated coarse sand
Application of binder and pre-coated 6.7mm aggregate or
Application of a fine slurry to obtain a Cape Seal effect
Re-application of binder and aggregate is normally the only feasible option unless sufficient funds are
available to overlay the area with asphalt.
Due to the binder film already on the road, the risk exists that too high binder application will result in a
bleeding surface. There is no simple answer to determine the appropriate binder application rate for the
repair action and it is recommended that some trials be conducted on site for this purpose.
The reader is referred to SABITA Manual 12 (1994) for additional guidelines on this topic.
8 Chip spreader
No leaks
Conveyor belt condition
Continuous even aggregate flow
Correct and full width application
Dry run – check application rate
9 Rollers
No leaks
At least 2 pneumatics (20+ ton ballasted)
Steel wheel if specified (5-8 tons)
Tyre pressures
10 Trial section & regular inspection
Traffic accommodation and safety
Spray lane demarcation done
Air /road temperatures confirmed OK
Binder temperature OK
All equipment checked for leaks/ condition
Aggregate available
Pre-coated quantity and quality
Sufficient equipment
o Loader
o Trucks
o Rollers
o Brooms
Sequence and follow distance
Joint paper (weighed down with chips)
Full section available to chip spreader and
rollers
Spray overlaps and fishplate usage
Binder application rate
Aggregate application rate
Back chipping, brooming to edges
Removing of double chipping
Rolling to edges (8-10 passes)
Brooming
o When
o Set height
o Rolling after brooming
Confirm competency of each operator +
o Straight lines
o Start and end on paper
Waiting periods before 2nd applications
Final inspection before opening to traffic
o Traffic accommodation & safety
o Stability of seal
Confirm road marking time and procedure
DESIGN FORMS
(Examples)
Aggregate Type 6,7 mm ; 9,5 mm ; 13,2 mm ; 13,2 mm + grit ; 13,2 mm + 6,7 mm ; 19,0 mm + slurry *
Binder Type
Code
General
Traffic Counts per Lane One Way Both Ways
Heavy Vehicles per Hour / Day *
E80 per Heavy Vehicles (Estimated / Determined) *
Average E80
Traffic Factor [P]
Climatic Zone
Road Surface Condition
Texture Depth mm
Aggregate
Particulars of 1 2 3
Sample No.
Source
Type
Stockpile at km
Nominal Size mm
ALD (Measured / Calculated) * mm
Flakiness %
AIV (Dry / Wet / Glicol) %
ACV (Dry / Wet) %
10% FACT (Dry / Wet) kN
Treton Value %
Application Rate m2/m3
Binder
A = Total Cold Nett = (P . Total ALD ) Ltr/m2 = ( . ) Ltr/m2 = ( ) Ltr/m2
B = Total Reduction a Construction Traffic % C = Total %
= A (C/100) b Aggregate Hardness % = (a+b+c+d)%
=( ) Ltr/m2 c Binder Type % = ( )%
d Other (Climbing Lanes, Steep Gradients, etc.) %
D = A − B = Required Total Cold Nett = ( − ) Ltr/m2 = ( ) Ltr/m2
E = Final Spray ( Emulsion Fogspray ) (i) Diluted (60 / 65 / 70 *) % Emulsion in a ( : ) ratio
(ii) Undiluted ( ) % Emulsion
F = Cold Nett Binder of Final Spray (Fogspray) @ ( ) Ltr/m2 = ( ) Ltr/m2
G = D − F = Remainder Cold Nett Binder for First (Tack) or First and Second = ( ) Ltr/m2
Spray 1 (Tack) 2 (Penetration) 3 (Final)
Distribution of G (Remainder Cold Nett Binder) % % −
Type of Binder Anionic/Cationic *
Required Cold Nett Ltr/m2
Binder Factor −
Hot Application Ltr/m2
Increase / Decrease
Recommended Rate at Spray Temp. Ltr/m2
Slurry
Layer
Slurry Mix Proportions : per 100 kg Aggr. or per m3 Mix (Dry) *
Single / Upper * Lower
Crusher Dust kg
Crusher Dust kg
Sand (Type) kg
Cement (Type) kg
Emulsion (Type) kg (litre)
Water litre
Flow of Slurry mm
* Cross out whichever option is not applicable or delete if not applicable
Remarks Approved by:
Sheet of
Date:
General General
Traffic Counts per lane Lane One Way Both Ways Traffic Counts per lane Lane One Way Both Ways
Traffic Counts (Daily Average) per lane Traffic Counts (Daily Average) per lane
% Heavies % Heavies
Traffic Factor Traffic Factor
ELV / Lane / Day ELV / Lane / Day
Texture depth Texture depth
Average Ball Penetration Average Ball Penetration
Climate Zone Climate Zone
Aggregate Aggregate
Particulars of Aggregate Spray 1 Spray 2 Spray 3 Particulars of Aggregate Spray 1 Spray 2 Spray 3
Source Source
Type Type
Nominal Size Nominal Size
ALD / GKA (Measured) mm ALD / GKA (Measured) mm
Flakiness % Flakiness %
ACV (Dry / Wet) % ACV (Dry / Wet) %
10% Fact (Dry / Wet) % 10% Fact (Dry / Wet) %
Polished Stone value Polished Stone value
Sand equivalent % Sand equivalent %
Procoating fluid type Procoating fluid type
Procoating fluid rate % Procoating fluid rate %
Application Rate m2/m3 Application Rate m2/m3
Binder Binder
Design ALD = (ALD1 +ALD2) = 12.4 + 4.5 = 16.9 Application 1 Application 2 Application 3 Design ALD = (ALD1 +ALD2) = 12.4 + 4.5 = 16.9 Application 1 Application 2 Application 3
Spray l/m2 Spray l/m2
Binder Type pen Binder Type pen
Required Cold Nett l/m2 Required Cold Nett l/m2
Spraying Temperature deg Spraying Temperature deg
Recommended Rate l/m2 Recommended Rate l/m2
Slurry Slurry
Proportions per 100kg Aggregate or per m3 mix (Dry) (Texture Slurry) Layer Proportions per 100kg Aggregate or per m3 mix (Dry) Layer
Bottom Top Bottom Top
Crusher Dust type (kg) Crusher Dust type (kg)
Crusher Dust type (kg) Crusher Dust type (kg)
Sand type (kg) Sand type (kg)
Cement type (kg) Cement type (kg)
Emulsion type (kg or liter*) Emulsion type (kg or liter*)
Water (liter Water (liter
Flow of slurry (mm) Flow of slurry (mm)
*Delete if not applicable *Delete if not applicable
1 PROJECT DESCRIPTION
CONTRACT: …
STARTING DATE OF THE SURFACING WORKS: ……1ST OR 2ND WEEK OF JULY 2007
2 CONTACT DETAILS
CONSULTANT:
- Engineer
- Residential Engineer
- Materials
CONTRACTOR:
- Contracts Manager
- Site Agent
COLAS:
- Branch Manager
- Operations Manager
- Factory Manager
- Transport Manager
PRODUCT SUPPLY, DELIVERY and STORAGE,
3.1 Product:
Date & Time for the first load on site: ……1ST OR 2ND WEEK OF JULY 2007
Product Temperature:
- Application: Max T°: 190ºC …….…. Period: 8 hours………………
- Storage: Max T°: 180ºC Period: < 24 hours………………
150ºC > 24 hours
Expected Daily Consumption: ………24 kl………………………………………………………
Date & Time for the first load on site: 1ST OR 2ND WEEK OF JULY 2007
Date & Time for the first load on site: ….….5 June 2007…………………………………………….
Colas are considering two options as detail below but will finalise during the
- Who is going to place orders: Initially Chris Eaton and move to Transport Manager - Ricky
- To whom the order must be sent to:
- Order to be placed by fax □ e-mail
- Default lead time for orders excluding weekends: 72 hours
- Weekly program sent on each Thursday by 13:00 pm for following week
3: ……………………
4: ……………………
Should binder have to stay overnight; heat control must be carefully monitored to ensure
product is not adversely affected.
4 QUALITY CONTROL
Colas will provided detailed method statement with planned quality control and testing regime (Trevor Distin).
Full spectrum of tests will only be done on product on first batch and thereafter every fifth batch.
External Test Requirements: Colas to conduct a lab correlation with SRT on full spectrum of tests to ensure
compliance to reproducibility limits. Historical correlation with SRT will also be evaluated.
SUPPLIER TO PROVIDE CERTIFICATE FOR BASE BITUMEN with each delivery to site.
Product Size Source Hauler Storage Sprayer
Colas will confirm the final source of bitumen supply and will provide historical records of Base Bitumen for
the last month (some form of track record).
*It was requested the samples ex-refinery be attained with each load. Colas will try but felt that refinery would
probably not entertain this.
Softening point has to be approved on site before spraying can commence, i.e. sample needs to be drawn 2
hours before spraying.
Concern was raised as to possible contamination of Binders from hauliers. This needs to be protected
against.
5 SPRAYING
5.1 Specifications
These are new standards in terms of spraying tolerances, which the contractor formally proposed to the
engineer (i.e. the specifications on this contract are still based on the Colto tolerances).
- Validity period for calibration certificate: 12 months - Colas to provide supporting correspondence
…………………
- Bakkie test Yes Site □
Colas
Date: To be confirmed…………. Time: …………………………
Bakkie test to be done every two months.
Calculation tolerances: 5% for 80/100
7% for Colflex S
Daily Operation Testing of Spray Bar Flushing of the Spray Bar
Where On site at stockpile areas On site at stockpile areas
Time Before spraying After spraying
Into a tray which allows product to be
How sucked back Discharged into drums for re-use
Spilled material will be mixed with
gravel/material and spoilt at an acceptable Drums removed from site and disposed
Disposal spoil site. of at an approved waste fill site.
5.3 Production
Colas Contractor
Protection of kerbs N/A
Traffic Control
Hand Sprayer
yes
□ no
At interchanges
OTHER NOTES:
The method of traffic accommodation was discussed in some depth. This is however to be looked at closer
and the correct method agreed to.
1. Position of joint.
4. Fish plate with low clearance to be provided to prevent binder during spraying from staining
concrete cut-off drain.
It was proposed that some x-sections be drawn in order to assist with the evaluation of the spraying options.
PROJECT
CONTRACT NO.
DATE OF MEETING
ATTENDANCE REGISTER