QP10 Control of Inspection & Measuring Equipment
QP10 Control of Inspection & Measuring Equipment
QP-10
Remarks:
Use this document only, if it is stamped with the Red One (Controlled
Copy Stamp).
No part of this procedure may be reproduced in any form by print,
photocopy, microfilm or any other means wholly or partially, or disclosed to
any person outside SITE TECHNOLOGY LTD. CO.. without a written
permission.
This Document is authorized by the CAO/ MR, and any change thereof
can only be made with his approval.
Page No. 1 of 3 Revision No. 4 Revision Date: 05/03/2017 Document No. QP-10
1.0 PURPOSE:
2.0 SCOPE:
2.1 This procedure shall be considered applicable to the measuring and test
equipment used by SITE TECHNOLOGY LTD. CO.
3.0 RESPONSIBILITIES:
3.1 The Division Manager (DM) and Project Engineer (PE) are responsible to review
and implement this procedure
4.0 PROCEDURE:
4.1 The DM shall prepare, maintain, the calibration plan (QPN10f1) annually for all
Measuring & Monitoring Devices requiring calibration. Also he shall update it
against any new instrument/equipment/device newly introduced to the system
or rather terminated.
4.2 Where it is agreed that internal calibration capability is inadequate for given
instrumentation, DM shall identify the external calibration sources.
4.3 The inspection, measuring and test equipment shall be calibrated through
traceable to national or international standards.
4.4 The intervals of calibration for each instrument shall be based on:
• External calibrating agency determination
• Manufacturers’ recommendations.
• Known instrument performance and frequency of usage.
4.5 The DM shall liaise with the external calibration agencies to ensure that the
instruments requiring calibration are collected from the project sites and
returned after calibration.
4.6 Advance notification period shall be determined by DM to all the projects sites
which have instrument-requiring calibration, taken into consideration the
external calibrating agencies response times.
Page No. 2 of 3 Revision No. 4 Revision Date: 05/03/2017 Document No. QP-10
4.7 DM shall send copies of calibration certificates done to the concerned project
site. All records of calibration shall be made available to the clients on request.
4.8 Upon project site request, the calibrated instrument / equipment shall be issued
to authorized personnel along with calibration certificate and shall be stored in
a controlled secure storage area.
4.9 DM & PE of every project shall ensure that the equipment calibrated are suitably
identified to indicate its calibration status using labels shown below (if
required).
CALIBRATED
Next Calibration Date: / / 200
Sig.:
OUT OF CALIBRATION
Date: / / 200
Sig.:
Page No. 3 of 3 Revision No. 4 Revision Date: 05/03/2017 Document No. QP-10