(1) The document provides a rate analysis for formwork shuttering for a retaining wall that is 7.9m long, 1m high, and has a contact area of 15.8 sqm. Materials included in the shuttering are plywood panels, channels, bridges, clips, and MS tubes. (2) Labor requirements and costs are estimated for fitters, beldars, shuttering oil, and sundries. (3) The total estimated rate is Rs. 7671.12 for the 15.8 sqm wall, which amounts to Rs. 486 per square meter of formwork shuttering.

Uploaded by

Manish Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
403 views

Ply Shuttering

(1) The document provides a rate analysis for formwork shuttering for a retaining wall that is 7.9m long, 1m high, and has a contact area of 15.8 sqm. Materials included in the shuttering are plywood panels, channels, bridges, clips, and MS tubes. (2) Labor requirements and costs are estimated for fitters, beldars, shuttering oil, and sundries. (3) The total estimated rate is Rs. 7671.12 for the 15.8 sqm wall, which amounts to Rs. 486 per square meter of formwork shuttering.

Uploaded by

Manish Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

RATE ANALYSIS

ITEM NO:
Centering shuttering including struttings, propping etc. and removal of form work for: Retaining
walls, return walls, walls (any thickness) including attached pilasters, but- tresses plinth and string
courses fillets etc.
Sr. No. Item Qty. Rate Per Amount
Details for 7.9m long and 1.00m high wall
Area of contact 2x7.9x1.0 = 15.8 sqm. —
—Materials:
Assuming shuttering material will be unseviceable
after use of 40 times

(1) Plywoof Panel (1.25x0.5) 2x3x2x2 = 24 Nos. 2.55 980.00 2499.00


Qty taken for cost of using once = 24x0.85/8 = 2.55

100mm channel shoulder 2.5m long, 4x2 = 8 0.85 1000.00 850.00


Qty taken for cost of using once = 8x0.85/8 =
0.85

Bridge clip 2x6x2 = 24 Qty taken for cost of using once 2.55 75.00 191.25
= 24x0.85/40 = 2.55
Single clip 2x3x2 = 12 1.275 60.00 76.50
Qty taken for cost of using once = 12x0.85/40
= 1.275
(2) M.S. Tube 40mm 2x2x8m = 32m 3.4 225.00 Sqm. 765.00
Qty taken for cost of using once = 32x0.85/40
= 3.40

(2) Nut & Bolts 1 72.00 Sqm. 72.00


(3) Carriage 1 90.00 Each 90.00
(4) Labour:

Fitter Grade-I 2 151.50 303.00


Beldar 5 135.25 676.25
Shuttering oil 1 78.00 78.00
Sundries 1 52.00 52.00

Total Rs. 5653.00


Add 15% profit on (2)to (8) 847.95
18% GST 1170.17
Rate for 15.80 Sqmt. 7671.12
Rate for 1.0 Sqmt. Say Rs. 486.00