Project Charter Final
Project Charter Final
2nd Floor OZ
Building 900 San Marcelino Street, Ermita,
Manila 1000
Phone (632) 524.20.11 local 407
CONSTRUCTION
PROJECT CHARTER
Prepared by:
Tom Fuentes
Submitted to:
Engr. Henry Florendo
September 23, 2023
FRL CONSTRUCTION : 3- Storey
Residential School Project
LOCATION: Cabiao Nueva Ecija
PROJECT CHARTER
Table of Contents
General Project
Information.................................................................................1
Scope
Overview.....................................................................................1
Milestone and
Deliverables………………………………………………….. .1-2
Project
Risk………………………………………………………….....2-3
Resource
Requirements...............................................................................3
Project Cost
Estimation....................................................................................4-5
Roles and
Responsibilities.............................................................................6
Project Title: 3- Storey Residential School Project
Brief Project The Project is a 3 STOREY RESIDENTIAL SCHOOL PROJECT With the Total
Description: area of 200 sq.m built for the Cabiao Nueva Ecija
Scope Overview:
The 3- Storey Residential School Project design and construction, landscaping, and a thorough estimate that
covers all the labor and services needed to accomplish this project from beginning to end are all included in the
scope of work.
The Sponsors/Owner will be asked to design the project plan and then to approve it. Upon approval, the project
plan will go into the execution phase. If the project has a clearly defined scope, an acceptable budget, cutting-
edge construction techniques, renewable technology, and efficient construction control, it should be possible to
complete it on schedule and within budget.
Current State Bid Preparation Owner and Consultant Satisfy the needs and
demands of the owner
Invitation to Bid (ITB) September 30, 2023 Owner and Consultant Getting at least 5
Invite bidders proposals
Prepare, issue and award October 7, 2023 Project Manager(s) A bid proposal that
independent cost satisfies the owner's
needs and
specifications (in
terms of job quality,
cost, and time and
length)
Design Development Phase October 14-21, Architect and Different design plans
2023 Structural Engineer present to the owner
Project Risks:
Identify the high-level project risks and the strategies to mitigate them.
Project Risks Contingency Plans / Mitigation
Strategy
1. Risks Associated with COVID-19 ● Obtaining third party insurance
coverage.
● DOH's recommended COVID-19
safety procedure
3. Unplanned work that must be ● Try and stay ahead of the schedule
accommodated
Resources Required:
Identify the initial funding, personnel, and other resources committed to this project by the project owner.
Resource Point Person
Manpower Contractor
Other Contractor
Consultant - investigate the company, use data analysis to pinpoint issues and create plans to execute
solutions, stay abreast of market changes, and work with management and staff to understand their
requirements.
Engr.
Project Manager - oversees the project's current state and various initiatives that need to be carried
out, keeps track of its development and completion, and ensures that the business meets its clients' and
owners' expectations.
Engr.
Core Member -responsible for ensuring that the project achieves its goals, complies
with the standards and best practices unique to their job, works to enhance team
performance, and establishes the tone and direction of the business.
Engr.
Engr.