0% found this document useful (0 votes)
222 views4 pages

WBVF Instruction For Jumper Cable

The document provides instructions for using jumper cables during the installation and commissioning of a control panel and traction machine. It describes the purpose and connections of different jumper cables for safety lines and final limit switches.

Uploaded by

kolwin .chindwin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
222 views4 pages

WBVF Instruction For Jumper Cable

The document provides instructions for using jumper cables during the installation and commissioning of a control panel and traction machine. It describes the purpose and connections of different jumper cables for safety lines and final limit switches.

Uploaded by

kolwin .chindwin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

WBVF Instruction for Jumper Cable

1. Interview
Before the travelling cable be finished installation and connection. These jumpers below should
be used for the control panel & traction machine commissioning and shaft parts‘ installation.

2. Jumpers of safety line

CN-S4 Jumpers CN-S2 Jumper


CN-S4 Jumpers:
CN_S4-1→CN_S8-2:shaft + car + car top E-stop switches
CN_S8-2→CN_S6-1:interlock switches
CN_S8-2→CN_S8-3:car door lock switches
CN-S2 Jumper:
for pit safety switches(buffers/governor tension/pit E-stop button)
Location in control panel:
3. Jumpers of final limit switches

Up limit switch jumper down limit switch jumper


Before up/down limit switches( on FLS) installed & connected, these jumpers should be connected on MAIN
Board, so you can drive the traction machine running up or down.
Location in control panel: