Manufacturing Case
Manufacturing Case
World class manufacturer’s say that BOM accuracy must be 98% or better to enable them to conduct their business competitively.
• All end items, subassemblies and manufactured components must be identified with a part number and must have a
corresponding bill of material. For accurate costing, include raw materials & consumables.
• Bills of materials must be entered into the system within five working days of a part numbers assignment.
• All changes to bills of material must be documented via the engineering change policy
• Bill of material changes and additions will be audited as per the BOM administrator’s job description
• Bill of material accuracy must be maintained at 98% or better.
• Bill of material accuracy is to be audited by the tracking of unscheduled issues and receipts, random sampling of single
levels of bills of material, reviewing stores pick lists and by disassembling by Quality Assurance.
The Problem
For identification and control purposes, any part that is ever stocked, shipped and /or scheduled needs to have a unique part
number. When making modifications to a part specification, engineers often do not know whether or not to assign a new part
number. Opinions differ not only in engineering but also in other departments of the company. The problem is compounded in some
companies where the part number is used for two separate functions:
Discussion
Since 1812, when rifles were first assembled from standardised parts, everyone has become increasingly familiar with the ability to
repair a product by replacing the faulty component with a component taken from a similar product. Part standardisation was an
important step in the progress of manufacturing. This familiarity has led to the popular belief that the replaced and the replacement
components are identical. This misunderstanding is not at all helpful when trying to solve the problem of if or when to change a part
number. For example:
“One part number must not identify two or more items that differ from each other, if ever so slightly”
Statements such as this show a fundamental lack of appreciation of the design process. When designing a part, a good engineer
will allow manufacturing as much flexibility as possible to produce a satisfactory part at minimum cost. The specification will
normally take the form of limits, within which manufacturing must operate, outside of which the engineer:
The specification limits needed to satisfy (b) are normally “tighter” than those needed to satisfy (a) e.g. two springs of similar
outside diameter and length are physically interchangeable but, if the wire diameter or material is different, only one may give the
desired performance. Just as no two people identical, no two parts ever made are identical. There are always slight differences,
within limits.
Other suggestions for solving the problem also put emphasis on the differences between parts:
“If the form, fit or function of a part is changed, it must have a new identifier a new part number”.
It is implied that differences in form, fit or function are distinct. In fact they tend not to be. Once the engineer has decided what type
of change the modification in question is, he is still left wondering whether the change of form, or fit, or function is significant
enough to justify allocating a new part number. For example, a 10% increase to the clearance between a shaft and a bearing is a
change of “fit”, but would not normally justify a new part number.
A Solution
It is proposed that the key to solving the problem is to analyse the similarities between parts, not the differences. Two parts
identified by the same part number must be sufficiently similar to:
The important point is that the performance of both the parts is adequate; they will never be the same. There will always be
differences. In a nutshell they should only have the same part number if they can be mixed in the stores (i.e. in the same stock bin).
Any of the tests can be carried out by the company, by any customer or any other body (usually at the company’s or customers’
request). Given the number of permutations of test and testers there obviously will be a wide range of opinion regarding what
performance is adequate for a particular part.
This is the reason that traditional (rigid) decision rules for changing part numbers do not work. It must be acknowledged that in
extreme cases, it is sometimes necessary to change a part because a particular customer firmly holds an unjustified opinion of the
performance of that part. If this is done, it will be necessary to schedule the new part for that customer and it is therefore essential
that the part number is also changed.
Case Yes No No No
3
Examples 4, 5 and 6 deliberately highlight some awkward situations where the engineer needs advice. In such circumstances, it is
the reason for the change – not the technicalities of the change – that determines whether or not to assign a new part number. It is
the responsibility of the Engineering Change co-ordinator to advise the engineer on this.
If it is decided to assign a new number to a part, it must then be decided whether or not to assign a new number to its parent. The
criteria for deciding this are exactly the same, at all levels in the Bill of Material structure.
Any change to the specification of a part has to be recorded on the drawing and therefore the drawing number should be changed.
This is normally achieved by adding a revision letter to the drawing identification. However if:
• a) the change relates to inter-changeability or performance (as described above) and
• b) the part number and drawing number are the same
then it is necessary to change the whole number on the drawing. Any temptation not to change the part number as prescribed,
because of the inconvenience of changing the number on the drawing, must be resisted.
All Applications
Development of a
Peg
Eng Change Standardize on Achieve Reduce M/C
Reason one peg adequate tool set up
performance time
Drawing(s)
Differs
from
part No
With computerised Product Life-cycle Management (PLM) change management must be formally controlled, but not to tightly, or
some of the reasons for implementing PLM will not be achieved. Of particular concern, are document control, configuration
management, traceability and product liability issues. Without proper attention the PLM installation benefits will fall far short of the
desired results.
Adapted from “Engineering Design: A Materials and Processing Approach” - see ref. 017
To do this manually requires many hours of research. Therefore a computer based approach is called for. This can be as simple as using a
database or spreadsheet tables similar to this one below:-
The above table plots the relative cost of materials using mass and volume. Other charts and tables could be used to plot any material
characteristic against another depending on the problem needing to be solved. Alternatively we can use more sophisticated approaches that
present properties in a graphical form like an “Ashby Chart” below showing density against Young’s Modulus:-
Whatever approach is taken it can speed the process of arriving at candidate materials for the engineer to make his final selection weighing all
the relevant factors in the process.
Material Selection in the Product Design Process
Material selection takes place at component level in the Product Structure.
As the design team iterates the design the actual material, shape and processing requirements of the components remain in a state of flux until
the team decide enough has been done to satisfy the Product Design Specification and the target cost. It is then “frozen”, approved and released
for manufacture.
The design team use tools that enable them to make many trade-offs to arrive at the final selection.
Many CAD and FEA systems have materials databases that can be adapted, populated or developed for this purpose. Some standalone systems
are available to do this in reverse – they provide the data and selection methodology and the data is made available to design and design analysis
tools. Material comparison charts and tables make useful reference data as input to Value Analysis or Value Engineering studies or projects. See
guide 6.22.
Many researchers have prepared process descriptions and parameters and cross-referenced them against the materials available.
This is the subject of intense research so that more rapid cost estimates can be obtained along with the process selection. Some
software products are available that directly produce list of candidate processes as a direct result of analysing the geometric shape
in the CAD model. These software products are being developed using content from CAPP or CAPPES software products as the
basis. Some have been developed from DFMA / DFA software and some are being developed by the CAD software vendors.
In any case they use a means to cross reference the materials to the process similar to the next table. The numbers in the matrix
indicate the maximum annual volume expressed as 10X where X is from the matrix.
ê Processes
3.02 – Rolling 6 6 6 6 6 6 6
3.03 – Drawing 6 6 6 6 6 6 6 6 6
3.06 – Swaging 7 7 7 7 7 7 7 7 7
3.10 – Spinning 4 2 4 4 4 4 4 4 4 4 4
4M – Machining – Manual 3 3 3 3 3 3 3 3 3 3 3 3
4A – Machining – Automatic 6 6 6 6 6 6 6 6 6 6 6 6
5.01 – EDM 3 3 3 3 2 3 3 3
5.02 – ECM 4 5 5 4 4 5 5 4
5.03 – EBM 3 4 4 4 4 4 4 4 4
The previous chart is by no means exhaustive – it serves to illustrate what the main factors are. There are many sub-factors to
selecting a process to match a material selection. Some are shown below:-
• Cost of manufacture
• Geometric Shape
• Actual Material Specification
• Tolerances / Surface Finish
• Tooling, Jigs and Fixtures
• Gauges
• Available Equipment (in-house or in the Supply Chain)
• Delivery Date
• The generation of alternative and cost effective design ideas that facilitates the matching of available manufacturing
processes to those ideas
• Using that data in the roll-up of component and assembly costs to measure design performance against Target Costs
and Target Weights.
Some firm’s competitive advantage comes from the ability to “design” new materials and processes and do not want that expertise
to become public. They may use a generic materials and process selection system or method and add their own data to the system
to make that knowledge available within the company.
The output from computerised material and process selection systems can be presented as shown in the following diagrams to
enable designers to make rapid trade-off decisions. The costs in this table are relative.
Poor strength
High strength
Low-med prod
2.2
rates
Non-Porous
Porous part
Plain Bearing
Low
detail/accuracy
High
Cover
detail/accuracy
Med 100,000 Closed Long lead
Carbon Die times
Steel Forging 1.3
High tooling &
equipment
costs
Poor strength
High strength
Spur Gear
A supplementary display giving instant feedback to the CAD designer on the cost of design ideas as the design is iterated also
speeds process selection (see diagram below).
6.17 - Part Classification and Group Technology
Manufacturing managers know that information or data that cannot be accessed is virtually useless. A company’s intellectual
property is contained in the products and parts it has created to solve particular design problems. According to one source, “Up to
80% of the work done in an engineering department is identical or very similar to work done previously” (from research by Arthur D
Little). Unfortunately this investment is not always managed effectively. One of the most satisfying tasks to reduce design and
manufacturing costs is to implement a part cataloguing and retrieval system enabling previous design work and parts to be re-used.
Deep
Flanges
Impellers
The design engineer will search for flanges or impellers and the manufacturing engineer will pull all those items into a single class
because they have similar manufacturing routes and can be made in the same manufacturing cell.
Classification – Definitions
Dictionary Definition: A system to arrange things in order.
Applied to industry, “A classification system must be able to organize data relating to the relevant component element(s) of a
business in a logical and systematic hierarchy, whereby like things are brought together by virtue of their similarities, and
then separated by their essential differences.” – Joseph Gombinski – Brisch Birn & Co.
To illustrate consider this simple functional classification using MRP or PLM item master records:-
Part Number Primary Description (or Main Noun) Secondary Description (attributes)
This approach, in the absence of a formal classification system, is a good place to start. Selecting and sorting on either description
enables the fairly quick location of previously designed parts. Displayed with a thumbnail image of the part it can be powerful in its
own right. It also lays the groundwork for formal classification systems implementation. The primary description would be used on
external documents only (e.g. maintenance and service manuals so as NOT to give away any IP) whereas the secondary would be
used internally for search, retrieval and recognition purposes. Some of that information can be used to populate a manufacturing
process coding system or functional coding system.
A B C D E Totals
Assemblies
1 1 1 1 10110 22
2 1 1 01011 9
3 1 1 1 10110 22
4 1 1 1 10110 22
5 1 00001 1
6 1 1 1 1 1 11111 31
7 1 1 01001 9
8 1 1 10010 18
9 1 1 1 10110 22
10 1 1 1 10110 22
11 1 1 01001 9
12 1 1 1 10110 22
13 1 1 01001 9
14 1 1 01001 9
Binary Total
Decimal
We can quickly see that parts 1, 3, 4, 9, 10, & 12 have the same binary score indicating they are common to some of the
assemblies (A, C, & D).
The next stage is to re-order the parts according to their binary totals thus:-
A B C D E Totals
Assemblies
6 1 1 1 1 1 11111 31
1 1 1 1 10110 22
3 1 1 1 10110 22
4 1 1 1 10110 22
9 1 1 1 10110 22
10 1 1 1 10110 22
12 1 1 1 10110 22
8 1 1 10010 18
2 1 1 01011 9
7 1 1 01001 9
11 1 1 01001 9
13 1 1 01001 9
14 1 1 01001 9
5 1 00001 1
Binary Total
Sort the columns by their totals and we get the result on the next chart. We have part groups (brown, green and yellow) highlighted
as shown.
Notice that ALL the assemblies contain part 6. This is a common part. The brown group is common to assemblies A C & D and the
green group is common to assemblies B & E.
A D C E B Totals
Assemblies
6 1 1 1 1 1 11111 31
1 1 1 1 10110 22
3 1 1 1 10110 22
4 1 1 1 10110 22
9 1 1 1 10110 22
10 1 1 1 10110 22
12 1 1 1 10110 22
8 1 1 10010 18
2 1 1 1011 9
7 1 1 1001 9
11 1 1 1001 9
13 1 1 1001 9
14 1 1 1001 9
5 1 1 1
Binary Total
Part 8 is common to A & D. Part 5 is unique to assembly E. After sorting, the binary and decimal values for the rows actually
change their values, but it does not affect the results. By using text concatenation and binary to decimal conversion add-ins in Excel
it is possible to manipulate some fairly large matrices in this manner. For information on how to manage common part groups in
similar assemblies to assist with part rationalisation and modular design see guide 6.20.
BOM Efficiency Improvements
The product structure for the original arrangement would be:-
Assembly A – 1, 3, 4, 6, 8, 9, 10, 12
Assembly B – 2, 6, 7, 11, 12, 13, 14
Assembly C – 1, 3, 4, 9, 10, 12
Assembly D – 1, 3, 4, 6, 8, 9, 10, 12
Assembly E – 2, 5, 6, 7, 11, 12, 13, 14
Assembly A and D are identical – this is not an unusual finding where little, or no, attention has been paid to modularisation. So of
the total of 37 structure records by modularisation we can eliminate assembly A or D all together. If we create sub assemblies
green and brown, we get the following:-
Sub-assembly (or phantom) Brown – 1, 3, 4, 9, 10, 12
Sub-assembly (or phantom) Green – 2, 7, 11, 13, 14
The original assemblies now look like this:-
Assembly A – Brown, 6, 8
Assembly C – Brown, 6
Assembly E – Green, 6, 5
Assembly B – Green, 6
The total product structures have been reduced to 21 from 37 – almost a 50% reduction. This affects computer processing time to
generate requirements and BOM displays etc. Assembly kitting is easier and the BOM maintenance time is reduced and
engineering change is much easier to manage.
Some BOM systems have a reporting capability called a matrix BOM. This is similar to ROC method described here. The user
schedules the report with the part numbers of the assemblies s/he wishes to compare and the number of levels the bill should be
exploded too. A matrix report is generated with components down the page and assemblies across the page. However, it is up to
the user to do the clustering to determine what the natural option groups could be. The matrix report could be imported into a
spreadsheet tool for clustering.
The next guide, modularising the BOM (guide 6.20), shows what else can be done to improve the BOM structure.
220
Colour Pink
Blue
To demonstrate the process we are going to use the ubiquitous example of the Sure Fire Lawn Mower. You may notice that Sure
Fire Ltd have now gone metric but still have not modularised their bills of materials which are shown below:-
1 – Identify the Product or Family group(s)
For the Sure Fire Lawn Mower this is easy. We have the family of lawn mowers of which there are 8 permutations – four 450mm
cut mowers and four 550mm cut mowers. Of course, with only eight end products it is a relatively trivial matter to manage each end
product bill of material. However, it does serve to illustrate the modularisation concept.
Engine Type 4 4 2 2 4 4 2 2
Starter Type A M A M A M A M
Item Part Description Qty 101- 101- 101- 101- 102- 102- 102- 102- Binary
No 1 2 3 4 1 2 3 4
Engine Type 4 4 2 2 4 4 2 2
Starter Type A M A M A M A M
Item Part Description Qty 101- 101- 101- 101- 102- 102- 102- 102- Binary
No 1 2 3 4 1 2 3 4
That’s 6 in all.
3 – Determine the option sensitivity
Using ROC analysis introduced in guide 6.19 we can determine option sensitivity.
Sorting by the binary numbers we get the following:-
The common parts group (green) immediately comes to the top when we sort by descending order. The housing and blade parts
are clustered together (yellow). The engine and shafts are also grouped (blue). By looking for the patterns we can quickly see what
the option sensitivity is for the product family. The housing and the blade are sensitive to the cut width. Obviously the engine is
sensitive to the 2 stroke or 4 stroke options. Shaft selection is sensitive to engine and cut width option. We have a total of four
shafts and only two engines and two blades. This makes things more complicated than they need be. There are a number of ways
to resolve this:-
1. Get engineering to reduce the number of shafts. One shaft would be wonderful. Two would be acceptable.
2. Review the manufacturing process. Is there commonality at the raw materials and processing level perhaps enabling the
items to be part finished and then the variation added when the actual order arrived?
3. Maybe nothing can be done – the shafts have to be the way they are. If that’s the case then each shaft will have to be
forecast according to the percentage of options it is used on. It could be handled by over-planning the shafts which is
better than building mowers to stock – just in case!
• Create a Works Order with each of the required phantom numbers as a line item on the order. This might mean the
creating and maintaining of an options selection guide for each product family.
• Use a configuration tool to allow order entry by selecting the options only. The configuration tool then puts the correct
parts on the order.
Because of the complexity of some products most users choose to use the second method utilising some kind of computerisation
that allows for the management of options that are dependant on other options, for instance, the selection of the right shaft, in the
Sure Fire Lawn Mower.