CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 1 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
BUSBAR TORQUE TEST
Temp:…..…. ºC
PANEL No.
REMARKS
R Y B
INSTRUMENT NAME:…………………………………………………………………………………...
SERIAL NO :…………………………………………………………………………………..
CALIBRATION DATE: ………………………………………………………………………………….
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 2 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
BUS BAR CONTACT RESISTANCE MEASUREMENT
Applied Current : 100 A DC Temp :………ºC
MEASURED RESISTANCE IN MICRO OHMS
PANEL N0. REMARKS
R Y B
INSTRUMENT NAME :………………………………………………………………………………….
SERIAL NO :…………………………………………………………………………………..
CALIBRATION DATE: …………………………………………………………………………………..
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 3 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
CIRCUIT BREAKER CONTACT RESISTANCE MEASUREMENT
Applied Current: 100 A DC Temp:………ºC
MEASURED RESISTANCE IN µΩ
PANEL N0. CB Serial No. REMARKS
R Y B
INSTRUMENT NAME :………………………………………………………………………………….
SERIAL NO :…………………………………………………………………………………..
CALIBRATION DATE: …………………………………………………………………………………..
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 4 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
CURRENT TRANSFORMER
Panel No. :
Name plate rating details of the equipment
Type Insulation level :
Serial No R: Y: B:
Core Class VK/VA Ratio Used for
a) Insulation Resistance Measurement : ( 500 V megger )
Temp:…........ºC
Test IR Value Measurement in Ω
CT cores combination & R Phase Y Phase B Remarks
Test point Phase
Core-1 1S1 to Earth
Core-2 2S1 to Earth
b) Polarity Test :
Secondary
CT Cores R Y B
Terminals
Core-1 1S1 to 1S2 & 1S3
Core-2 2S1 to 2S2 & 2S3
c) Winding Resistance Test :
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 5 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
CT Core Phase Terminals Resistance Remarks
1S1 – 1S2
R
1S1 – 1S3
1S1 – 1S2
1
Y 1S1 – 1S3
1S1 – 1S2
B
1S1 – 1S3
2S1 – 2S2
R
2S1 – 2S3
2S1 – 2S2
2 Y
2S1 – 2S3
2S1 – 2S2
B
2S1 – 2S3
d) Ratio Test :
Applied
Measured Measured Secondary Current in A
Core No Actual Ratio Primary
Terminals R Y B
current in A
1S1 -1S2
1
1S1 – 1S3
2S1 – 2S2
2
2S1 – 2S3
INSTRUMENT NAME :………………………………………………………………………………….
SERIAL NO :………………………………………………………………………………….
CALIBRATION DATE: …………………………………………………………………………………..
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 6 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
FUNCTIONAL CHECKS
11 kV Circuit Breaker Local Operations & Interlocks
ITEM TO
WHAT TO CHECK COMMENTS REMARKS
CHECK
BREAKER - CAN RACK IN & OUT SMOOTHLY
- EARTH SWITCH CANNOT BE CLOSED
- VCB CLOSED: BKR CANNOT BE RACK OUT
SERVICE
POSTION - VCB OPENED: BKR CAN BE RACK OUT
- MAIN DOOR CANNOT BE OPENED
- VCB CAN BE CLOSED
- VCB CLOSED: BKR CANNOT BE RACKED IN
TEST
POSITION - CONTROL PLUG CAN BE REMOVED
- EARTH SWITCH CAN BE CLOSED
INTERMEDIATE
- VCB CANNOT BE CLOSED
POSITION
- CAN OPEN & CLOSE SMOOTHLY
EARTH SWITCH
- PADLOCK FACILITY PROVIDED
CB PLUG - WITH OUT CB PLUG CB NOT POSSIBLE TO RACK IN
VT SHUTTER
- SMOOTH OPENING & CLOSING
PT SHUTTERS
CB ON/OFF BY -ON COMMAND
ELECTRICAL
COMMAND -OFF COMMAND
CB ON/OFF
-ON & OFF CHECKED
MANUAL
INSTRUMENT NAME :………………………………………………………………………………….
SERIAL NO :………………………………………………………………………………….
CALIBRATION DATE: ………………………………………………………………………………….
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 7 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
VOLTAGE TRANSFORMER
TYPE :
RATED VOLTAGE :
RATIO :
OUTPUT (VA) :
PURPOSE :
SERIAL No. : R……………………….Y………………………B…………………….
YEAR OF MANUFT :
INSULATION, RATIO, POLARITY & RESISTANCE TEST
1. INSULATION TEST ( )
MEGGER
WINDING R Y B
(V)
PRIMARY TO EARTH 5000
PRIMARY TO SECONDARY-1 1000
PRIMARY TO SECONDARY-2 1000
SECONDAY -1 TO EARTH 500
SECONDAY -1 TO EARTH 500
SECONDAY -1 TO SECONDARY - 2 500
a) Polarity Test :
Secondary
CT Cores R Y B
Terminals
Core-1 a1 – n1
Core-2 a2 – n2
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 8 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
VOLTAGE TRANSFORMER
3. RATIO CHECK:
APPLIED PRIMARY MEASURED MEASURED
PHASE
VOLTAGE (V) VOLTAGE (V) ON VOLTAGE (V) ON
PRIMARY
SECONDARY-1 SECONDARY-2
RY
YB
BR
RN
YN
BN
4. VT WINDING RESISTANCE: TEMP:……. ºC
PHASE PRIMARY(K) SECONDARY-1 (m) SECONDARY-2 (m)
R
INSTRUMENT NAME:………………………………………………………………………………….
SERIAL NO :………………………………………………………………………………….
CALIBRATION DATE: …………………………………………………………………………………
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 9 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
PROTECTION RELAY TESTING
RELAY DETAILS
TYPE :……………………. MAKE :………………………………
AUX. VOLTS :……………V SERIAL NO :…………………………
GENERAL INSPECTION AND CHECKS
Sl.No. Checks Result
1 Installation and wiring correct to relevant drawings
2 Model number or rating information is correct
3 Output contacts are operating properly
4 LED Indication operation
a. Measurement:
CT RATIO :……………………………
Phase Phase R Phase Y Phase B Earth
Current Injected(A)
Current displayed
on Relay(A)
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 10 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
b. O/C & E/F Function
Characteristic Curve = NI
Setting Current Is> Pickup Current Drop off Current
Phase Remarks
Amps. Amps Amps.
R 1.0
Y 1.0
B 1.0
E/F 1.0
Characteristic Curve = NI
Setting Injected =2 x Is Injected=5 x Is
TMS
Phase Current
(A) Expected Time Sec. Actual Time Sec. Expected Time Sec. Actual Time Sec.
R 1.0 0.1
Y 1.0 0.1
B 1.0 0.1
E/F 1.0 0.1
C . Testing definite time stages
High set stage I >>
Test element Relay setting Current injected
Time setting (Sec) Operating time (Sec)
I >> (A) (A)
R 1 2
Y 1 2
B 1 2
E/F 1 2
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 11 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
d. Final settings for O/C & E/F Function
Setting Injected =2 x Is Injected=5 x Is
TMS
Phase Current
(A) Expected Time Sec. Actual Time Sec. Expected Time Sec. Actual Time Sec.
R
Y
B
E/F
INSTRUMENT NAME:…………………………………………………………..………………………….
SERIAL NO :……………………………………………………………………………………….
CALIBRATION DATE: ………………………………………………………………………………….……
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 12 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
HIGH VOLTAGE TEST
1. INSULATION RESISTANCE TEST
Test Voltage: 5 kV DC Ambient Temp:………ºC
Voltage Applied Between BEFORE HV ( Ω) AFTER HV ( Ω)
R to Y+B+ Earth
Y to R+B+ Earth
B to R+Y+ Earth
2. HIGH VOLTAGE TEST
Applied Voltage: 22.4 kV AC for 60 SEC
Voltage Applied Between Leakage Current (mA) Result
R to Y+B+ Earth
Y to R+B+Earth
B to R+Y+Earth
INSTRUMENT NAME:………………………………………………………………………………….
SERIAL NO :…………………………………………………………………………………
CALIBRATION DATE: …………………………………………………………………………………
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 13 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
PRIMARY INJECTION TEST ON CT CIRCUIT
PRIMAR
CT RATIO PHASES Y ENTER DETAILS OF MEASURING POINTS AND PHASES
& PUROSE INJECTED CURREN
SWGR SWGR
T (Amps)
TERMINAL BLOCK - SA1 SWITCH
CORE -1 X311 X312 X313 X314 2 6 10 1
Ratio -
R–E
Metering R–Y
R–B
PRIMAR
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES Y
&
INJECTED CURREN
PUROSE SWGR SWGR.
T (Amps)
AMMETER DISPLAY
CORE -1 R Y B
Ratio - R–E
R–Y
Metering
R–B
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 14 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
PRIMARY INJECTION TEST ON CT CIRCUIT
PRIMARY
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES INJECTED CURRENT
& PUROSE (Amps) SWGR
SWGR
TERMINAL BLOCK TEST PLUG
X301 X302 X303 X304 1/22 23/24 25/26 27/28
CORE -2
Ratio - R–E
PROT. R–Y
R–B
PRIMARY
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES INJECTED CURRENT
& PUROSE (Amps) SWGR
SWGR
RELAY RELAY DISPLAY
49 51 53 56 R Y B N
CORE -2
Ratio - R–E
PROT. R–Y
R–B
INSTRUMENT NAME:………………………………………………………………………………….
SERIAL NO :………………………………………………………………………………….
CALIBRATION DATE: …………………………………………………………………………………
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 15 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
PRIMARY INJECTION TEST ON CT CIRCUIT
PRIMARY
CT RATIO
PHASES INJECTED CURRENT ENTER DETAILS OF MEASURING POINTS AND PHASES
& PUROSE (Amps) SWGR SWGR
TERMINAL BLOCK - TEST PLUG
X301 X302 X303 X304 21/22 23/24 25/26 27/28
CORE -1
Ratio - R–E
Protection. R–Y
R–B
PRIMARY ENTER DETAILS OF MEASURING POINTS AND PHASES
CT RATIO
PHASES INJECTED CURRENT
& PUROSE (Amps) SWGR SWGR
RELAY RELAY DISPLAY
49 51 53 56 R Y B N
CORE -1
Ratio -
R–E
Protection R–Y
R–B
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 16 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
PRIMAR Y INJECTION TEST ON CT CIRCUIT
PRIMARY
CT RATIO
PHASES INJECTED CURRENT ENTER DETAILS OF MEASURING POINTS AND PHASES
& PUROSE (Amps) SWGR SWGR
TERMINAL BLOCK - SA1(SELECTOR SWITCH)
X311 X312 X313 X314 2 6 10 1
CORE -2
Ratio - R–E
Metering R–Y
R–B
PRIMARY
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES INJECTED CURRENT
& PUROSE (Amps)
SWGR
AMMETR DISPLAY
R Y B N
CORE -2
Ratio -
R–E
Metering R–Y
R–B
INSTRUMENT NAME:………………………………………………………………………………….
SERIAL NO :…………………………………………………………………………………
CALIBRATION DATE: …………………………………………………………………………………
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 17 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
VOLTMETER FUNCTIONAL TEST
1. INSTRUMENT DETAILS
MAKE :…………………………….
RANGE : ………………………………..
MODEL/TYPE :…………………………….
VT RATIO :…………………………….
2. SECONDARY INJECTION
Expected Measured
Applied Voltage
Sl. No. Reading (KV) Reading (KV) % Error
(V)
[s] [ns]
1
2
3
4
5
(ns – s)
% Error = --------------------- x 100
(Full scale value)
3. EQUIPMENT USED :
INSTRUMENT NAME
MAKE / MODEL SERIAL NO. CAL DUE DATE
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :
CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 18 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client
Signature : Signature : Signature : Signature :
Name : Name : Name : Name :
Date : Date : Date : Date :