JBCC C and Cguide 2014 03 Complete 2
JBCC C and Cguide 2014 03 Complete 2
1
2
This composite and updated guide includes earlier publications by the JBCC® as a desktop reference manual for
consultants and contractors alike. This guide seeks to simplify the tendering for and the administration of building
agreements and to avoid/minimise disagreements arising from poor contract administration - in the interests of
standardisation of documentation and good practice in the building industry.
The JBCC® accepts no liability for loss, damage or expense incurred as a result of information provided in good faith in this
guide
Definitions: This is a composite collection of definitions used in the three JBCC® Agreements. There may be minor
variations in some definitions as the wording, for example, in the Principal Building Agreement may not
totally match that in the Minor Works Agreement albeit the intent is the same
Contract Data: The 2014 edition of JBCC® Agreements introduced a single ‘contract data’ to be completed by the
principal agent to invite tenders, and to be completed by the contractor as the form of tender / offer
Completed ‘contract data for the Principal Building Agreement, (similar for the N/S Subcontract Agreement and the Minor
Works Agreement) are included to illustrate how these forms must be used
Completed ‘agreement’ form on appointment of a (sub)contractor = the last page of each of the agreements, signed by
the parties as a record of the project data for the Principal Building Agreement, (similar for the N/S Subcontract Agreement
and the Minor Works Agreement)
Completed ‘waiver of the contractor’s lien’ and ‘certificate of site possession” forms follow
The ‘completion’ process is described in five stages with completed certificates of interim, practical and final completion
of the works as a whole or in sections. The concept of ‘latent liability’ of the contractor is explained in detail
Aspects of the ‘payment’ process are described in notes and illustrated with completed payment and related certificates
supplemented by the calculation of interest and the administration of the various ‘securities’
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
3
1. DEFINITIONS
!
Only key definitions used in JBCC® agreements are repeated for ease of reference; - there may be minor
!
differences in wording
A word or phrase in bold type in a JBCC® Agreement or this Guide shall have the meaning assigned to it in these
! definitions. A word or phrase not in bold type shall be interpreted in the context of its usage
Numbers, generally preceded by “in terms of”, indicate references to clause numbers [0.0] in that document
Headings of clauses are for reference purposes only and shall not be used in the interpretation of such
clauses
ADJUSTMENT AMOUNT: The amount calculated in terms of the applicable adjustment formula using the tax
!
exclusive method – applicable in the CPAP guide
AGENT: The entity dealing with specific aspects of the works appointed by the employer or delegated by the
principal agent
AGREEMENT: The JBCC® Principal Building Agreement, the JBCC® Nominated/Selected Subcontract
Agreement or the JBCC® Minor Works Agreement and the respective completed JBCC® contract data, or the
!
corresponding JBCC® Public Sector Agreements and the respective completed JBCC® contract data
! BASE MONTH: The calendar month during which tenders closed – applicable in the CPAP guide
BILLS OF QUANTITIES: The document drawn up in accordance with the measuring system [CD]
BUDGETARY ALLOWANCE: An amount included in the contract sum for work intended for execution by the
BUDGETARY ALLOWANCE: An amount included in the n/s subcontract sum for work intended for execution
!
by the subcontractor the extent of which is identified but not detailed
CALENDAR DAYS: Twenty four (24) hour days commencing at midnight (00:00) which include Saturdays,
! Sundays, proclaimed public holidays and recorded annual builders’ holiday periods [CD]
CERTIFICATE of FINAL COMPLETION: A certificate issued by the principal agent to the contractor with a
copy to the employer stating the date on which final completion of the works, or of a section thereof, was
!
achieved
CERTIFICATE of INTERIM COMPLETION: A certificate issued by the contractor to the subcontractor stating
!
the date on which interim completion of the n/s subcontract works, or a section thereof, was achieved
CERTIFICATE of PRACTICAL COMPLETION: A certificate issued by the principal agent to the contractor with
a copy to the employer stating the date on which practical completion of the works, or of a section thereof,
!
was achieved
CONSTRUCTION EQUIPMENT: Equipment and/or plant provided by or belonging to the contractor and/or the
!
subcontractor used during the construction period
CONSTRUCTION INFORMATION: All information issued by the principal agent and/or agents including the
contract documents, specifications, drawings, schedules, notices and contract instructions required for the
!
execution of the works
CONSTRUCTION PERIOD: The period commencing on the intended date [CD] of possession of the site by the
!
contractor and ending on the date of practical completion (Private Sector Agreement only)
CONSTRUCTION PERIOD: The period commencing on the date of the letter of appointment to the contractor
!
and ending on the date of practical completion (Public Sector Agreement only)
!
CONTRACT DATA: The document listing the contract variables
! [CD]: The notation used where project specific information is recorded in the contract data
CONTRACT DOCUMENTS: This agreement, the contract drawings, the priced document and other identified
!
documents [CD]
CONTRACT DRAWINGS: The drawings listed on which the accepted tender or the negotiated amount was
!
based [CD]
CONTRACT INSTRUCTION: A written instruction issued by or under the authority of the principal agent to the
contractor, which may include drawings and other construction information
CONTRACT MINUTES: A comprehensive set of minutes prepared by the principal agent in which all pertinent
contractual information that arises at meetings is progressively recorded (defined in MWA, applicable to all
agreements)
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
4
CONTRACT PRICE ADJUSTMENT: Provision used for the adjustment of the contract value [CD] (using
!
information published monthly by Statistics South Africa)
CONTRACT SUM: The accepted tender amount, inclusive of tax, that is not subject to adjustment [CD]
! CONTRACT VALUE: A monetary value initially equal to the contract sum that is subject to adjustment in terms
of the agreement
CONTRACTOR: The party [CD] contracting with the employer for the execution of the works (PBA + MWA only)
CONTRACTOR: The party contracting with the subcontractor for the execution of n/s subcontract works [CD]
!
(NSSA only)
CONTRACTUAL DATE FOR COMPLETION: The actual date for practical completion of the works or any
revision of the initial contractual date for practical completion in terms of the agreement, whichever occurs first,
!
provided that if no revision is granted, it shall mean the initial contractual completion date (used in CPAP guide)
CPAP: The Contract Price Adjustment Provisions used for the adjustment of fluctuations in the cost of labour,
!
plant, materials and goods that are required to construct the works (used in CPAP guide)
DAMAGES: Proven financial loss claimed or awarded to compensate the contractor where the subcontractor
!
has not completed the subcontract works in accordance with the contract documents
DEFECT: Any aspect of materials and workmanship forming part of the works that does not conform to the
!
contract documents
DEFECT: Any aspect of materials and workmanship forming part of the n/s subcontract works that does not
DIRECT CONTRACTOR: An entity appointed under separate agreement by the employer to do work on site
! EMPLOYER: The party [CD] contracting with the contractor for the execution of the works
FINAL ACCOUNT: The document prepared by the principal agent that reflects the final contract value of the
!
works at final completion or termination
FINAL COMPLETION: The stage of completion of the works as certified by the principal agent as being free of
! defects
FINAL PAYMENT CERTIFICATE: The certificate issued by the principal agent after the issue of the certificate
! of final completion after the final account has been agreed, or deemed to have been agreed
!
FORCE MAJEURE: An exceptional event or circumstance that:
!
(c) could not reasonably have been avoided or overcome
FREE ISSUE: Materials and goods provided at no cost to the contractor and/or the subcontractor by the
!
employer for inclusion in the works whether stored on or off the site or in transit [CD]
GUARANTEE for ADVANCE PAYMENT: A security in terms of the JBCC® Security for Advance Payment form
GUARANTEE for DEPOSIT: A security in terms of the JBCC® Security for Deposit form obtained by the
!
contractor from an institution approved by the employer [CD] (used in the MWA only)
GUARANTEE for CONSTRUCTION: A security in terms of the JBCC® Security for Construction form obtained
!
by the contractor from an institution approved by the employer [CD]
GUARANTEE for PAYMENT: A security in terms of the JBCC® Security for Payment form obtained by the
employer from an institution approved by the contractor [CD]
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
5
INDEX: A work group index published in a Stats SA Statistical Release P0151 or any index calculated from a
!
selected set of sub-indices (used in the CPAP guide)
INTEREST: The bank rate applicable from time to time to registered banks borrowing money from the Central or
Reserve Bank of the country [CD]. The ruling bank rate on the first calendar day of each month shall be used in
!
calculating the interest due for such month (Private Sector Agreements)
!
Or …
!
INTEREST: The interest rate in terms of legislation applicable to organs of state (Public Sector Agreements)
INTERIM COMPLETION: The state of completion where the n/s subcontract works, or a section thereof, is
LATENT DEFECT: A defect that a reasonable inspection of the (n/s subcontract) works by the principal agent
LIST for COMPLETION: A list issued by the principal agent where practical completion has been certified,
!
listing defects and/or outstanding work to be completed
LIST for FINAL COMPLETION: An updated list for completion issued by the principal agent after the
inspection of the works for final completion, where final completion has not been achieved, listing defects
and/or outstanding work to be completed to achieve final completion
LIST for INTERIM COMPLETION: A list issued by the contractor after the inspection of the n/s subcontract
works for interim completion, where interim completion has not been certified, listing outstanding work and/or
defects to be completed to achieve interim completion (JBCC® Nominated/Selected Subcontract Agreement)
LIST for PRACTICAL COMPLETION: A comprehensive and conclusive list issued by the principal agent after
the inspection of the works for practical completion, where practical completion has not been achieved, listing
MATERIALS AND GOODS: Unfixed materials, goods and/or items fabricated for inclusion in the works whether
!
stored on or off the site or in transit
MORA INTEREST: The rate of interest payable prescribed in law from time to time [CD] where performance,
! which is due and enforceable, has not been paid on or before a determined date
NOTICE: A communication issued by either party, the principal agent and/or agents to the other party or any
agent to, inter alia, record an event, request for outstanding information and/or where suspension and/or
!
resumption of the (n/s subcontract) works, or termination of the agreement is contemplated
N/S SUBCONTRACT AGREEMENT: The JBCC® Nominated/Selected Subcontract Agreement and the
completed JBCC® contract data, between the contractor and the subcontractor used in conjunction with the
N/S SUBCONTRACT BILLS OF QUANTITIES: The document drawn up in accordance with the measuring
N/S SUBCONTRACT CONSTRUCTION INFORMATION: All information issued by the principal agent and or
agents including specifications, drawings, notices and contractor’s instructions required for the execution of
!
the n/s subcontract works
N/S SUBCONTRACT CONSTRUCTION PERIOD: The period commencing on the intended date [CD] of access
!
to the site according to the programme and ending on the date of interim completion
!
N/S SUBCONTRACT DATA: The document listing the subcontract variables
N/S SUBCONTRACT DOCUMENTS: This n/s subcontract agreement, the n/s subcontract drawings, the n/s
!
subcontract priced document and other identified documents [CD]
N/S SUBCONTRACT DRAWINGS: The drawings listed on which the tender is based [CD]
N/S SUBCONTRACT FINAL ACCOUNT: The document, prepared by the principal agent, which reflects the
! final n/s subcontract value of the n/s subcontract works at final completion or termination
N/S SUBCONTRACT PAYMENT ADVICE: A document issued at regular intervals [CD] by the contractor stating
the amount due and payable by the contractor to the subcontractor or vice versa using the JBCC ® N/S
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
6
N/S SUBCONTRACT PAYMENT NOTIFICATION: A document issued with each payment certificate by the
principal agent stating the amount due and payable by the contractor to the subcontractor or vice versa using
the JBCC® N/S Subcontract Payment Notification format
N/S SUBCONTRACT PRICED DOCUMENT: N/S subcontract bills of quantities, schedule of rates or other
N/S SUBCONTRACT PROGRAMME: A diagrammatic representation of the planned execution of units of work or
activities indicating the dates for commencement and completion as prepared by the subcontractor in conformity
N/S SUBCONTRACT RECOVERY STATEMENT: The statement prepared at regular intervals by the contractor
!
using the JBCC® N/S Subcontract Recovery Statement format
N/S SUBCONTRACT GUARANTEE for ADVANCE PAYMENT: A security in terms of the JBCC® Security for
! Advance Payment form obtained by the subcontractor from an institution approved by the employer [CD]
N/S SUBCONTRACT GUARANTEE for CONSTRUCTION: A security in terms of the JBCC® Security for
! Construction form obtained by the subcontractor from an institution approved by the contractor [CD]
N/S SUBCONTRACT GUARANTEE for PAYMENT: A security in terms of the JBCC® Security for Payment form
obtained by the contractor from an institution approved by the subcontractor [CD]
! N/S SUBCONTRACT SUM: The accepted tender amount, inclusive of tax, that is not subject to adjustment [CD]
N/S SUBCONTRACT VALUE: A monetary value initially equal to the n/s subcontract sum and that is subject to
N/S SUBCONTRACT WORKS: The extent of work to be executed by the subcontractor described in the n/s
subcontract documents and contractor’s instructions, which includes free issue, and materials and goods.
Work or installations to be executed by direct contractors and others responsible to the employer are excluded
! [CD]
PARTY: The employer or the contractor and “parties” shall refer to both of them
!
PARTY: The contractor or the subcontractor and “parties” shall refer to both of them
PAYMENT CERTIFICATE: A certificate issued at regular agreed intervals [CD] by the principal agent to the
!
parties certifying the amount due and payable in terms of the JBCC® Payment Certificate format
PENALTY: The stipulated amount per calendar day [CD] payable by the contractor to the employer where the
! date or the revised date for practical completion, whichever is the later, has not been met
PRACTICAL COMPLETION: The stage of completion as certified by the principal agent where the works or a
section thereof has been completed free of patent defects other than minor defects identified in the list for
!
completion and can be used for the intended purpose [CD]
PRELIMINARIES: The priced items listed in the preliminaries document with any additions, alterations or
!
modifications thereof incorporated in the (n/s subcontract) contract documents
PRICED DOCUMENT: Bills of quantities, schedule of rates or other documents appropriate to this agreement
[CD]
PRIME COST AMOUNT: An amount included in the (n/s subcontract) contract sum for the delivered cost of
! materials and goods obtained from a supplier as instructed by the principal agent
PRINCIPAL AGENT: The entity [CD] appointed by the employer with full authority and obligation to act in terms
of this agreement
PROGRAMME: A diagrammatic representation of the planned execution of units of work or activities indicating
the dates for commencement and completion prepared and maintained by the contractor
PROGRAMME: A diagrammatic representation by the contractor of the planned execution of units of work or
activities by the contractor and subcontractors indicating the dates for commencement and completion
PROVISIONAL SUM: An amount included in the contract sum for the supply and installation of work by a
!
subcontractor
RECOVERY STATEMENT: The statement prepared and issued in conjunction with each payment certificate by
!
the principal agent in terms of the JBCC® Recovery Statement format
RETENTION: The security selected by the contractor as a payment reduction from the value certified in a
!
payment certificate
RETURNABLES: Documents listed [CD] to be provided by the tenderer on notice from the employer
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
7
!
!
SCHEDULE: The listed variables applicable to the preliminaries
SECTION: An identified portion of the works for which practical completion is required by a date earlier than
SECURITY: A monetary guarantee provided by the employer to the contractor, or the contractor to the
employer in terms of this agreement [CD] from which either party may recover expense and loss in the event of
! default
SECURITY: A monetary guarantee provided by the contractor to the subcontractor, or the subcontractor to
the contractor in terms of this agreement [CD] from which either party may recover expense and loss in the
!
event of default
SHOP DRAWINGS: Drawings, diagrams, designs, illustrations, schedules, performance charts, brochures,
setting out drawings, shop details and other data which are prepared by the contractor, subcontractor,
manufacturer, supplier or distributor which illustrate manufacturing details and methods of execution of work
!
(used in the ASAQS Preliminaries)
!
SITE: The land or place where the works is to be executed [CD]
!
STATS SA: Statistics South Africa as the provider of the indices used for CPAP (used in the CPAP guide)
STATUS REPORT: A report compiled by the principal agent and/or agents in the event of termination of the
agreement, or where the works has been suspended due to a force majeure event, or in the event of
termination of the n/s subcontract agreement by the contractor, to record the state of completion or otherwise
of the works or the n/s subcontract works, as the case may be. Such status report may include marked up
drawings and photographs
!
for which a provisional sum has been included in the contract sum [CD]
!
SUSPENSION: The temporary cessation of the (n/s subcontract) works by the contractor (subcontractor)
!
TAX: Value-added tax or any other tax, duty or levy applicable by law
VALUATION PERIOD: The contractual period between two payment certificates or the period from
! acceptance of tender up to the first payment certificate issued (used in the CPAP guide)
!
WORK COMPLETED IN TIME: The work value executed up to the contractual date for completion, and …
WORK COMPLETED LATE: The work value executed after the contractual date for completion (used in the
! CPAP guide)
WORK GROUP: A “grouping” of work descriptions that are more commonly undertaken by a particular
recognised “tradesman”, or that is generally recognised in the construction industry as sharing common
characteristics, and for which an index is available, or is determined by a means that is acceptable to both the
!
employer and contractor (used in the CPAP guide)
WORK VALUE: The value of work executed that qualifies for adjustment in terms of these provisions – (used in
!
the CPAP guide)
WORKING DAYS: Calendar days which exclude Saturdays, Sundays, proclaimed public holidays and recorded
annual builders’ holiday periods [CD]
WORKS: The extent of work to be executed by the contractor described in the contract documents and
contract instructions, which includes free issue, and materials and goods. Work or installations to be
executed by direct contractors and others responsible to the employer are excluded [CD]
!
!
!
!
!
!
!
!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
Page 1
8
CONTRACT DATA
used in conjunction with the
Preface
JBCC® Constituents
The Joint Building Contracts Committee® NPC (JBCC®) is representative of building owners and developers, professional
consultants and general and specialist contractors who contribute their knowledge and experiences to the compilation of
JBCC® documents. JBCC® documents portray the consensus view of the constituent members and are published in the
interests of standardisation and good practice with an equitable distribution of contractual risk. The constituents are:
This contract data contains unique requirements applicable to the project and variables referred to in the JBCC® Principal
Building Agreement. The information provided in this document by the principal agent is complete and accurate at the time of
calling for tenders. Where additional information becomes available, all tenderers will be informed in writing. Reference to
clause numbers in the JBCC® Principal Building Agreement are shown in [square brackets] in this contract data eg [3.2.1].
Spaces requiring information must be filled in, or marked as ‘not applicable’ but not left blank. This contract data, when
completed and submitted by the contractor, becomes the form of tender. Where the contractor is appointed, the contract
documents comprise the signed JBCC® Principal Building Agreement, this completed contract data, the priced document,
drawings and other listed documents
Warning
The JBCC® Principal Building Agreement, the JBCC® Nominated / Selected Subcontract Agreement and respective
Contract Data Edition 6.1 have been coordinated with JBCC® Certificates and other support documents. Forms from
previous editions are not compatible with Edition 6.1
© Copyright Reserved
The name ‘Joint Building Contracts Committee®’, the abbreviation JBCC®, the product eJBCC® and the JBCC logo are
registered trademarks. The Joint Building Contracts Committee® claims authorship of this work in terms of the Copyright Act
No 98 of 1978 as amended. All rights are reserved. No part of this publication may be reproduced, stored in any retrieval
system, or transmitted, in any form or by any means, without the prior written permission of the Joint Building Contracts
Committee® NPC. Unauthorised reproduction of the work is an infringement of the copyright and judicial proceedings can
and will be instituted to obtain relief and the recovery of damages
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 2
9
A TENDER INFORMATION
A1 Project name
Cosy Flats
A2 Works description
Existing offices converted into flats, existing 6 storey reinforced concrete structure retained,
partition and external walls demolished,new installation of electrical and plumbing services,
external and internal walls and finishes, refurbishment of existing (2) lifts.Prepare street level
sapce for future retail. There is no basement. Space behind the building to store construction
materials etc. The building will not be occupied during the construction period
A3 Site description
A4 Employer
Business registration number 1 234 567 890 VAT/GST 4 567 890 123
E-mail [email protected]
Registered street address 40 Mozart Street, Symphony Village
A5 Principal agent
Name
Telephone Fax
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 3
10
A6 Agent
Name
Telephone Fax
A7 Agent
Name
Telephone Fax
A8 Agent
Name
Telephone Fax
A9 Agent
Name
Telephone Fax
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 4
11
B CONTRACT DATA
Clause references apply to the JBCC® Principal Building Agreement Edition 6.1 (PBA) published March 2014
Only clauses in the PBA requiring the provision of information [CD] are quoted below
Priced document
Lump sum priced document, or yes / no? No
Priced bills of quantities (BoQ) yes / no? Yes
System/method of measurement SA Standard System Rev ? 2013
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 5
12
10.0 Insurances
By the employer in the joint names of the parties, yes/no ? yes Obligation Currency Insured amount
Contract Works Insurance (CWI) (including materials and goods, temporary works) contract sum
Allowance for professional fees and escalation of the insured value at 25% pa, or ? % % 23.0%
Free issue material at new replacement value, added to CWI, where applicable not applicable
Employer owned surrounding property (care,custody, control or worked on) not applicable
Public Liability Insurance (each and every claim OR unlimited / value ?) every claim 10 000 000.00
Supplementary Insurance (incl CWI extensions) per CWI
Removal of Lateral Support Insurance employer ZAR 10 000 000
Other: not applicable
Policy deductibles Currency Amount
- Works / free issue contractor ZAR 10 000.00
- Employer owned surrounding properties contractor not applicable
- Public Liability contractor ZAR 10 000.00
- Supplementary Insurance contractor ZAR 10 000.00
- Removal of Lateral Support contractor not applicable
- Other: contractor
or…
By the contractor in the joint names of the parties, yes/no ? no Currency Insured amount
Contract Works Insurance (CWI) (including materials and goods, temporary works) contract sum
Allowance for professional fees and escalation of the insured value at 25% pa, or ? % %
Free issue material at new replacement value
Public Liability Insurance (each and every claim OR unlimited for the period)
Supplementary Insurance (incl CWI extensions) per CWI
Policy deductibles
Other:
11.0 Security
11.1.1-5 The contractor shall provide a Guarantee for Construction to the employer>D11.2-3 yes / no? yes
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 6
13
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 7
14
19.1.1 Criteria to achieve practical completion (the BoQ may contain a more detailed description)
Per Specification
25.0 Payment
25.0 Currency: ZAR South African Rand
25.2 Issue of regular payment certificates on date@month seventh or… day of week n/a
25.3.2 Materials and goods off site - paid subject to ... Guarantee for Advance Payment provided ? no
25.3.4/26.9.5 Contract price adjustment provisions Method? fixed price
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 8
15
Nil
Note: The amendments contained herein or in the single referenced Annexure constitute the only
amendments to the standard JBCC Agreement that will apply. No other amendments shall be of any
force or effect.”
NOTE: If insufficient space, please see annexure:-
C TENDER CLOSING
Alternate offer considered ? yes / no? No Only if original tender submitted yes / no? No
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 9
16
Where the contractor does not indicate option 'A' or option 'B' - option 'A' shall apply
The contractor shall provide a breakdown of charges (incuding tax) within 15 working days of
the date of acceptance of tender and, where applicable, an apportionment of preliminaries per
section
Where such information is not provided the following subdivision shall be deemed to apply:
- 10% of the amount shall not be varied
- 15% varied in proportion of the contract value to the contract sum
- 75% varied in proportion to the revised construction period compared to the initial yes
construction period …
Or … Or …
Option B The contractor shall within 15 working days of the date of possesion of the site provide the
principal agent with a detailed breakdown of preliminaries amounts for the works as a whole,
or per section where applicable, including administative and supervisory staff charges and for no
the use of construction equipment in terms of the programme.
Where the contractor does not indicate option 'A' or option 'B' - option 'A' shall apply
Notes
1 By submission of this tender to the employer the tenderer offers and agrees to execute and complete the works
and remedy any defects in conformity with the specification for the tender sum stated - to be paid in instalments
as work is completed
2 The tender shall remain in full legal force for forty five (45) calendar days from the closing date of the tender.
The tenderer accepts liabilty for damages that may be suffered by the employer should the tender validity
period not be honoured
3 The lowest or any offer will not necessarily be accepted by the employer - nor need reasons be given for such a
decision
4 Any provision in this agreement that may confer any benefit or right in favour of any subcontractor shall be
binding on the parties and be capable of acceptance by such subcontractor at any time
5 Annexures … marked
A Not applicable
B Not applicable
C Not applicable
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
Page 10
17
(print) TENDERER Capacity who, by its SIGNATURE warrants authority thereto Date Location
TENDERER'S DETAILS
Name Purrfect Builers
E-mail [email protected]
Registered street address 22 Strauss Crescent, Symphony Village
Copyright reserved JBCC® Principal Building Agreement Edition 6.1 March 2014 CONTRACT DATA
18 of 32 Pages
Page 32
AGREEMENT
This agreement, the completed contract data and the listed documents [CD] comprise the entire contract between
the parties. Any provision in this agreement that may confer a right or benefit on a subcontractor shall be binding
on the parties and be capable of acceptance by such subcontractor at any time. No representations, terms,
conditions or warranties not contained in this agreement shall be binding on the parties. No agreement or addendum
varying, adding to, deleting or terminating this agreement including this clause shall be effective unless reduced to
writing and signed by the parties
Tax number (VAT/GST) Value Added Tax 4 567 890 Value Added Tax 4 987 654
Signed – who by
signature hereto
warrants authority
Signed - date 201?-11-11 201?-11-11
Signed - witness
Copyright reserved JBCC® Principal Building Agreement Edition 6.01– March 2014
19
®
Certificate of Site Possession for use with the …
Principal Building Agreement Edition used ?
PROJECT DETAILS
The following particulars of the site were pointed out to the contractor by the agent
Information attached hereto: Survey plan with GPS coordinates and levels above mean sea level
This certificate records the hand-over of the site to the contractor for the purpose of constructing the works
in terms of the agreement. A copy of this certificate shall be provided to the contractor
COMPLETION
!!
INTRODUCTION
!
All JBCC® agreements follow the same procedures to achieve Interim, Practical and Final Completion. The procedures
described in the JBCC® agreements to achieve each of the three degrees of completion must be applied strictly to
minimise disagreements later. Other than payment, completion is the most important aspect of the agreement and therefore
no “short cuts” should be taken in certifying any of the degrees of completion. The procedures and time bars applying to
!!
completion and to payment must be strictly adhered to by the principal agent and be observed by the parties
2.0 INTERIM COMPLETION (in terms of the JBCC® N/S Subcontract Agreement only)
!!
!
2.1 PURPOSE
The contractor generally requires the work of all subcontractors to be completed before the date of practical completion
to permit the timeous commissioning of services and general cleaning of the site before relinquishing possession of the site/
works to the employer
!
Note: Stage completion: The contractor and the subcontractor may agree which aspects of the n/s subcontract works
!
must be completed before interim completion can be achieved in a particular project (only applies in the NSSA)
!
2.2
▪
SUBCONTRACT CONSTRUCTION PERIOD AND PROGRAMME
The n/s subcontract construction period set by the principal agent in the pre-tender information and stated in the n/
s subcontract data
▪ Where the contractor has been appointed at the time of calling for the subcontract tender, the principal agent must
consult the contractor in setting the date for interim completion. The contractor and the subcontractor must agree
the n/s subcontract programme in harmony with the works as a whole
▪ The parties may agree to vary the start of the n/s subcontract programme and the intended date of interim
! completion
!
2.3
▪
ACHIEVEMENT OF STAGE COMPLETIONS AND INTERIM COMPLETION
Criteria for stage completions must be set at the start of the n/s subcontract construction period to avoid possible
disputes later
▪ The contractor must inform the principal agent if the assistance of an appointed specialist agent will be required for
the inspection for achievement of interim completion
▪ On achievement of interim completion the responsibility for the n/s subcontract works passes to the contractor.
! This does not relieve the subcontractor of his responsibility in respect of defective or incomplete work
!
2.4
▪
DAMAGES
The subcontractor may be liable for damages to the contractor for the late achievement of interim completion. The
subcontractor must be allowed sufficient time to achieve stage and/or interim completion set by the contractor
▪ Where the subcontractor is prevented from fulfilling obligations due to default of the contractor, other subcontractors
or a direct contractor, the subcontractor shall be entitled to damages. Adjustments to the subcontractor’s
completion dates are not dependant on the contractor obtaining similar adjustments in terms of the agreement with
the employer
!!
▪ The calculation of damages must be shown in the n/s subcontract recovery statement - see page 62
!!
!!
!!
!!
!!
!!
!!
!!
!!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
21
Comple6on
stages
in
JBCC
building
agreements
3 years
CONSTRUCTION PERIOD = Private Sector 90day DLP 5 year LDLP
®
Certificate of lnterim Completion
Issued in terms of clause 18.0 or clause 20.3.1 of the
N/S Subcontract Agreement Edition 6.1 © March 2014
or
NOTE: The subcontractor remains liable for defects until final completion.
Where practical completion has been certified
the Defects Liability Period ends ninety (90) calendar days
from the date of practical completion
subject to clause 21 (final completion)
Date
201?-01-31
Signed by the contractor who certifies that the n/s subcontract works has been completed in accordance
with the specified criteria for interim completion on the date stated,
irrespective of the date of signature of this certificate
3 years
CONSTRUCTION PERIOD = Private Sector 90day DLP 5 year LDLP
▪
PURPOSE
The principal agent must specify in appropriate detail in the contract data at tender stage what quality of work and
degree of completion the contractor has to produce to achieve practical completion to limit subjective interpretation
thereof. This will vary from one project to another depending on the nature and purpose of the building
▪ The professional consultants and the team of contractors have been appointed to provide the employer with a building
that “... can effectively be used for the intended purpose…” Achievement of practical completion is the most important
!
3.2
▪
CONSTRUCTION PERIOD
The principal agent at the tender stage determines and specifies in the contract data the construction period and
the intended date for practical completion of the whole works, or the intended dates for practical completion where
the works is to be completed in sections - but not both!
• During the construction period the principal agent must “inspect the works, or a section thereof, at appropriate
intervals to give the contractor interpretations and direction on the standard of work and the state of completion of the
works required of the contractor to achieve practical completion”… and likewise for work by subcontractors
• Any such interpretations and direction given to the contractor may not be construed as approval of any work or
!
3.3
•
ACHIEVEMENT OF PRACTICAL COMPLETION
The principal agent at the tender stage determines and specifies in the contract data the period required to inspect
the works and to issue the list for practical completion, then the “certificate of practical completion” and finally the
list for completion
• “The contractor shall inspect the works to satisfy himself that the specified degree of completion of the works has
been achieved” and give timeous notice to the principal agent to inspect the works on or before the anticipated date
of practical completion
• The contractor must make provision in his programme (possibly as a sub-programme for the 3-4 weeks before the
date for practical completion) for the inspection period required by the principal agent. The principal agent may
require reasonable notice of the date(s) when the contractor intends such inspection to take place
• The principal agent and other specialist agents must decide during such inspections if the works is “... substantially
complete and can effectively be used for the purpose intended ...”
• Where the degree of completion of the works does not comply with the specifications, the principal agent must
forthwith issue a single “comprehensive and conclusive list for practical completion recording the defects and/or
outstanding work to be completed to achieve practical completion. The principal agent may not add to this list for
practical completion once it has been issued but he can issue a contract instruction at any time where, for example,
a water pipe bursts that must be repaired without delay
• The principal agent can issue an ‘updated’ list for practical completion that excludes remedied defects
• Where the degree of completion of the works complies with the specifications, the principal agent must issue the
certificate of practical completion and a list for completion
• Whilst other appointed agents may assist in such inspections the issue of the certificate of practical completion is
solely the responsibility of the principal agent
• Where the principal agent does not issue the (updated) list for practical completion or the certificate of practical
completion within five (5) working days of such inspection, the contractor may give notice to the principal agent to
comply within a further five (5) working days - failing which practical completion will be deemed to have occurred on
expiry date of such notice
• After certification of practical completion the employer may impose the penalties stated in the contract data (from
the specified or revised date for practical completion until the actual date of practical completion when possession of
the site is relinquished to the employer by the contractor). Similarly, the contractor may be entitled to recover
damages from a subcontractor or vice versa
• The issue of the certificate of practical completion may not occur before the specified/revised date for practical
completion, unless agreed by the parties, as the contractor’s obligation is to hand over the works on the date for
practical completion and not earlier
• The principal agent must issue a certificate of practical completion (and later a certificate of final completion) to
the contractor for each defined section. The certificate for the last section is for the whole works. Thus multiple
! completion dates are applicable to product warranties, the defects liability period and the latent defects liability period
!
3.4 CONSEQUENCES
!
▪ The contractor becomes entitled to compensatory interest (PBA only)
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
Prac%cal
Comple%on
25
applicable
in
the
JBCC
Principal
Building
and
Minor
Works
Agreements
C's CONSTRUCTION PERIOD = Public Sector Note: C fixes items on list for comple6on
®
Certificate of Final Completion
Issued in terms of clause 20.0 or clause 21.0 of the
Principal Building Agreement Edition 6.1 © March 2014
or
Date
201?-02-02
Signed by the principal agent who, as agent for the employer, certifies that the works has been
completed in accordance with the specified criteria for final completion on the date stated,
irrespective of the date of signature of this certificate
®
Certificate of Practical Completion
Issued in terms of clause 19.0 or clause 20.0 of the
Principal Building Agreement Edition 6.1 © March 2014
or
Date
201?-02-02
Signed by the principal agent who, as agent for the employer, certifies that the works has been
completed in accordance with the specified criteria for practical completion on the date stated, irrespective
of the date of signature of this certificate
!!
4.0 FINAL COMPLETION
!
!
4.1 PURPOSE
The definition of final completion requires the principal agent to certify “... the stage of completion of the works to be free
of defects…” The issued certificate of final completion is “…conclusive as to the sufficiency of the works and that the
!
contractor’s obligations have been fulfilled other than for latent defects”
!
4.2
▪
ACHIEVEMENT OF FINAL COMPLETION
The defects liability period (DLP) automatically comes into force on the calendar day following the date of practical
completion and ends at midnight ninety (90) calendar days from that date … or when defects on the list for final
completion have been satisfactorily completed (but not before expiry of the ninety (90) calendar day DLP)
▪ The contractor must “… rectify all items on the list for completion at least ten (10) working days before the expiry of
the DLP and give notice to the principal agent to inspect the works within five (5) working days of receipt of such
notice”. The principal agent must, within reason, inspect the whole of the works for latent defects that may have
become patent during the DLP and not just identified items on the list for completion
▪ The principal agent must forthwith issue to the contractor a list for final completion incorporating the list for
completion and any latent defects that may have become patent to rectify to achieve final completion. The
contractor must give the principal agent notice to inspect rectified items until all defects have been rectified to the
satisfaction of the principal agent
▪ Note: Where the employer takes possession of the site/works before practical completion has been certified – the
principal agent must issue the certificate of practical completion forthwith (specifying the date when possession of
the site/works was relinquished by the contractor) and issue the list for completion of items to be rectified by the
contractor within thirty (30) calendar days
• Where the principal agent does not issue the (updated) list for final completion or the certificate of final
completion within five (5) working days of such inspection, the contractor may give notice to the principal agent to
comply within a further five (5) working days - failing which final completion will be deemed to have occurred on
!
4.3 CONSEQUENCES
!!
▪ The final payment certificate can now be issued
Projects may have to be completed in sections - as separate buildings or by storey. Each section must be clearly defined
with due consideration for common areas, provision of services, safe access by the employer and continued access by the
contractor to complete the works. Sectional completions should be avoided where each section cannot be defined as a
!
homogeneous unit and where there is no reasonable continuity of work for the contractor
Note: The contract works insurance must be effected by the employer to prevent conflict that may arise from multiple
practical completions possibly insured by different insurers. Securities, guarantees, warranties and the like should only be
!
provided for the works as a whole and not for individual sections
!
5.2 ACHIEVEMENT OF SECTIONAL FINAL COMPLETION
Where sectional completions are required - each section (other than the last section) must be treated as unique for
completion purposes. Thus each section requires:
▪ A certificate of interim completion for each subcontractor
▪ A certificate of practical completion
!
▪ A certificate of final completion (other than the last section)
!
5.3 CONSEQUENCES
Payment is always made for the works as a whole - never for a section - by issuing the following documents:
▪ A (monthly) interim payment certificate
▪ A (monthly) recovery statement
▪ A (monthly) payment notification to each subcontractor
▪ A final account
▪ A final payment certificate
!
▪ A certificate of final completion for the works as a whole incorporating the last section
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
Final
Comple-on
29applicable
in
the
JBCC
Principal
Building
and
Minor
Works
Agreements
Note:
CONSTR. PERIOD = Private C's
public
liability
period
ends
Value
of
securi6es
reduces
NSSA
warran6es
ceded
to
E
CONSTR. PERIOD = Public
30
!!
6.0 LATENT DEFECTS LIABILITY PERIOD
!
!
6.1 PURPOSE
In common law the liability of the contractor (and of agents described in the professional appointment agreement) to the
employer for latent defects is open ended and will only expire with the demolition of the building - clearly an untenable
situation. In all JBCC® agreements the latent defects liability period (LDLP) of the contractor is restricted to a period of five
(5) years from the certified date of final completion or the date of termination by the contractor or where execution of the
!
works has become impossible:-
▪ The definition of a “latent defect” relies on the definition of “defect”. Thus the latent defect definition becomes “... any
aspect of the works which ... includes an imperfection that impairs the structure, composition or function of the works ...
which a reasonable inspection ... would not have revealed before the issue of the list for final completion”, and
!
▪
“defects which may appear up to the date of final completion shall be addressed...."
This definition does not specify how a defect that becomes apparent after final completion is to be dealt with. Where
this occurs, the employer must give notice to the contractor to remedy the defect within the LDLP. Failure by the
contractor to do so entitles the employer to employ another contractor to remedy the patent defect(s) and to claim
such expense from the contractor. The obligation to remedy a defect is clear in common law and in the Consumer
!
▪
Protection Act
The “period“ is defined: “The latent defects liability period shall commence at the start of the construction period and
!
▪
end five years from the date of final completion”. The time period is clear where the works reaches final completion
If final completion is not achieved - where the agreement is terminated prior to the achievement of final completion
the termination clauses apply. The final account must be prepared, and on acceptance by the parties, the final
payment certificate must be issued by the principal agent. Final completion will be deemed to have occurred on the
date of acceptance of the final account but no certificate of final completion is issued in terms of the agreement.
!
▪
The five year period applies (contractor default) or no period is applicable (employer default)
The “liability” aspect - The contractor shall make good all defects that appear up to the date of expiry of the LDLP.
Where termination of this agreement occurs before the date of final completion, the LDLP shall end five (5) years from
! the date of termination [29.10] for the completed portion of the works only,
or
!
▪ Where termination of this agreement occurs before the date of final completion on the date of termination where
execution of the works has become impossible due to circumstances beyond the control of either party, or on the date
!
▪
of termination by the contractor due to default by the employer
The liability of the principal and other agents is determined by the terms of their conditions of appointment and not
!
6.2 PRESCRIPTION PERIOD
All defects as defined in terms of the agreement are subject to a prescription period determined by law. In South Africa this
period is three (3) years. The prescription period commences from the date on which the employer (principal agent)
!
becomes aware of a defect and notifies the contractor forthwith
The LDLP is not extended by the prescription period – but the obligation on the contractor to remedy an identified and
!!
notified defect only remains – and this may extend beyond the five (5) year LDLP
!!
!!
!!
!!
!!
!!
!
!
!
!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
DATE
-‐
Tender
award
90C-day DLP
LATENT DEFECTS LIABILITY PERIOD
5 year LDLP
In
common
law
DATE
prescrip6on
-‐
e-‐xpiry
runs
for
PRESCRIPTION
three
years
from
the
date
that
a
defect
was
noted
and
reported
to
the
contractor
32
!
PAYMENT
!
!
INTRODUCTION
All JBCC® agreements follow the same payment procedures that must be applied strictly to minimise disagreements later.
“Payment” is probably the most ‘sensitive’ aspect of the agreement and therefore no “short cuts” should be taken in
certifying amounts due to the contractor or a subcontractor, and occasionally due to the employer! The procedures and
time bars applying to valuation and certification as well as to payment must be applied by the principal agent and be
!!
observed by the parties
!
The following contract data clauses have a direct bearing on the preparation for valuation, certification and payment:-
Pre-Tender Information
▪ Employer details
▪ Principal Agent details (Only the principal agent is authorised to certify payment)
▪ Works description
▪ Law of the agreement
▪ Criteria for practical completion
▪ Site description
▪ Payment (or not!) for materials and goods (unfixed on site, off site or in transit)
▪ Completion - per section or the works as a whole
▪ Penalty - per section or the works as a whole
▪ Contract Price Adjustments – method used
!
▪ Changes, if any, to the provisions of the JBCC® agreement
!
▪ The security option selected in terms of the tender
!
7.2 THE INTERIM PAYMENT CYCLE (See diagram opposite)
!
Setting the Cycle
▪ The principal agent records the date of issue of the interim payment certificate in the contract data
▪ The contractor and subcontractors must cooperate with the principal agent to submit payment claims in terms of the
defined payment cycle
▪ The employer must pay the contractor within fourteen (14) calendar days of the date of issue of a payment
certificate
▪ The contractor must pay each subcontractor within twenty one (21) calendar days of the date of issue of a payment
certificate
▪ The contractor must pay the employer within twenty one (21) calendar days of the date of issue of a payment
! certificate
!
Valuation and certification
The principal agent shall issue a payment certificate by the defined date [CD] in the agreed payment cycle - based on the
valuation of completed work provided by the contractor or, where not provided, assessed by the principal agent (and/or
!
the quantity surveyor where appointed)
The principal agent shall issue a payment certificate in every payment cycle comprising a fair estimate of work executed
and of materials and goods to the contractor with a copy to the employer, and
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
Interim
payment
33
cycle
applicable
to
all
JBCC
Building
Agreements
Contract
Data
Contract
Data
Contract
Data
Issue
cer.ficate E
pays
C C
pays
SC's
The default value of the security is set at the maximum guaranteed sum not to exceed ten per cent (10%) of the
contract sum
▪ The security reduces to not more than six per cent (6%) once 50%+ of the contract sum has been certified
▪ After practical completion the value reduces to not more than four per cent (4%) of the contract sum
▪ After final completion the value reduces to not more than two per cent (2%) of the contract sum
▪ The security expires on payment of the amount due to the contractor in the final payment certificate. Where
! payment is due to the employer the security expires on settlement of such amount
!
8.2
▪
GUARANTEE for CONSTRUCTION (FIXED and PAYMENT REDUCTION)
The default value of the security is set at the maximum guaranteed sum not to exceed five per cent (5%) of the
contract sum.
▪ The value of the works to be certified that does not exceed the contract sum is adjusted to 95% of such value up to
practical completion
▪ Where the value of the works increases during construction the 95% limit of the contract sum will be achieved prior to
practical completion
▪ The contract value of the works that exceeds the contract sum plus any CPAP adjustments is certified in full
▪ On achievement of practical completion the fixed portion of the security expires
▪ On achievement of practical completion the value of the works to be certified is adjusted to 97,5%
▪
!
100% of the contract value is certified in the final payment certificate
Note: The payment reduction has two possible negative impacts. These are:
* No interest is payable on the reduction
! * A negative cash flow results where payment to n/s subcontractors is certified in full
!
8.3
▪
VARIABLE CONSTRUCTION GUARANTEE (MINOR WORKS AGREEMENT)
As 8.1 but the security is set at the maximum guaranteed sum not to exceed six per cent (6%) of the contract sum. No
reduction of value occurs before practical completion
▪ When practical completion is achieved the value reduces to not more than four per cent (4%) of the contract sum
!
▪ When final completion is achieved the value reduces to not more than two per cent (2%) of the contract sum
Note: (Applicable to 8.1, 8.2 and 8.3) The security has an expiry date. This must be specified in the tender documents.
Such expiry date should be set at least six months after the anticipated date for practical completion. Where the
contract is likely to continue beyond this date the employer may instruct the contractor to have such period
extended by the guarantor – who may choose to reissue such a security for the balance of the works only
Note: (Applicable to 8.1, 8.2 and 8.3) Where the contract value exceeds the contract sum by more than 10% such
!
8.4
▪
RETENTION – MINOR WORKS AGREEMENT
Retention, as a payment reduction of the value of the completed works to be certified is set at eight per cent (8%) to a
maximum of four per cent (4%) of such value to practical completion – the four per cent (4%) limit will be reached long
before practical completion
▪ The retention reduces to two per cent (2%) after practical completion
▪
!
No retention is deducted in the final payment certificate
Note Where an amount certified in a payment certificate is in favour of the employer [0.0] the retention [0.0] is increased
by that amount
* No interest is paid on the retention held by the employer
! * The contractor must appreciate that the retention is “at risk” in the hands of the employer
!
8.5
▪
PUBLIC SECTOR
Guarantee for construction (fixed) – similar to the private sector; the five (5) per cent cash deposit is dealt with as
above
!!
▪ Guarantee for Construction (variable) – similar to the private sector
!!
!!
!!
!!
!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
35
!
COMPARISON OF GUARANTEE FORM - CLAUSES
Documents required PA: Interim Pay Certificate PA: Interim Pay Certificate PA>E+C: Recovery Stmnt, Interim Pay Cert, Final Pay Cert
PA: Final Pay Certificate PA: Recovery Statement PA>E+C: Prac Completion / Final Completion Certificate
C: Payment Advice C>SC: Interim Pay Advice, PA: Final Pay Advice
C: Final Pay Advice PA>SC+C: Interim + Final Pay Notification
Intended completion date Intended completion date
Expiry date + 6 months + 6 months Intended completion + 6 months
Guaranteed aggregate sum yes yes (multiple ‘products’) yes 5% fxd expires @ Prac Compl
Recoupment 1.1 ‘Start’ month Then 6% until Prac Compl 5% retention until Prac Compl
Guarantor obligations 1.1 Guarantor obligations 2.1 Guarantor obligations 3.1 Guarantor obligations
Beneficiary procedures 1.2 Payment of money only 2.2 Payment of money only 3.2 Payment of money only
6.0 G pay < 7cD of receipt of 6.0 G pay < 7cD of receipt of
1st written demand 1st written demand 8.0 G pay <7cD of 1
Physical addresses 8.0 G physical address 8.0 G physical address 10.0 G physical address
Security ‘not negotiable’, ‘not 9.0 SfAP not negotiable or 9.0 SfAP not negotiable or 11.0 CG not negotiable or transferable, expire on date, or full
transferable’, transferable, expire on date or transferable, expire on date or pay’t of CG amount
return original on expiry full pay’t / return original form full pay’t / return original form
Liquid document 10.0 SfP = liquid document 10.0 SfAP = liquid document 12.0 SfC = liquid document
!
The guarantor’s liability reduces pro rata; Guaranteed amount = 0 at final completion
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
36
®
Waiver of the Contractor's Lien for use with the …
Principal Building Agreement Edition used ? Ed 6.1 March 2014
Minor Works Agreement Edition used ?
AGREEMENT
The contractor waives in favour of the employer any lien or right of retention that is or
may be held in respect of the works to be executed on the site
This waiver shall only come into effect on provision by the employer of a security for
payment in fulfilment of obligations in terms of the identified agreement
For use with the JBCC® Principal Building Agreement state edition /date
GUARANTOR
DETAILS
Guarantor:
Physical address:
Employer:
Contractor:
Principal Agent:
Works:
Site:
AGREEMENT
DETAILS
Sections Total
number
/
not
applicable Last
section
Principal
Agent
issues 'JBCC® format Interim Payment Certificates, the Final Payment Certificate, the Certificate of Practical Completion and
the
Certificate
of
Final
Completion
1.1 Where a Guarantee for Construction (Variable) in terms of the Agreement has been selected this clause 1.0 and 3.0 to 13.0 shall apply.
The
Guarantor’s
liability
shall
be
limited
to
the
diminishing
amounts
of
the
Guaranteed
Sum
as
follows:-‐
1.1.1 Maximum Guaranteed Sum (not exceeding 10.0% of the contract From and including the date of issue of this Guarantee for Construction
sum)
in
the
amount
of: and up to and including the date of issue of the interim payment
certificate
certifying
in
excess
of
50%
of
the
contract
sum
1.1.2
Reducing to the Guaranteed Sum (not exceeding 6.0 % of the From and including the day after the date of the aforesaid interim
contract
sum)
in
the
amount
of: payment certificate and up to and including the date of issue of the only
Certificate of Practical Completion or last Certificate of Practical
Completion
where
there
are
sections
1.1.3 Reducing to the Guaranteed Sum (not exceeding 4.0% of the From and including the day after the date of the applicable Certificate of
contract
sum)
in
the
amount
of: Practical Completion and up to and including the date of issue of the only
Certificate of Final Completion or the last Certifcate of Final Completion
where
there
are
sections
38
1.1.4 Reducing to the Guaranteed Sum (not exceeding 2.0% of the From and including the day after the date of the applicable Certificate of
contract
sum)
in
the
amount
of: Final Completion and up to and including the date of issue of the Final
Payment Certificate where payment is due to the Contractor, whereafter
this Guarantee for Construction shall expire. Where the Final Payment
Certificate reflects payment due to the Employer this Guarantee for
Construction
shall
expire
upon
payment
of
the
full
amount
certified
1.2 The Guarantor's liability limits set out in 1.1.1 to 1.1.4 shall apply in respect of any claim received by the Guarantor during the Security validity
Maximum Guaranteed Sum (not exceeding 5,0% of From and including the date of issue of this Guarantee for Construction
the
contract
sum)
in
the
amount
of: and up to and including the date of the only Certificate of Practical
Completion or the last Certificate of Practical Completion where there are
sections,
whereafter
this
Guarantee
for
Construction
shall
expire
3.1 Any reference in this Guarantee for Construction to the Agreement is made for the purpose of convenience and shall not be
construed
as
any
intention
to
create
an
accessory
obligation
or
any
intention
to
create
a
suretyship
3.2 Its obligation under this Guarantee for Construction is restricted to the payment of money
3.3 Reference to a recovery statement or an Interim or Final Payment Certificate, or a Certificate(s) of Practical or Final Completion shall
mean
such
certificate
issued
by
the
Principal
Agent
4.0 Subject to the Guarantor’s maximum liability referred to in clauses 1.0 or 2.0 , the Guarantor hereby undertakes to pay the Employer the sum
certified
upon
receipt
of
the
documents
identified
in
4.1
to
4.3:-‐
4.1 A copy of a first written demand notice issued by the Employer to the Contractor stating that payment of a sum certified by the
Principal Agent in an interim or Final Payment Certificate has not been made in terms of the Agreement and failing such payment
within
seven
(7)
calendar
days,
the
Employer
intends
to
call
upon
the
Guarantor
to
make
payment
in
terms
of
4.2
4.2 Afirst written demand notice issued by the Employer to the Guarantor at the Guarantor’s physical address with a copy to the
Contractor stating that a period of seven (7) calendar days has elapsed since the issue of the first written demand notice in terms of
4.1 and that the sum certified has not been paid to date. The Employer herewith calls up this Guarantee for Construction and
demands
payment
of
the
sum
certified
from
the
Guarantor
4.3 A
copy
of
the
applicable
payment
certificate
which
entitles
the
Employer
to
receive
payment
in
terms
of
the
Agreement
of
the
sum
certified
in
4.0
5.0 Subject to the Guarantor’s maximum liability referred to in 1.0 or 2.0 , the Guarantor undertakes to pay the Employer the Guaranteed Sum or the
full outstanding balance upon receipt of a first written demand notice from the Employer to the Guarantor at the Guarantor's physical address
calling
up
this
Guarantee
for
Construction
stating
that:-‐
5.1 The Agreement has been terminated due to the Contractor's default and that the Security for Construction is called up in terms of
5.0.
The
demand
notice
shall
enclose
a
copy
of
the
notice
of
termination;
or
5.2 A provisional sequestration or liquidation court order has been granted against the Contractor and that the Guarantee for
Construction
is
called
up
in
terms
of
5.0.
The
demand
notice
shall
enclose
a
copy
of
the
court
order
6.0 The aggregate amount of payment to be made by the Guarantor in terms of 4.0 and 5.0 shall not exceed the Guarantor's maximum liability in terms
of
1.0
or
2.0
7.0 Where the Guarantor is a registered insurer and has made payment in terms of 5.0, the Employer shall within one hundred and eighty (180)
calendar days of receipt of payment submit an expense account to the Guarantor showing how all monies received in terms of the Guarantee for
Construction have been expended, or will be expended, and shall refund to the Guarantor any surplus amount. All monies refunded to the
Guarantor in terms of this Guarantee for Construction shall bear interest at the prime overdraft rate of the Employer’s bank compounded monthly
and
calculated
from
the
date
of
payment
by
the
Guarantor
to
the
Employer
until
the
date
of
refund
39
8.0 Payment by the Guarantor in terms of 4.0 or 5.0 shall be made within seven (7) calendar days upon receipt of the first written demand notice to the
Guarantor
9.0 The Employer shall have the absolute right to arrange his affairs with the Contractor in any manner which the Employer deems fit and the Guarantor
shall
not
have
the
right
to
claim
his
release
from
this
Guarantee
for
Construction
on
account
of
any
conduct
alleged
to
be
prejudicial
to
the
10.0 The Guarantor chooses the physical address stated above for all transactions in relation to this security
11.0 This Guarantee for Construction is neither negotiable nor transferable and shall expire in terms of either 1.1.4 or 2.1, or on payment in full of the
Guaranteed Sum or on the Security expiry date, whichever is the earlier, where after no claims will be considered by the Guarantor. The original
Guarantee
for
Construction
form
shall
be
returned
to
the
Guarantor
after
it
has
expired
12.0 This Guarantee for Construction, with the required demand notices in terms of 4.0 or 5.0, shall be regarded as a liquid document for the purpose of
obtaining
a
court
order
13.0 Where this Guarantee for Construction is issued in the Republic of South Africa the Guarantor hereby consents to the jurisdiction of a court in the area
where
the
project
is
located
Witness Witness
For use with the JBCC® NSSA Subcontract Agreement state edition /date
GUARANTOR DETAILS
Guarantor:
Physical address:
Contractor:
Subcontractor:
Principal Agent:
Works:
Site:
AGREEMENT DETAILS
1.1.1 Maximum Guaranteed Sum (not exceeding 10.0% of the From and including the date of issue of this NSSA Guarantee for
subcontract
sum)
in
the
amount
of: Construction and up to and including the date of issue of the interim
payment
advices
certifying
in
excess
of
50%
of
the
contract
sum
1.1.2
Reducing to the Guaranteed Sum (not exceeding 6.0 % of the From and including the day after the date of the aforesaid interim
subcontract
sum)
in
the
amount
of: payment advice and up to and including the date of issue of the only
Certificate of Practical Completion or last Certificate of Practical
Completion
where
there
are
sections
1.1.3 Reducing to the Guaranteed Sum (not exceeding 4.0% of the From and including the day after the date of the applicable Certificate of
subcontract
sum)
in
the
amount
of: Practical Completion and up to and including the date of issue of the only
Certificate of Final Completion or the last Certifcate of Final Completion
where
there
are
sections
41
Amount
in
words:
1.1.4 Reducing to the Guaranteed Sum (not exceeding 2.0% of the From and including the day after the date of the applicable Certificate of
subcontract
sum)
in
the
amount
of: Final Completion and up to and including the date of issue of the Final
Payment Advice where payment is due to the Subcontractor, whereafter
this NSSA Guarantee for Construction shall expire. Where the Final
Payment Certificate reflects payment due to the Contractor this NSSA
Guarantee for Construction shall expire upon payment of the full amount
certified
1.2 The
Guarantor's
liability
limits
set
out
in
1.1.1
to
1.1.4
shall
apply
in
respect
of
any
claim
received
by
the
Guarantor
during
the
Security
validity
period
Maximum Guaranteed Sum (not exceeding 5,0% of From and including the date of issue of this NSSA Guarantee for
the
subcontract
sum)
in
the
amount
of: Construction and up to and including the date of the only Certificate of
Practical Completion or the last Certificate of Practical Completion where
there are sections, whereafter this NSSA Guarantee for Construction shall
expire
3.1 Any reference in this NSSA Guarantee for Construction to the Agreement is made for the purpose of convenience and shall not be
construed
as
any
intention
to
create
an
accessory
obligation
or
any
intention
to
create
a
suretyship
3.2 Its obligation under this NSSA Guarantee for Construction is restricted to the payment of money
3.3 Reference
to
a
recovery
statement
or
a
interim
or
final
Payment
Advice
shall
mean
such
advice
issued
by
the
Contractor
Reference to a recovery statement or an Interim or Final Payment Certificate, or a Certificate(s) of Practical or Final Completion shall
mean
such
certificate
issued
by
the
Principal
Agent
4.0 Subject to the Guarantor’s maximum liability referred to in clauses 1.0 or 2.0, the Guarantor undertakes to pay the Contractor the sum certified on
receipt
of
the
documents
identified
in
4.1
to
4.3:-‐
4.1 A
copy
of
a
first
written
demand
notice
issued
by
the
Contractor
to
the
Subcontractor
stating
that
payment
of
a
sum
certified
by
the
Principal
Agent
in
an
interim
or
Final
Payment
Certificate
has
not
been
made
in
terms
of
the
Agreement
and
failing
such
payment
within
seven
(7)
calendar
days,
the
Contractor
intends
to
call
upon
the
Guarantor
to
make
payment
in
terms
of
4.2
4.2 A first written demand notice issued by the Contractor to the Guarantor at the Guarantor’s physical address with a copy to the
Subcontractor stating that a period of seven (7) calendar days has elapsed since the issue of the first written demand notice in terms
of 4.1 and that the sum certified has not been paid to date. The Contractor herewith calls up this Guarantee for Construction and
demands
payment
of
the
sum
certified
from
the
Guarantor
4.3 A copy of the applicable payment advice which entitles the Contractor to receive payment in terms of the Agreement of the sum certified in 4.0
5.0 Subject to the Guarantor’s maximum liability referred to in 1.0 or 2.0 , the Guarantor undertakes to pay the Contractor the Guaranteed Sum or the
full outstanding balance upon receipt of a first written demand notice from the Contractor to the Guarantor at the Guarantor's physical address
calling
up
this
NSSA
Guarantee
for
Construction
stating
that:-‐
5.1 The Agreement has been terminated due to the Subcontractor's default and that the NSSA Guarantee for Construction is called up in
terms
of
5.0.
The
demand
notice
shall
enclose
a
copy
of
the
notice
of
termination;
or
5.2 A provisional sequestration or liquidation court order has been granted against the Subcontractor and that the NSSA Guarantee for
Construction
is
called
up
in
terms
of
5.0.
The
demand
notice
shall
enclose
a
copy
of
the
court
order
6.0 The aggregate amount of payments to be made by the Guarantor in terms of 4.0 and 5.0 shall not exceed the Guarantor's maximum liability in terms
of
1.0
or
2.0
7.0 Where the Guarantor is a registered insurer the Contractor shall within one hundred and twenty (120) calendar days of receipt of payment submit
an expense account to the Guarantor showing how all monies received in terms of the NSSA Guarantee for Construction have been expended, or
will be expended, and shall refund to the Guarantor any surplus amount. All monies refunded to the Guarantor in terms of this NSSA Guarantee for
Construction shall bear interest at the prime overdraft rate of the Contractor’s bank compounded monthly and calculated from the date payment at
the prime overdraft rate of the Contractor’s bank compounded monthly and calculated from the date of payment by the Guarantor to the
Contractor
until
the
date
of
refund
42
8.0 Payment by the Guarantor in terms of 4.0 or 5.0 shall be made within seven (7) calendar days upon receipt of the first written demand notice to the
Guarantor
9.0 The Contractor shall have the absolute right to arrange his affairs with the Subcontractor in any manner which the Contractor deems fit and the
Guarantor shall not have the right to claim his release from this NSSA Guarantee for Construction on account of any conduct alleged to be prejudicial
to
the
Guarantor
10.0 The Guarantor chooses the physical address stated above for all transactions in connection with this Security
11.0 This NSSA Guarantee for Construction is neither negotiable nor transferable and shall expire in terms of either 1.1.4 or 2.1, or payment in full of the
Guaranteed Sum or on the Security expiry date, whichever is the earlier, whereafter no claims will be considered by the Guarantor. The original
NSSA
Guarantee
for
Construction
form
shall
be
returned
to
the
Guarantor
after
it
has
expired
12.0 This NSSA Guarantee for Construction, with the required demand notices in terms of 4.0 or 5.0, shall be regarded as a liquid document for the
purpose
of
obtaining
a
court
order
13.0 Where this NSSA Guarantee for Payment is issued in the Republic of South Africa the Guarantor hereby consents to the jurisdiction of a court in the
area
where
the
project
is
located
Witness Witness
For use with the JBCC® Minor Works Agreement state edition /date
GUARANTOR DETAILS
Guarantor:
Physical address:
Employer:
Contractor:
Principal Agent:
Works:
Site:
AGREEMENT
DETAILS
Agent
issues JBCC® format Payment Certificates, Final Payment Certificate, Certificate of Practical Completion and
Certificate
of
Final
Completion
1.0 The Guarantor’s liability shall be limited to the diminishing amounts of the Guaranteed Sum as follows:
1.1.2
Reducing to the Guaranteed Sum (not exceeding 4.0% of the From and including the day after the date of the Certificate of
contract
sum)
in
the
amount
of: Practical Completion and up to and including the date of the
Certificate
of
Final
Completion
1.1.3 Reducing to the Guaranteed Sum (not exceeding 2.0% of the From and including the day after the date of the Certificate of
contract
sum)
in
the
amount
of: Final Completion and up to and including the date of issue of the
Final Payment Certificate where payment is due to the
Contractor, whereupon this MWA Guarantee for Construction
shall expire. Where the Final Payment Certificate reflects
payment due to the Employer, this MWA Guarantee for
Construction
shall
expire
on
payment
of
the
full
amount
certified
2.0 The Guarantor's liability limits set out in clauses 1.1 to 1.3 shall apply in respect of any claim received by the Guarantor during the security
validity
period
3.1 Any reference in this MWA Guarantee to the Agreement is made for the purpose of convenience and shall not be construed
as
any
intention
whatsoever
to
create
an
accessory
obligation
or
any
intention
whatsoever
to
create
a
suretyship
3.2 Its obligation under this Security is restricted to the payment of money
3.3 Reference to a Certificate of Practical Completion or to a Certificate of Final Completion shall mean such certificate as issued
by
the
Agent
4.0 Subject to the Guarantor’s maximum liability referred to in 1.0, the Guarantor hereby undertakes to pay the Employer the sum certified
upon
receipt
of
the
documents
identified
in
4.1
to
4.3:
4.1 A copy of a first written demand notice issued by the Employer to the Contractor stating that payment of a sum certified by
the Principal Agent has not been made in terms of the Agreement and failing such payment within seven (7) calendar days,
the
Employer
intends
to
call
upon
the
Guarantor
to
make
payment
in
terms
of
4.2
4.2 A first written demand notice issued by the Employer to the Guarantor at the Guarantor’s physical address with a copy to the
Contractor stating that a period of seven (7) calendar days has elapsed since the date of issue of the first written demand
notice in terms of 4.1 and that the sum certified has still not been paid to date. The Employer herewith calls up this MWA
Guarantee
for
Construction
and
demands
payment
of
the
sum
certified
from
the
Guarantor
4.3 A copy of the applicable payment certificate which entitles the Employer to receive payment in terms of the Agreement of the sum certified
5.0 Subject to the Guarantor’s maximum liability referred to in 1.0, the Guarantor undertakes to pay the Employer the Guaranteed Sum or the
full outstanding balance upon receipt of a first written demand from the Employer to the Guarantor at the Guarantor's physical address
calling
up
this
MWA
Guarantee
for
Construction
stating
that:
5.1 The Agreement has been terminated due to the Contractor's default and that the MWA Guarantee for Construction is called
up in terms of 5.0. The demand notice shall enclose a copy of the notice of termination; or called up in terms of 5.0. The
demand
notice
shall
enclose
a
copy
of
the
notice
of
termination;
or
5.2 A provisional sequestration or liquidation court order has been granted against the Contractor and that the MWA Guarantee
for
Construction
is
called
up
in
terms
of
5.0.
The
demand
notice
shall
enclose
a
copy
of
the
court
order
6.0 It is recorded that the aggregate amount of payments required to be made by the Guarantor in terms of 4.0 and 5.0 shall not exceed the
Guarantor's
maximum
liability
in
terms
of
1.0
7.0 Where the Guarantor is a registered insurer and has made payment in terms of 5.0, the Employer shall within one hundred and twenty (120)
calendar days of receipt of payment submit an expense account to the Guarantor showing how all monies received in terms of this MWA
Guarantee for Construction have been expended or will be expended, and shall refund to the Guarantor any resulting surplus. All monies
refunded
to
the
Guarantor
in
terms
of
this
MWA
Guarantee
for
Construction
shall
bear
interest
at
the
prime
overdraft
rate
of
the
Employer’s
bank compounded monthly and calculated from the date payment at the prime overdraft rate of the Employer’s bank compounded monthly
and
calculated
from
the
date
of
payment
by
the
Guarantor
to
the
Employer
until
the
date
of
refund
8.0 Payment by the Guarantor in terms of 4.0 or 5.0 shall be made within seven (7) calendar days upon receipt of the first written demand
notice
to
the
Guarantor
9.0 The Employer shall have the absolute right to arrange his affairs with the Contractor in any manner which the Employer deems fit and the
Guarantor shall not have the right to claim his release from this MWA Guarantee for Construction on account of any conduct alleged to be
prejudicial
to
the
Guarantor
10.0 The Guarantor chooses the physical address as stated above for all purposes in connection herewith
11.0 This MWA Guarantee for Construction is neither negotiable nor transferable and shall expire in terms of either 1.3, or payment in full of the
Guaranteed Sum or on the Guarantee expiry date, whichever is the earlier, where after no claims will be considered by the Guarantor. The
original
of
this
MWA
Guarantee
for
Construction
form
shall
be
returned
to
the
Guarantor
after
it
has
expired
12.0 This MWA Guarantee for Construction, with the required demand notices in terms of 4.0 or 5.0, shall be regarded as a liquid document for
the
purpose
of
obtaining
a
court
order
13.0 Where this MWA Guarantee for Construction is issued in the Republic of South Africa the Guarantor hereby consents to the jurisdiction of a
court
in
the
area
where
the
project
is
located
Witness Witness
For use with the JBCC® Principal Building Agreement state edition /date
Guarantor:
Physical address:
Employer:
Contractor:
Principal Agent:
Works:
Site:
AGREEMENT
DETAILS
Principal
Agent
issues JBCC®
format
Interim
Payment
Certificates
and
a
Final
Payment
Certificate
1.1 Any reference in this Guarantee for Payment to the Agreement is made for the purpose of convenience and shall not be construed
as
any
intention
to
create
an
accessory
obligation
or
any
intention
to
create
a
suretyship
1.2 Its obligation under this Guarantee for Payment is restricted to the payment of money
1.3 Reference to a Certificate of Practical Completion or to a Certificate of Final Completion shall mean such certificate issued by the
Principal
Agent
2.0 Subject to the Guarantor’s maximum liability in terms of the Guaranteed Sum, the Guarantor undertakes to pay the Contractor the sum
certified
upon
receipt
of
the
documents
identified
in
2.1
to
2.3:-‐
2.1 A copy of a first written demand notice issued by the Contractor to the Employer stating that payment of a sum certified by the
Principal Agent has not been made in terms of the Agreement and failing such payment within seven (7) calendar days, the
Contractor
intends
to
call
upon
the
Guarantor
to
make
payment
in
terms
of
2.2
2.2 A first written demand notice issued by the Contractor to the Guarantor at the Guarantor's physical address with a copy to the
Employer stating that a period of seven (7) calendar days has elapsed since the date of issue of the first written demand notice in
terms of 2.1 and that the sum certified has not been paid to date. The Contractor herewith calls up this Guarantee for Payment and
demands
payment
of
the
sum
certified
from
the
Guarantor
2.3 A
copy
of
the
payment
certificate
which
entitles
the
Contractor
to
receive
payment
in
terms
of
the
Agreement
of
the
sum
certified
in
2.0
3.0 Subject
to
the
Guarantor’s
maximum
liability
in
terms
of
the
Guaranteed
Sum,
the
Guarantor
hereby
undertakes
to
pay
the
Contractor
the
demanded
sum
upon
the
receipt
of
the
documents
identified
in
3.1
and
3.2:-‐
46
3.1 A copy of a first written demand notice issued by the Contractor to the Employer stating that the Contractor demands the issue of a
payment certificate and failing such issue within seven (7) calendar days, the Contractor intends to call upon the Guarantor to make
payment
in
terms
of
3.2
of
the
demanded
sum
as
set
out
in
the
demand
3.2 A first written demand notice issued by the Contractor to the Guarantor at the Guarantor's physical address with a copy to the
Employer stating that a period of seven (7) calendar days has elapsed since the issue of a first written demand notice in terms of 3.1
and that a payment certificate has still not been issued. The Contractor herewith calls up this Guarantee for Payment and demands
payment
of
the
demanded
sum
from
the
Guarantor
4.0 The aggregate amount of payments to be made by the Guarantor in terms of 2.0 and 3.0 shall not exceed the Guaranteed Sum
5.0 Where the Guarantor is a registered insurer and has made payment in terms of 3.0, the Contractor shall within one hundred and eighty
(180) calendar days of receipt of payment submit an expense account to the Guarantor showing how all monies received in terms of the
Guarantee for Payment have been expended, or will be expended, and shall refund to the Guarantor any surplus amount. All monies
refunded to the Guarantor in terms of this Guarantee for Payment shall bear interest at the prime overdraft rate of the Contractor’s bank
compounded
monthly
and
calculated
from
the
date
of
payment
by
the
Guarantor
to
the
Contractor
until
the
date
of
refund
6.0 The Guarantor shall make payment in terms of 2.0 or 3.0 within seven (7) calendar days of receipt of the first written demand notice to the
Guarantor
7.0 The Contractor shall have the absolute right to arrange his affairs with the Employer in any manner which he deems fit and the Guarantor
shall
not
have
the
right
to
claim
his
release
on
account
of
any
conduct
alleged
to
be
prejudicial
to
the
Guarantor
8.0 The Guarantor chooses the physical address stated above for all transactions in connection with this Security
9.0 This Guarantee for Payment is neither negotiable nor transferable and shall expire upon payment of the final payment certificate in terms
of the Agreement or on payment in full of the Guaranteed Sum or on the Security expiry date, whichever is the earlier, whereafter no
claims
will
be
considered
by
the
Guarantor.
The
original
Guarantee
for
Payment
form
shall
be
returned
to
the
Guarantor
after
it
has
expired
10.0 This Guarantee for Payment, with the required demand notices in terms of 2.0 or 3.0, shall be regarded as a liquid document for the
purpose
of
obtaining
a
court
order
11.0 Where this Guarantee for Payment is issued in the Republic of South Africa the Guarantor hereby consents to the jurisdiction of a court in
the
area
where
the
project
is
located
Witness Witness
For use with the JBCC® NSSA Subcontract Agreement state edition /date
GUARANTOR DETAILS
Guarantor:
Physical address:
Employer:
Contractor:
Subcontractor:
Principal Agent:
N/S Works:
Site:
AGREEMENT
DETAILS
Contractor
issues JBCC®
format
Payment
Advice
and
a
Final
Payment
Advice
1.1 Any reference in this NSSA Guarantee for Payment to the Agreement is made for the purpose of convenience and shall not be
construed
as
any
intention
to
create
an
accessory
obligation
or
any
intention
to
create
a
suretyship
1.2 Its obligation under this NSSA Guarantee for Payment is restricted to the payment of money
1.3 Reference to a Payment Advice or a final Payment Advice shall mean such advice issued by the Contractor
2.0 Subject to the Guarantor’s maximum liability in terms of the Guaranteed Sum, the Guarantor undertakes to pay the Subcontractor the sum
certified
upon
receipt
of
the
documents
identified
in
2.1
to
2.3:-‐
2.1 A copy of a first written demand notice issued by the Subcontractor to the Contractor stating that payment of a sum certified in the
payment
advice
statement
has
not
been
made
in
terms
of
the
Agreement
and
that:-‐
2.1.1 The Contractor has failed to notify the Subcontractor of payment default by the Employer and has failed to make payment to
the
Subcontractor
within
seven
(7)
calendar
days
after
due
date
for
payment
to
the
Contractor
by
the
Employer;
or
2.1.2 The Contractor has received timeous payment from the Employer and has failed to make payment to the Subcontractor
within
seven
(7)
calendar
days
after
due
date
for
payment
to
the
Contractor
by
the
Employer;
or
2.1.3 The Contractor has received late payment from the Employer and has failed to make payment to the Subcontractor within
seven
(7)
calendar
days
of
the
Contractor
receiving
payment
from
the
Employer;
or
2.1.4 The Contractor has failed to pay to the Subcontractor within thirty (30) calendar days after the due date for payment to the
Contractor by the Employer and failing payment of the sum certified by the Contractor in the payment advice statement
within
seven
(7)
calendar
days,
the
Subcontractor
intends
to
call
upon
the
Guarantor
to
make
payment
in
terms
of
2.2
48
2.2 A first written demand notice issued by the Subcontractor to the Guarantor at the Guarantor's physical address with a copy to the
Contractor stating that a period of seven (7) calendar days has elapsed since date of issue of the the first written demand notice in
terms of 2.1 and that the sum certified has not been paid to date. The Subcontractor herewith calls up this NSSA Guarantee for
Payment
and
demands
payment
of
the
sum
certified
from
the
Guarantor
2.3 A copy of the payment advice statement issued by the Contractor and which entitles the Subcontractor to receive payment of the
sum
certified
in
2.0
3.0 Subject to the Guarantor’s maximum liability in terms of the Guaranteed Sum, the Guarantor hereby undertakes to pay the Subcontractor
the
demanded
sum
upon
the
receipt
of
the
documents
identified
in
3.1
and
3.2:-‐
3.1 A copy of a first written demand notice issued by the Subcontractor to the Contractor stating that the Subcontractor demands the
issue of a payment advice statement and failing such issue within seven (7) calendar days, the Subcontractor intends to call upon the
Guarantor
to
make
payment
in
terms
of
3.2
of
the
sum
as
set
out
in
the
demand
3.2 A written demand notice issued by the Subcontractor to the Guarantor at the Guarantor's physical address with a copy to the
Contractor stating that a period of seven (7) calendar days has elapsed since the issue of a first written demand notice in terms of
3.1 and that a payment advice statement has not been issued. The Subcontractor herewith calls up this NSSA Guarantee for Payment
and
demands
payment
of
the
sum
as
set
out
in
the
demand
from
the
Guarantor
4.0 The aggregate amount of payments to be made by the Guarantor in terms of 2.0 and 3.0 shall not exceed the Guaranteed Sum
5.0 Where the Guarantor is a registered insurer the Subcontractor shall within one hundred and twenty (120) calendar days of receipt of
payment submit an expense account to the Guarantor showing how all monies received in terms of the NSSA Guarantee for Payment have
been expended, or will be expended, and shall refund to the Guarantor any surplus amount. All monies refunded to the Guarantor in terms
of this NSSA Guarantee for Payment shall bear interest at the prime overdraft rate of the Subcontractor’s bank compounded monthly and
calculated
from
the
date
of
payment
by
the
Guarantor
to
the
Subcontractor
until
the
date
of
refund
6.0 Payment by the Guarantor in terms of 2.0 or 3.0 shall be made within seven (7) calendar days upon receipt of the first written demand
notice
to
the
Guarantor
7.0 The Subcontractor shall have the absolute right to arrange his affairs with the Contractor in any manner which he deems fit and the
Guarantor
shall
not
have
the
right
to
claim
his
release
on
account
of
any
conduct
alleged
to
be
prejudicial
to
the
Guarantor
8.0 The Guarantor chooses the physical address stated above for all transactions in connection with this Security
9.0 This NSSA Guarantee for Payment is neither negotiable nor transferable and shall expire upon payment of the final payment advice in terms
of the Agreement or on payment in full of the Guaranteed Sum or on the Security expiry date, whichever is the earlier, whereafter no claims
will
be
considered
by
the
Guarantor.
The
original
NSSA
Guarantee
for
Payment
form
shall
be
returned
to
the
Guarantor
after
it
has
expired
10.0 This NSSA Guarantee for Payment, with the required demand notices in terms of 2.0 or 3.0, shall be regarded as a liquid document for the
purpose
of
obtaining
a
court
order
11.0 Where this NSSA Guarantee for Payment is issued in the Republic of South Africa the Guarantor hereby consents to the jurisdiction of a
court
in
the
area
where
the
project
is
located
Witness Witness
!9.0 CONTRACTUAL CLAIMS – also applicable to insurance and security clauses, may apply on termination
!
!
9.1 DEFINITION
Claim – a formal request for compensation by either contracting party, evaluated by the principal agent
!
(provided notice of a potential claim is given and the substantiated claim is submitted within the prescribed periods)
Dispute - an unresolved disagreement between the contacting parties (or a claim) involving an independent entity to guide
!
the process or to adjudicate such claim – not the principal agent!
!
9.2 PROCESS – (SUB)CONTRACTOR
Give notice of a potential (time) claim P6.0 Cl 23.1-3; Cl 23.4.2= 20 W-days; N6.0 Cl 23.1-3; Cl 23.4.2= 20 W-days
Give notice of a potential (money) claim P6.0 Cl 26.1-4; Cl 26.5= 20 W-days; N6.0 Cl 26.1-4; Cl 26.5= 20 W-days
The (sub)contractor gives notice to the employer (contractor) and/or the principal agent to inter alia consider the event /
!
evaluate design and execution options etc to complete the project within the construction period and budget
contractor submits a substantiated (time) claim P6.0 Cl 23.1-3; 23.4.2= Cl 23.5= 40 W-days M5.0 Cl 17.1-3
subcontractor submits a substantiated (time) claim N6.0 Cl 23.1-3; 23.4.2= Cl 23.5= 20 W-days
contractor submits a substantiated (money) claim P6.0 Cl 26.1-4; 26.5= Cl 26.6= 40 W-days M5.0 Cl 20.4-5
!
subcontractor submits a substantiated (money) claim N6.0 Cl 26.1-4; 26.5= Cl 26.6= 15 W-days
The contractor motivates the claim using site records, if applicable – stating briefly:-
▪ The ‘problem’ (refer to “records”)
▪ The root cause – identify events / entities responsible for act / omission
▪ Single / multiple events > identify dominant cause (isolate + quantify the effect of each cause)
▪ Separate events due to the (sub)contractor’s inefficiency from employer obligations
▪ The effect - on the (revised) date for practical completion … events that impact directly on scheduled completion
date
▪ The effect - adjustment of the contract value
▪ Options explored – preventative measures
▪ Effect on (original) critical path on revised programme
!
▪ Other consequences
!
Note: Where the employer occupies the works before practical completion some of the criteria listed may apply
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
50
!
!
9.3
▪
PROCESS – PRINCIPAL AGENT
PA may request additional information where the submission is not clear / ask for a quotation
▪ PA (Cl 23.0 and 26.0) must grant in full, reduce or refuse a claim and determine the revised date for practical
completion and adjust the contract value with reasons using essentially the same headings …
!
▪
▪
No decision by the PA within specified time period, the contractor may give notice of a disagreement (Cl 30.1)
Note: The construction period in an existing agreement can not be shortened by issuing a contract
instruction – this implies ‘acceleration’ with the associated reprogramming, reallocating resources etc –
for which the contractor must be compensated
▪ Note: Reprogramming the works as a result of contract instructions may not necessarily lengthen the
! construction period but may require other / additional resources attracting additional costs
▪
!
The PA may certify partial payment for a claim in an interim payment certificate for resolved items
The PA may create a ‘final account‘ for the event – and pay such amount in full, in an interim payment certificate
!!
!
….. work as a team!
!
9.4 PRELIMINARIES
Where a project is divided into sections for completion at different times before the date for practical completion for
the works as a whole the parties should agree an allocation of preliminaries per section to facilitate valuation of
payment certificates and calculation of adjustments to the contract value later
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
51
!
10.2
drawings and photographs
BACKGROUND
The concept has been hidden away in previous editions of JBBC® agreements under the interpretation heading
of duties to be carried out in writing. In practice it is an essential administration tool where status of an agreement
changes where:
▪ The employer sells a project and another employer takes over to record work done, payments earned and
items not completed
▪ Either party terminates the agreement
▪ Both parties decide to terminate an agreement
!
10.3 PROCESS
The principal agent in cooperation with other agents and the contractor and subcontractors assemble all
information pertaining to the project. The information required is similar to the requirements to submit a claim (§
! 9.0)
! Determine:
▪ The nature of the change of status of the project = termination, sale of the project, or other reason(s)
▪ The effective date when the status of the project changed
▪ Immediate actions – stop work but make the site safe in terms of the Health and Safety requirements, and /
!! ▪ or suspend work until the status of the work can be assessed and quantified to produce the final account
!
Assess progress:-
! ▪ Omissions
▪ Compare interim payments up to the date of the status report with draft final account
▪ Identify expense and/or loss the contractor may have incurred
▪ Options explored – preventative measures … additional security or safety requirements
Additional information:
Mark up drawings to highlight completed work / defective work / work that may be late in terms of the programme
!!
Provide photographs (with a date) of virtually everything – may be needed later if disagreements arise
!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
52
!
11.0 INTEREST CALCULATIONS (compensatory and default interest)
!
11.1 PRACTICAL COMPLETION
▪ **Compensatory interest only applies to payment certificates issued 31 calendar days after practical
completion in the PBA only!
!
11.2.
▪ Default interest applies to late payment of any payment certificate - applicable to the PBA, NSSA and MWA
FINAL COMPLETION
!
11.3
▪ At least 3 interim payment certificates must be issued before the issue of the final payment certificate
PAYMENT CERTIFICATE 11
▪ The first payment certificate after practical completion (say 15 calendar days) attracts no compensatory
interest
!
11.4
▪ The employer makes payment of the certified amount
PAYMENT CERTIFICATE 12
▪ Compensatory interest over 15+30 = 45 calendar days included in payment certificate shown in the
recovery statement
!
11.5
▪ The employer makes payment of the certified amount
PAYMENT CERTIFICATE 13
▪ Compensatory interest for 75 calendar days included
▪ The employer pays certificate number 13 twenty one (21) calendar days after issue date. The first fourteen
(14) calendar days is the employer’s “payment window”. The further seven (7) calendar days attracts
default interest
▪ Should the employer pay the certified amount + the default interest i.e. the “debt due” no further default
interest applies
▪ Should the employer pay only the certified amount further default interest of 2 calendar days would apply to
the
“unpaid balance” and must be included in the next recovery statement
▪ With the employer’s concurrence, the default interest on the “unpaid balance” should be calculated up to the
!
11.6
next expected payment date viz 9+7 = 16 calendar days thereby extinguishing the default
PAYMENT CERTIFICATE 14
▪ The employer meets payment requirements without 11.5 inclusion
!
11.7
▪ Should 9.5 not have been applied the “unpaid balance” default interest as per 11.5 would again apply
PAYMENT CERTIFICATE 15
▪ Should final completion and acceptance of the final account not be achieved in ninety (90) calendar days
further interim payment certificates must be issued to maintain the “payment cycle”
▪ The final payment certificate also attracts compensatory interest (PBA only). Should the final payment
!
11.8
certificate be paid late default interest is due and is recoverable by the contractor as a debt
!
11.9
Calculation: 20 000 x 5.5% x 45 / 365
Assumptions:
• Interest rate (Repo + 6.0%) = 5.5% + 6.0% (see interest definition)
• Certificate No 3 payment due = 91 200.00
• Payment made after Certificate issue date = 21 calendar days
• Employer (21-14) calendar day default pay period = 7 calendar days (see 11.5.2 above)
• Balance of payment cycle = 9 calendar days
• Next Employer payment (expected) = 14 calendar days
Calculation: 91 200 x 11.5% x 7 / 365 = 201.14
* Assuming the employer makes payment of the certificate amount only:
Add: 201.14 x 11.5% x 9 / 365 = 0.57 (see 11.5.4 above)
Total default interest due at end of payment cycle = 201.71
* Additional interest to expected employer payment date
Add: 201.71 x 11.5% x 14 / 365 = 1.02 (see 11.5.5 above)
!
11.10 COMPENSATORY AND DEFAULT INTEREST – ASSUMPTIONS
!
** Compensatory interest only applies in the JBCC® Principal Building Agreement
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
DATE
-‐
comple6on
PRACTICAL
Compensatory
and
default
53
interest
calcula-ons
applicable
to
JBCC
Building
Agreements
Pay
within
C11
14
C
days if
paid
late
=
Def
interest
Pay
within
C12 14
C
days if
paid
late
=
Def
interest
ONLY
applicable
to
PBA
compensatory
interest Pay
within
C13 14
C
days if
paid
late
=
30+15
=
45
C
days
Def
interest
ONLY
applicable
to
PBA
compensatory
interest Pay
within
C14 14
C
days
30+30+15
=
75
C
days if
paid
late
=
Def
interest
54
!
12.0 RECOVERY STATEMENT (PBA)
!
!
12.1 PURPOSE
The recovery statement deals with financial transactions between the employer and the contractor that do not affect the
contract value and are therefore not part of the valuation of work in progress or the final account. Such transactions can
occur at any time during the construction period. The amounts due to either party are determined by the principal agent
on a monthly basis, and are included in the payment certificate issued at that time. Documentation substantiating the
amounts due must accompany the recovery statement. By dealing with these transactions as they occur and not at the end
!
of the contract considerable administrative frustration is avoided
!
12.2
Column A
THE STATEMENT
!
Column B
All amounts as determined by the principal agent are accounted for on an accumulative basis
!
Column C
Previously determined accumulative amounts are accounted for
! payment certificate
!
12.3 AMOUNTS DUE TO THE EMPLOYER
There are ten conditions not related to the contract value that the employer may recover from the contractor. These are:
▪ The first seven (1.1.1-7) are grouped together as they impact on the tax on the certified contract value
▪ Penalties due (1.2) are accounted for before tax but are separated for clarity purposes
▪ Default interest (1.3.1) is tax neutral and is accounted for after tax
!
12.4 AMOUNTS DUE TO THE CONTRACTOR
There are only four conditions that the contractor may recover from the employer. These are:
▪ Compensatory (2.1.1) and default interest (2.1.2) amounts, which are both tax neutral, and accounted for after
tax
▪ Advance payment received (2.1.3) is accounted for after tax
!
12.5 IMPORTANT NOTES
!!
See Page 66
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
!!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
55
®
Recovery Statement Certificate No: PA certificate 11
issued in terms of Clause 27.0 of the
Principal Building Agreement Edition 6.1 © March 2014 Date of Certificate: 201?-02-07
Employer
Contractor
Works
Site
The following amounts, detailed in supplementary documentation where required, are recovered in the current Payment Certificate
A B C
TOTAL AMOUNT LESS PREVIOUS RECOVERY
TO BE RECOVERED RECOVERY THIS PERIOD
1.0 AMOUNTS DUE TO THE EMPLOYER
1.1.4 Contractor not paying the employer an amount due [27.2.5 ] 0.00 0.00
An amount of money that is due and payable by the employer to the contractor or vice versa is ‘certified’ in a payment
certificate issued by the principal agent. Liquidity is conferred where the employer (the debtor), by the signature of the
principal agent, acknowledges his indebtedness to the contractor for a determined sum of money. The wording must be
correct – specifying the employer, principal agent and the contractor and the payment amount that is due to the
contractor. Payment due to the employer is provided for in the agreement and the payment certificate form but is not a
!
liquid document!
!
13.2 THE PAYMENT CERTIFICATE
!
Column A Contract Sum The contract sum i.t.o. the agreement remains fixed for the duration of the contract
Column B Current Contract Value The totals of Columns A and B give an immediate comparison between the contract
sum and contract value at the time of issue of the payment certificate. The quantity
surveyor, where appointed, determines the adjustments to the contract value for
!
Column C Current Valuation
The principal agent certifies the current valuation amounts and items of expense and/or
!
1.0 Value of work executed
loss detailed in the recovery statement as well as tax on the applicable items
The valuation must be “a reasonable estimate of the work executed” without it being
“work satisfactorily completed”. The principal agent must act impartiality to verify (or
Materials and goods on and off site may be included in the valuation
Note: Projects financed by a financial institution generally exclude payment of unfixed
materials leaving the employer short of money to make payment of an issued payment
certificate. The principal agent must record in the contract data if unfixed materials
(on or off site) will be paid, or not, where included in a payment certificate
A Guarantee for Advance Payment may cover some such materials and will reduce the
employer’s additional risk (see Recovery Statement)
Transfer of ownership of materials off site may be difficult to prove in law
!
3.0
4.0
SUB TOTAL
Security adjustment Applies where the contractor has chosen the security (fixed) to which payment
reduction provisions apply, or is in default by not providing such security and the
!
5.0 Net contract sum The amount reflected in Column B is the same as the amount in Column A
!
6.0 Authorised adjustments … Authorised adjustments to date are included [B 6.0], excluding anticipated adjustments
!
7.0 Provision for ‘contract price adjustments’ included in [A 7.0], updated in [B7.0], if included in a valuation [C+D 7.0]
!
8.0 TOTAL AMOUNT CERTIFIED … in [D 8.0]
!
9.0 Less Amount certified in the previous payment certificate … [D 9.0]
!
10.0 NET AMOUNT CERTIFIED The net resultant portion of the contract value certified in this payment certificate
!
11.1-3 Recovery Statement Adjustment of amounts due to/by the contractor that attract tax
!
12.0
13.0
SUB TOTAL
Tax
The summed total of the previous items
The subtotal 12.0 is pre-tax. The tax percentage must be filled in and calculated
!
14.1-6 Recovery Statement Amounts that do not attract tax = interest and advance payment amounts (loans)
!
15.0 TOTAL The total of the contract sum and the comparative variable current contract value
!
16.0
17.0
CERTIFIED AMOUNT DUE FOR PAYMENT Identify the currency / receiving party / amount due
Contract sum execution Where the contractor has provided a Guarantee for Construction (variable) the
percentage of the contract sum that has been executed must be determined.
!!
The completion status must be indicated as it affects all the security options
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
57
®
Certificate for Payment Certificate No: 11
Valuation Date 201?-02-05 Issue Date 201?-02-07 Payment due date 201?-02-21
A B C D
CONTRACT SUM CURRENT CURRENT CURRENT
CONTRACT VALUE VALUATION CERTIFICATION
4.0 Security adjustments applicable [11.3.2; 25.3.4] If applicable, state % 0.0 % 0.00 290 000.00
9.0 Less Previous amount certified [25.3.6] (excluding tax) (120 000.00)
11.1 Less Expense and loss payable to the employer [Recovery Statement 1.1] (excluding tax) 0.00
11.2 Less Penalties levied and payable to the employer [Recovery Statement 1.2] (excluding tax) 0.00
11.3 Add Damages payable to the contractor [Recovery Statement 2.2] (excluding tax) 0.00
12.0 SUB TOTAL 2 500 000.00 2 600 000.00 (excluding tax) 180 000.00
13.0 Add Tax on 11.0 [25.3.8] 14 % 350 000.00 364 000.00 25 200.00
14.1 Less Default interest payable to the employer [Recovery Statement 1.3] (excluding tax) 0.00
14.2 Less Recoupment from contractor of an advance payment [Recovery Statement 1.3.2] (excluding tax) (40 000.00)
14.3 Add Compensatory interest payable to the contractor [Recovery Statement 2.1.1] (excluding tax) 0.00
14.4 Add Default interest payable to the contractor [Recovery Statement 2.1.2] (excluding tax) 648.85
14.5 Add Advance payment made to the contractor [Recovery Statement 2.1.3] (excluding tax) 150 000.00
14.6 Add Tax exempt items (salvaged materials used in the works) [25.3.10] (excluding tax) 0.00
16.0 Currency ZAR CERTIFIED AMOUNT DUE FOR PAYMENT to the Contractor / Employer Contractor 315 848.85
17.0 Contract sum execution (Security for Construction- variable - only) (D8.0/A12.0*100) 12.0 %
Security status
Mark each box as appropriate < 50% ✔ > 50% ✖ Practical Completion ✖ Final Completion ✖
The payment certificate notification informs the n/s subcontractor of a subcontract amount included in the total amount
certified to the contractor (or employer) in the current payment certificate. Any adjustment made to such amount due to
the security provided by the contractor is not applicable to the payment due to the subcontractor. The contractor must
certify the full amount due to the subcontractor and make any adjustment in terms of the security provided by the
!
subcontractor. The NOTE on the payment notification form details this condition
Column A Subcontract Sum The subcontract sum i.t.o the agreement remains fixed for the duration of the
!
Column B Current SC Value
subcontract
The totals of Columns A and B give an immediate comparison between the subcontract
sum and the subcontract value at the date of issue of the payment certificate. The
quantity surveyor, where appointed, determines the adjustments to the subcontract
!
Column C Current Valuation
The principal agent notifies the subcontractor of the current subcontract valuation
amounts certified to the contractor together with any adjustment i.t.o. the security
provided by the contractor, the previous gross subcontract amount certified as well as
!
1.0 Value of work executed
tax on the net subcontract amount certified
The principal agent inserts the value of work included in the current payment
!
2.1-2 Materials on and off site
certificate
The principal agent inserts the value of items included in the current payment
! certificate
!
3.0
4.0
SUB TOTAL
Security adjustment The principal agent notifies the subcontractor of adjustments made to the valuation of
items included in the current payment certificate (if applicable) to comply with the
contractor’s security provision in terms of the principal agreement
!
5.0 Net contract sum The amount reflected in Column B is the same as the amount in Column A
!
6.0 Authorised adjustments … Authorised adjustments to date are included [B 6.0], excluding anticipated adjustments
!
7.0 Provision for ‘contract price adjustments’ included in [A 7.0], updated in [B7.0], if included in a valuation [C+D 7.0]
!
8.0 TOTAL AMOUNT CERTIFIED … in [D 8.0]
!
9.0
10.0
Less Amount certified in the previous payment certificate … [D 9.0]
NET AMOUNT CERTIFIED The amount of the n/s subcontract value that has been certified in the current payment
certificate. This amount may differ in the contractor’s payment advice due to
adjustments the contractor may be entitled to make in terms of the subcontractor’s
!
11.0 Tax
security or the n/s subcontract recovery statement
The subtotal 10.0 is pre-tax. The tax percentage must be filled in and calculated
!
12.1-2 SC Recovery Statement
13.0 TOTAL
Amounts that affect the subcontractor’s income or expenditure, that are tax neutral
The total of the subcontract sum and the comparative variable current subcontract
!
value
!
14.0
15.0
AMOUNT DUE FOR PAYMENT Identify the currency / receiving party / amount due
Subcontract sum execution Where the subcontractor has provided a Guarantee for Construction (variable) the
percentage of the subcontract sum that has been executed must be determined.
The completion status must be indicated as it affects all the security options for the
Note: The principal agent is not responsible for and is not involved in determining any
of the recovery amounts nor for determining whether the security provided by the
!
subcontractor varies the amount due
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
59
®
Subcontractor's Payment Certificate Notification Notification No: 11
issued in terms of Clause 25.4.3 of the
Principal Building Agreement Edition 6.1 © March 2014 Interim or Final interim
Contractor
Subcontractor
N/S Works
Site
Note: The payment certificate identified above has been issued to the contractor that includes an amount due for payment to or by the named subcontractor.
Where applicable, the adjusted amount certified is in terms of the security provided by the contractor. This adjustment may or may not affect the amount certified
to the subcontractor. No account is taken of other amounts that may be due between the parties. The compilation of the certified amount is set out below
4.0 Security Adjustments [14.7.1, 31.8] If applicable, state % 0.0% % 0.00 20 000.00
9.0 Less Previous gross amount certified [25.3.6] (excluding tax) 0.00
10.0 SUB TOTAL 600 000.00 600 000.00 (excluding tax) 20 000.00
12.1 Less Interest / Advance Payment Recoupment [27.1.7] (excluding tax) 0.00
12.2 Add Interest / Advance Payment Made [27.2.4] (excluding tax) 150 000.00
14.0 Currency ZAR AMOUNT DUE FOR PAYMENT to the Subcontractor / Contractor Subcontractor 172 800.00
15.0 N/S Contract Sum execution % (Security for Construction - variable- only) (D8.0/A10.0*100) 3.3 %
The n/s subcontract recovery statement deals with expenses and losses suffered by the contractor or the subcontractor
that do not affect the n/s subcontract value and that are not part of the valuation of the work in progress nor the n/s
subcontract final account. Such expenses and losses can occur at any time during the n/s subcontract construction
period. The amounts as are determined by the contractor on a monthly basis and are included in the interim or the final
!
subcontractor’s payment advice issued at that time
!
Documentation substantiating the amounts due must accompany the n/s subcontract recovery statement
By dealing with such expenses and losses as they occur and not at the end of the contract considerable administrative
!
frustration is avoided and the parties are correctly compensated for such expenses and losses incurred
!
15.2
Column A
THE STATEMENT
!
Column B
All amounts as determined by the contractor are accounted for on an accumulative basis
!
Column C
Previously determined amounts are accounted for
!
15.3 AMOUNTS DUE TO THE CONTRACTOR
There are eight conditions for which the contractor is entitled to recovery from the subcontractor. These are:
▪ The first six (1.1.1-6) are grouped together as they all impact on the tax calculated on the certified n/s subcontract
value
▪ The remaining two items, default interest (1.2.1) and advance payment recoupment (1.2.2), are accounted for after tax
!
15.4 AMOUNTS DUE TO THE SUBCONTRACTOR
There are five conditions for which the subcontractor is entitled to recovery from the contractor. These are:
▪ Damages (2.1.1) and non-contract variations (2.1.2) are accounted for before tax
▪ {Compensatory interest (2.2.1) =discontinued}, default interest (2.2.2) and advance payments made
! These amounts are tax neutral and are accounted for after tax
!
15.5
▪
IMPORTANT NOTES
The n/s subcontract recovery statement must be issued simultaneously with each n/s subcontractor’s payment
advice
▪ All recovery amounts exclude tax as this is dealt with in the n/s subcontractor’s payment advice
▪ Each item to be recovered is identified by a n/s subcontractor’s payment advice location reference with only the
!!
See Page 66
!!
!!
!!
!!
!!
!!
!!
!!
!!
!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
61
®
Subcontractor's Recovery Statement Advice No: PA certificate 11
issued in terms of Clause 27.0 of the
N/S Subcontract Agreement Edition 6.1 © March 2014 Date of Advice: 201?-02-08
Contractor
Subontractor
N/S Works
Site
The following amounts, detailed in separate documents, are to be recovered in the stated Payment Advice
A B C
Payment Certificate/payment due 11 201?-02-21 TOTAL TO BE LESS PREVIOUS RECOVERY
RECOVERED RECOVERY THIS PERIOD
1.0 AMOUNTS DUE TO THE CONTRACTOR
!!
16.0 PAYMENT ADVICE STATEMENT (NSSA)
!
!
16.1 PURPOSE
The amount of money that is due and payable by the contractor to the subcontractor or vice versa is ‘certified’ in a n/s
subcontractor’s payment advice issued by the contractor. Liquidity is conferred where the contractor (the debtor)
acknowledges his indebtedness to the subcontractor for a determined sum of money. The wording must be correct –
!
specifying the contractor and the subcontractor and the payment amount that is due to the subcontractor
Payment due to the employer is provided for in the agreement and the payment certificate form but is not a liquid
!
document!
!
16.2 THE PAYMENT ADVICE STATEMENT
Column A Contract Sum The n/s subcontract sum in terms of the agreement remains fixed for the duration of
! the subcontract
Column B Current Contract Value The totals of Columns A and B give an immediate comparison between the n/s
subcontract sum and the n/s subcontract value at the date of issue of the n/s
!
Column C Current Valuation
subcontractor’s payment advice.
The contractor incorporates the valuation provided by the principal agent in the
!
Column D Current Certification
statement issued in terms of the Principal Building Agreement
The contractor certifies the current valuation amounts and items of expense and/or loss
!
1.0 Value of work executed
detailed in the n/s subcontract recovery statement as well as tax on applicable items
The contractor incorporates the valuation provided by the principal agent in the
statement issued in terms of the Principal Building Agreement. The contractor has no
!
2.1-2 Materials on and off site
authority to reduce or vary such valuation
The subcontractor’s materials on and off site are to be included where they are
!
3.0
4.0
SUB TOTAL
Security adjustment Applies only where the subcontractor has chosen the security (fixed) to which
payment reduction provisions apply, or is in default by not providing such security and
the contractor elects to apply the payment reduction option
!
5.0
6.0
Net subcontract sum The amount reflected in Column B is the same as the amount in Column A
Authorised adjustments … Authorised adjustments determined by the principal agent to date are included [B 6.0],
!
7.0 Provision for ‘contract price adjustments’ included in [A 7.0], updated in [B7.0], if included in a valuation [C+D 7.0]
!
8.0 GROSS AMOUNT CERTIFIED … in [D 8.0]
!
9.0
10.0
Less Amount certified in the previous payment advice statement … [D 9.0]
NET AMOUNT CERTIFIED The net resultant portion of the n/s subcontract value certified in this n/s
!
11.1-2 Recovery Statement Amounts that affect the subcontractor’s income or expenditure, that are tax neutral
!
12.0
13.0
SUB TOTAL
Tax
The summed total of the previous items
The subtotal 12.0 is pre-tax. The tax percentage must be filled in and calculated
!
14.1-2 Recovery Statement
15.0 TOTAL
Amounts that do not attract tax = interest and advance payment amounts.
The total of the n/s subcontract sum and the comparative variable current n/s
! subcontract value
!
16.0
17.0
CERTIFIED AMOUNT DUE FOR PAYMENT Identify the currency / receiving party / amount due
Contract sum execution Where the subcontractor has provided a Guarantee for Construction (variable) the
percentage of the n/s subcontract sum that has been executed must be determined.
!
The completion status must be indicated as it affects all the security options
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
63
®
Subcontractor's Payment Advice Advice No: PA certificate 11
Issued in terms of Clause 25.3 of the
N/S Subcontract Agreement Edition 6.1 © March 2014 Date: 201?-02-08
Contractor
Subcontractor
N/S Works
Site
4.0 Security Adjustments [14.7.1, 25.3.3] no / if yes, percentage? 90.0 % (2 000.00) 18 000.00
9.0 Less Previous gross amount certified [25.3.6] (excluding tax) 0.00
11.1 Less Expense and loss [Recovery Statement 1.1] (excluding tax) (2 500.00)
11.2 Add Amounts due [Recovery Statement 2.1] (excluding tax) 12 000.00
12.0 SUB TOTAL 600 000.00 600 000.00 (excluding tax) 27 500.00
14.1 Less Interest / Advance Payment Recoupment [Recovery Statement 1.2] (excluding tax) 0.00
14.2 Add Interest / Advance Payment Made [Recovery Statement 2.2] (excluding tax) 150 000.00
16.0 Currency ZAR AMOUNT DUE FOR PAYMENT to the subcontractor / contractor Subcontractor 181 350.00
17.0 N/S Contract sum execution % (Security for Construction- variable - only) (D8.0/A12.0*100) 3.0 %
Contractor completion status < 50% ✔ > 50% ✖ Practical Completion ✖ Final Completion ✖
!!
17.0 PAYMENT CERTIFICATE (MWA)
!
!
17.1 PURPOSE
An amount of money that is due and payable by the employer to the contractor or vice versa is ‘certified’ in a payment
certificate issued by the principal agent. Liquidity is conferred where the employer (the debtor), by the signature of the
principal agent, acknowledges his indebtedness to the contractor for a determined sum of money. The wording must be
correct – specifying the employer, principal agent and the contractor and the payment amount that is due to the
!
contractor
Payment due to the employer is provided for in the agreement and the payment certificate form but is not a liquid
!
document!
!
17.2 THE PAYMENT CERTIFICATE
!
Column A Contract Sum The contract sum i.t.o. the agreement remains fixed for the duration of the contract
Column B Current Contract Value The totals of Columns A and B give an immediate comparison between the contract
!
Column C Current Valuation
The principal agent certifies the current valuation amounts and items of expense
!
1.0 Value of work executed
and/or loss {detailed in the recovery statement} as well as tax on the applicable items
The valuation must be “a reasonable estimate of the work executed” without it being
“work satisfactorily completed”. The principal agent must act impartiality {to verify (or
!
2.1-2 Materials on and off site
modify) the quantity surveyor’s valuation before certifying such amount}
Materials and goods on and off site may be included in the valuation
Note: Projects financed by a financial institution generally exclude payment of unfixed
materials leaving the employer short of money to make payment of an issued payment
certificate. The principal agent must record in the contract data if unfixed materials
(on or off site) will be paid, or not, where included in a payment certificate
A Guarantee for Deposit may cover some such materials and will reduce the
employer’s additional risk {see Recovery Statement}
!
3.0
4.0
SUBTOTAL
Security adjustment
The total of the previous items
Applies where the contractor is in default by not providing a specified security and the
!
employer elects to apply the payment reduction option
!
5.0 Net contract sum The amount reflected in Column B is the same as the amount in Column A
!
6.0 Authorised adjustments … Authorised adjustments to date are included [B 6.0], excluding anticipated adjustments
!
7.0 TOTAL AMOUNT CERTIFIED … in [D 7.0]
!
8.0 Less Amount certified in the previous payment certificate … [D 8.0]
!
9.0 NET AMOUNT CERTIFIED The net resultant portion of the contract value certified in this payment certificate
!
10.1-3 (Recovery Statement) Amounts that affect the contractor’s income or expenditure, that are tax neutral
!
11.0
12.0
SUB TOTAL
Tax
The summed total of the previous items
The subtotal 11.0 is pre-tax. The tax percentage must be filled in and calculated
!
13.1-4 (Recovery Statement)
If this subtotal is negative, tax will not apply
Amounts that do not attract tax = interest and advance payment amounts.
! Any deposit paid by the employer for the purchase of materials must also be included
!
14.0 TOTAL The total of the contract sum and the comparative variable current contract value
!
15.0
16.0
CERTIFIED AMOUNT DUE FOR PAYMENT Identify the currency / receiving party / amount due
Contract sum execution Where the contractor has provided a Guarantee for Construction (variable) the
percentage of the contract sum that has been executed must be determined.
!!
The completion status must be indicated as it affects all the security options
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
65
®
Certificate for Payment Certificate No: 3
Employer
Contractor
Works
Site
Valuation Date 201?-02-05 Issue Date 201?-02-07 Payment due date 201?-02-21
A B C D
CONTRACT SUM CURRENT CURRENT CURRENT
CONTRACT VALUE VALUATION CERTIFICATION
4.0 Security adjustments applicable [8.3.1; 19.3.3] If applicable, state % 4.0 % (20 400.00) 489 600.00
8.0 Less Previous amount certified [19.3.5] (excluding tax) (302 100.00)
10.1 Less Expense and loss payable to the employer [Recovery Statement 1.1] (excluding tax) (30 500.00)
10.2 Less Penalties levied and payable to the employer [Recovery Statement 1.2] (excluding tax) 0.00
10.3 Add Damages payable to the contractor [Recovery Statement 2.2] (excluding tax) 0.00
11.0 SUB TOTAL 840 000.00 900 000.00 (excluding tax) 157 000.00
12.0 Add Tax on 11.0 [25.3.8] 14 % 117 600.00 126 000.00 21 980.00
13.1 Less Recoupment from contractor of a deposit [Recovery Statement 1.3.2] (excluding tax) 0.00
13.2 Add Default interest payable to the contractor [Recovery Statement 2.2.1] (excluding tax) 0.00
13.3 Add Deposit amounts paid to the contractor [Recovery Statement 2.1.2] (excluding tax) 0.00
13.4 Add Tax exempt items (salvaged materials used in the works) [18.3.10] (excluding tax) 0.00
15.0 Currency ZAR CERTIFIED AMOUNT DUE FOR PAYMENT to the Contractor / Employer Contractor 178 980.0
16.0 Contract sum execution (Variable construction guarantee only) (C3.0/A11.0*100) 60.7 %
Security status
Mark each box as appropriate < 50% ✖ > 50% ✔ Practical Completion ✖ Final Completion ✖
!!
18.0 PROMPT PAYMENT regulations + application
!
!
18.1 BACKGROUND
In South Africa the Construction Industry Development Board (CIDB) submitted draft regulations during 2012 to
the Minister of Public Works consisting, amongst others, of Part IV C entitled “Prompt Payment” and Part IV D
entitled “Adjudication” including a standard of adjudication (the “standard”) advising that the draft regulations be
promulgated by the Minister as regulations in terms of the Section 33(i) of the CIDB Act 38 of 2000
!
18.2 PURPOSE
!
To ensure that all contractors get paid by the due date for work completed
!
Applies in the relationship between the contractor as employer and each subcontractor
!
Payment terms are recorded in the agreement and /or the contract data between the parties
Reasons for not paying the full amount in the stipulated time period may include:
▪ Quality of work is disputed
!
▪ Quantity of work completed is disputed
Note: An interim payment certificate is a fair approximation of the quantum of work produced but does not
warrant acceptance of the quality of such work on the date of issue by the principal agent of an interim payment
!
certificate
! terminate the works forthwith on expiry of such notice …and be entitled to recover damages
!
The same applies in the relationship between contractor as employer and each subcontractor
!! !
!!
!!
!!
!!
!!
!!
!!
!
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
67
The Guarantee for Advance Payment (a Guarantee for Deposit in the MWA) is a financial instrument to enable the
employer to make an advance payment (a loan) to the contractor or the subcontractor for materials or equipment to be
ordered in advance of their requirement on site. Such goods can not be included in a payment certificate as “value of
!
work executed”
!
Some form of collateral will be required by the institution providing such a security
!
A “transfer of ownership” may be considered to be a legally unenforceable substitute
!
19.2
19.2.1
ADMINISTRATION
All advance payment (deposit) transactions are dealt with in the applicable recovery statement (Minor Works
!
19.2.2
generally in the payment certificate)
No “direct payments” or recoupment of an advance payment (deposit) may bypass the payment certificate to
!
19.2.3
ensure that all financial transactions pertaining to the agreement are accounted for in the various payment forms
Interest or other charges related to the Guarantee for Advance Payment (deposit) must be agreed directly
!
19.2.4
between the parties --- They are not part of the contract sum nor the contract value!
A Guarantee for Advance Payment (deposit) should not be demanded for materials off site that adequately fall
! within the provisions of a Guarantee for Construction provided by the contractor or n/s subcontractor
!
19.2.5 ‘Advance payments’ (deposit) are a form of loan and therefore do not attract tax
!
19.2.6
19.2.7
Note: The end Current Certification balances with the end Total Net Payment
The employer is entitled to call up the Guarantee for Advance Payment (deposit) should the contractor or a
!!
19.2.8 Advance Payment Life Cycle Table
The following tables set out the typical cash flow of an advance payment to either or both the contractor and a
!!
subcontractor
!!
!
Payment Certificate M1 M2 M3 M4 M5 M6 M7 M8 Total
Contract
Valuation: Contractor 40 000 120 000 280 000 500 000 800 000 1 200 000 1 700 000 2 000 000 Value
N/S 0 0 20 000 70 000 240 000 480 000 570 000 600 000
Certified: Contractor 0 -40 000 -120 000 -280 000 -500 000 -800 000 -1 200 000 -1 700 000
N/S 0 0 0 -20 000 -70 000 -240 000 -480 000 -570 000
Current certification 40 000 80 000 180 000 270 000 470 000 640 000 590 000 330 000 2 600 000
Add Tax at 14% 5 600 11 200 25 200 37 800 65 800 89 600 82 600 46 200 364 000
Gross certification 45 600 91 200 205 200 307 800 535 800 729 600 672 600 376 200 2 964 000
Advance/ recoupment C 200 000 0 -40 000 -40 000 -40 000 -40 000 -40 000 0
Advance/recoupment N/S 0 0 150 000 0 -50 000 -50 000 -50 000 0
Total net payments 245 600 91 200 315 200 267 800 445 800 639 600 582 600 376 200 2 964 000
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
68
For use with JBCC® Principal Building Agreement state edition /date
GUARANTOR
DETAILS
Guarantor:
Physical address;
Employer:
Recipient:
Contractor:
Contractor:
Principal Agent:
Works:
Site:
AGREEMENT DETAILS
Principal Agent issues JBCC® format Interim Payment Certificates, interim Recovery Statements
1.1 The particulars of the recoupment of the guaranteed Advance Payment sum are set out in the following schedule:-‐
1.2 The Guarantor’s liability shall be limited to the outstanding diminishing amounts of the guaranteed Advance Payment sum as
follows:-‐
1.2.1 The guaranteed Advance Payment sum on receipt thereof by the Recipient
1.2.2 The full outstanding balance after the deduction of each recoupment made in terms of the monthly payment certificate as
stated
in
1.1
1.2.3 After the deduction of the last scheduled recoupment payment or on settlement of the full outstanding balance this
Guarantee
for
Advance
Payment
shall
expire
2.1 Any reference in this Guarantee for Advance Payment to the Agreement is made for the purpose of convenience and shall not be
construed
as
any
intention
to
create
an
accessory
obligation
or
any
intention
to
create
a
suretyship
2.2 Its
obligation
under
this
Guarantee
for
Advance
Payment
is
restricted
to
the
payment
of
money
69
2.3 Reference to a recovery statement or a Payment Certificate shall mean such certificate issued by the Principal Agent
3.0 Subject to the Guarantor’s maximum liability referred to in 1.0 the Guarantor undertakes to pay the Employer the sum certified on receipt
of
the
documents
identified
in
3.1
to
3.3:-‐
3.1 A copy of a first written demand notice issued by the Employer to the Recipient stating that payment of a sum certified by the
Principal Agent has not been made in terms of the Agreement and failing such payment within seven (7) calendar days, the
Employer
intends
to
call
upon
the
Guarantor
to
make
payment
in
terms
of
3.2
3.2 A first written demand notice issued by the Employer to the Guarantor at the Guarantor’s physical address with a copy to the
Recipient stating that a period of seven (7) calendar days has elapsed since the issue of the first written demand notice in terms of
3.1 and that the sum certified has not been paid to date. The Employer herewith calls up this Guarantee for Advance Payment and
demands
payment
of
the
sum
certified
from
the
Guarantor
3.3 A copy of the recovery statement and payment certificate which entitles the Employer to receive payment in terms of the
Agreement
of
the
sum
certified
in
3.0
4.0 Subject to the Guarantor’s maximum liability referred to in 1.0 the Guarantor undertakes to pay the Employer the guaranteed Advance
Payment sum or the full outstanding balance upon receipt of a first written demand notice from the Employer to the Guarantor at the
Guarantor's
physical
address
calling
up
this
Guarantee
for
Advance
Payment
stating
that:-‐
4.1 The Agreement has been terminated due to the Recipient's default and that the Guarantee for Advance Payment is called up in
terms
of
4.0.
The
demand
notice
shall
enclose
a
copy
of
the
notice
of
termination;
or
4.2 A provisional sequestration or liquidation court order has been granted against the Recipient and that the Guarantee for Advance
Payment
is
called
up
in
terms
of
4.0.
The
demand
notice
shall
enclose
a
copy
of
the
court
order
5.0 The
aggregate
amount
of
payments
to
be
made
by
the
Guarantor
in
terms
of
3.0
and
4.0
shall
not
exceed
the
Guarantor's
maximum
liability
in
terms
of
1.0
6.0 Payment by the Guarantor in terms of 3.0 or 4.0 shall be made within seven (7) calendar days on receipt of the first written demand notice
to
the
Guarantor
7.0 The Employer shall have the absolute right to arrange his affairs with the Recipient in any manner which the Employer deems fit and the
Guarantor shall not have the right to claim his release from this Guarantee for Advance Payment on account of any conduct alleged to be
prejudicial
to
the
Guarantor
8.0 The Guarantor chooses the physical address stated above for all transactions in connection with this Security
9.0 This Guarantee for Advance Payment is neither negotiable nor transferable and shall expire upon payment of the final payment certificate
in terms of the Agreement or on payment in full of the guaranteed Advanced Payment Sum or on the expiry date of the Security, whichever
is the earlier, whereafter no claims will be considered by the Guarantor. The original Guarantee for Advance Payment form shall be
returned
to
the
Guarantor
after
it
has
expired
10.0 This Guarantee for Advance Payment, with the required demand notices in terms of 3.0 or 4.0, shall be regarded as a liquid document for
the
purpose
of
obtaining
a
court
order
Witness Witness
For use with the JBCC® Minor Works Agreement state edition /date
GUARANTOR
DETAILS
Guarantor:
Physical address:
Employer:
Recipient:
Contractor / Subcontractor:
Principal Agent:
Works:
Site:
AGREEMENT
DETAILS
Principal
Agent
issues JBCC®
format
Payment
Certificate,
Recovery
Statement
1.1 The particulars of the recoupment of the guaranteed deposit amount are set out in the following schedule:
1.2 The Guarantor’s liability shall be limited to the outstanding diminishing amounts of the guaranteed deposit amount as follows:
1.2.1 The guaranteed deposit amount on receipt thereof by the Recipient
1.2.2 The full outstanding balance after the deduction of each recoupment made in terms of the monthly payment certificate as
stated
in
1.1
1.2.3 After the deduction of the last scheduled recoupment payment or on settlement of the full outstanding balance this MWA
Guarantee
for
Deposit
shall
expire
2.1 Any reference in this Guarantee for Deposit to the Agreement is made for the purpose of convenience and shall not be construed as
any
intention
to
create
an
accessory
obligation
or
any
intention
to
create
a
suretyship
2.2 Its obligation under this MWA Guarantee for Deposit is restricted to the payment of money
2.3 Reference
to
a
recovery
statement
or
a
Payment
Certificate
shall
mean
such
certificate
issued
by
the
Principal
Agent
71
3.0 Subject to the Guarantor’s maximum liability referred to in 1.0 the Guarantor hereby undertakes to pay the Employer the sum certified
upon
receipt
of
the
documents
identified
in
3.1
to
3.3:-‐
3.1 A copy of a first written demand notice issued by the Employer to the Recipient stating that payment of a sum certified by the
Principal Agent has not been made in terms of the Agreement and failing such payment within seven (7) calendar days, the
Employer
intends
to
call
upon
the
Guarantor
to
make
payment
in
terms
of
3.2
3.2 A first written demand notice issued by the Employer to the Guarantor at the Guarantor’s physical address with a copy to the
Recipient stating that a period of seven (7) calendar days has elapsed since the issue of the first written demand notice in terms of
3.1 and that the sum certified has still not been paid to date. The Employer herewith calls up this Guarantee for Deposit and
demands
payment
of
the
sum
certified
from
the
Guarantor
3.3 A copy of the recovery statement and payment certificate which entitles the Employer to receive payment in terms of the
Agreement
of
the
sum
certified
in
3.0
4.0 Subject to the Guarantor’s maximum liability referred to in 1.0 the Guarantor undertakes to pay the Employer the guaranteed deposit sum
or the full outstanding balance upon receipt of a first written demand notice from the Employer to the Guarantor at the Guarantor's
physical
address
calling
up
this
MWA
Guarantee
for
Deposit
stating
that:-‐
4.1 The Agreement has been terminated due to the Recipient's default and that the MWA Guarantee for Deposit is called up in terms of
4.0.
The
demand
shall
enclose
a
copy
of
the
notice
of
termination;
or
4.2 A provisional sequestration or liquidation court order has been granted against the Recipient and that the MWA Guarantee for
Deposit
is
called
up
in
terms
of
4.0.
The
demand
shall
enclose
a
copy
of
the
court
order
5.0 The
aggregate
amount
of
payments
to
be
made
by
the
Guarantor
in
terms
of
3.0
and
4.0
shall
not
exceed
the
Guarantor's
maximum
liability
in
terms
of
1.0
6.0 Payment by the Guarantor in terms of 3.0 or 4.0 shall be made within seven (7) calendar days upon receipt of the first written demand
notice
to
the
Guarantor
7.0 The Employer shall have the absolute right to arrange his affairs with the Recipient in any manner which the Employer deems fit and the
Guarantor shall not have the right to claim his release from this MWA Guarantee for Deposit on account of any conduct alleged to be
prejudicial
to
the
Guarantor
8.0 The Guarantor chooses the physical address stated above for all transactions in connection with this Security
9.0 This MWA Guarantee for Deposit is neither negotiable nor transferable and shall expire upon payment of the final payment certificate in
terms of the Agreement or on payment in full of the guaranteed deposit amount or on the expiry date of the Security, whichever is the
earlier, whereafter no claims will be considered by the Guarantor. The original MWA Guarantee for Deposit form shall be returned to the
Guarantor
after
it
has
expired
10.0 This MWA Guarantee for Deposit, with the required demand notices in terms of 3.0 or 4.0, shall be regarded as a liquid document for the
purpose
of
obtaining
a
court
order
Witness Witness
!
Manual and the Work Groups Composition and weighting of sub-indices
! The indices are calculated and compiled by Statistics SA and are available from their webpage free of charge:-
!
www.statssa.gov.za/publications/mystats.asp?myfavpubl=1&myfavpubln=P0151
! The weighting of the indices are also useful when analysing unit rates
! Io = the value of the index applicable to such work group for the base month
The formula is applied to the net amount certified for every workgroup. The net amount is determined by deducting the
amount previously certified from the accumulative amount for the current month for each workgroup. The base month index
(Io) remains constant throughout the contract for each workgroup. The only time where this would not be the case is when
work is undertaken at a different time than that of the initial tender. An example would be an item that was included in the
tender as a provisional sum and that is tendered at a later stage than the main contract. The current month index (Ie) moves
!
along month by month according to the date of the certificate
The format according to which the escalation is calculated resembles that of the detail of the certificate and also starts off
with the cumulative total for each workgroup less the amount previously certified to obtain the amount that needs to be
adjusted. It is important to realise that the result arrived at is no longer a cumulative amount and therefore the adjustments
of all the certificates need to be added together to obtain a cumulative amount for inclusion in the valuation
!
The indices are obtained from the P0151 publication and the monthly indices and inserted into the sheet as illustrated below;
Assume the following:- Tender date: November 2009 Date of Certificate no 1: January 2010
ESCALATION CALCULATIONS
PROJECT: NEW WAREHOUSE
CERTIFICATE NO: CERTIFICATE NO. 1 (ONE)
DATE: 20 JANUARY 2010
Note that the adjustment for workgroup 114 reinforcement is negative. This indicates the cost of reinforcement
!
has decreased since the date of tender. The next certificate would be as follows
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014
73
ESCALATION CALCULATIONS
PROJECT: NEW WAREHOUSE
CERTIFICATE NO: CERTIFICATE NO. 2 (TWO)
DATE: 20 FEBRUARY 2010
There may be instances where the value of work is based on information that does not stem from the same time as the
tender - for instance items that were included in the tender documentation as cost price items and that are adjusted to the
correct cost according to invoices that are to be submitted as soon as the work the pertain to is executed. Such an event can
be handled in two ways - either these values can be grouped together in a total that is not subject to escalation, or the rates
may be de-escalated back to the same base month as the tender and then included with the other work and escalated
together with the other work. To de-escalate a value the inverse of the formula must be applied
1 .
Base index (Io) for November 2009 for tiling is 360.4
! = R 9 981
It is important during the final account stage to double check that the indices used to calculate the fluctuations are correct in
all the certificates. The indices prepared by Statistics SA are issued on a monthly basis. When the CPAP is calculated and
the indices for the current month are not available the latest available indices are used. Should any of the indices be
incorrect the specific month’s calculations must be redone as well as all subsequent calculations to correct the cumulative
!!
value for the CPAP
©JBCC® Guide to Completion, Valuation, Certification and Payment - Edition 6.1, March 2014